Line 11: | Line 11: |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 50: | Line 50: |
2017/3/21(Thur.) * Remote participants by eZuce: Kimura, Miyoki |
=== 2018/4/2(Mon.) === * Remote participants by eZuce: Enomoto |
Line 56: | Line 55: |
* IFO: *Izumi, Miyamoto, Eleonora * Daily Beam check was confirmed at the REFL port yesterday evening. * Measurement of BS sensing and driving matrix and diagonalizarion of them. * This method should be automatically performed, but still we needs some work to be done. * T of ETMY was checked and improved. We need the same work for L. * LSC screen has been updated. * AOS: *Akutsu, Yokogawa * Green light reached to ETMY on Tuesday. Misalignment was ~100urad order. * IMC, CAL: Yokozawa, Yamamoto, Miyamoto * IMC Transmitted light is too low. Alignment should be checked. * Injection to MCE for calibration was tested. * VAC: Uchiyama * Vacuum level of X arm is degraded. |
* ETMX: *Ushiba * Confirmed the returned beam at REFL * Calibration of OpLev is on going (mostly finished) * Start Characterization * ETMY: *Miyamoto * Damping is working well. Less than 2urad RMS. * BS: *Enomoto * Two different problems identified * Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone * Glitches -> Looks like the same problem as ETMY: DAC output goes to zero * PCal: Binhua * Aligned the beam within the PCal module * ETMX camera: Yokozawa * Ready but not installed * TMS: no one to report |
Line 78: | Line 78: |
* Alignment: *Izumi * ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX. * Needs power supply for QPD. * AOS: *Akutsu, Yokogawa * TMS alignment at ETMY. * Cooling will start at 10AM. |
* ETMX: *Ushiba, Miyamoto * Start Characterization * BS: Enomoto * Check the glitches over the weekend * PCal: Binhua * Measure PCal transfer functions * ETMX Camera: Yokozawa * Set up necessary components to take high frame rate pictures |
Line 88: | Line 91: |
* [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F. * [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F. * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F. |
* [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F ==== Work plan (*:responsible person) ==== * ETMX: *Ushiba, Takahashi * Beam will be aligned more precisely with aligned IR. * CAL: *Yamamoto * CAL model is tested using iMC. * Camera: Yokozawa * EX camera takes every one hour. It is necessary 1 sec picture in the weekend. ==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 94: | Line 131: |
* week of 3/19 * TMS alignment using green light at ETMY. * 3/21~: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa * week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Issues |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * 4/5 12:30 at fan hut: Meeting before pump down 1 * week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC ==== Issues ==== * BS: DAC had some glitches but if DAC is off, no glitch was found. |
Line 117: | Line 155: |
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/2(Mon.)
* Remote participants by eZuce: Enomoto
Report of work (*:responsible person)
* ETMX: *Ushiba
- Confirmed the returned beam at REFL
Calibration of OpLev is on going (mostly finished)
- Start Characterization
* ETMY: *Miyamoto
- Damping is working well. Less than 2urad RMS.
* BS: *Enomoto
- Two different problems identified
Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone
Glitches -> Looks like the same problem as ETMY: DAC output goes to zero
* PCal: Binhua
- Aligned the beam within the PCal module
* ETMX camera: Yokozawa
- Ready but not installed
* TMS: no one to report
Work plan (*:responsible person)
* ETMX: *Ushiba, Miyamoto
- Start Characterization
* BS: Enomoto
- Check the glitches over the weekend
* PCal: Binhua
- Measure PCal transfer functions
* ETMX Camera: Yokozawa
- Set up necessary components to take high frame rate pictures
Laser hazard
* [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Work plan (*:responsible person)
- ETMX: *Ushiba, Takahashi
- Beam will be aligned more precisely with aligned IR.
- CAL: *Yamamoto
- CAL model is tested using iMC.
- Camera: Yokozawa
- EX camera takes every one hour. It is necessary 1 sec picture in the weekend.
Laser hazard
- [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- 4/5 12:30 at fan hut: Meeting before pump down 1
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC
Issues
- BS: DAC had some glitches but if DAC is off, no glitch was found.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)