10003
Comment:
|
10223
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 51: | Line 51: |
2017/3/23(Fri.) | 2017/3/27(Tue.) |
Line 53: | Line 53: |
* Remote participants by eZuce: Izumi, Miyoki | * Remote participants by eZuce: Yokozawa |
Line 57: | Line 57: |
* IFO: *Izumi, Miyamoto, Eleonora * BS had some difficulty to close control loop of Y of oplev. * T of ETMY control loop was closed. * Circuits of baffle PD are being prepared. |
* Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi + CRY * All are free except for Pre-isolator. * Cable connections seemed to be fine. * First contact will be removed. |
Line 62: | Line 62: |
* AOS: *Akutsu, Yokogawa * Green team succeeded to reach green and IR to ETMY. * BRT alignment is going on yesterday and today. * Oplev is being prepared at EXC. |
* Oplev at ETMX: Akutsu * Preparation is almost done. |
Line 67: | Line 65: |
* Camera: Yokozawa, Yamamoto, Miyamoto * X end camera will be recovered. * IYC cooling started. |
* BS: *Enomoto * Oplev servo servo oscillation was fixed by fixing channel assignment on digital system by restarting RT model. |
Line 74: | Line 71: |
* Alignment: *Eleonora, Miyamoto * BS diagonalization * ETMY damping |
* Camera: *Inoue, Yokozawa * ETMX PD will be removed. * GigE camera will be removed today and placed next week. |
Line 78: | Line 75: |
* AOS: *Akutsu, Yokogawa * BRT alignment is going on yesterday and today. * Oplev work at EXC. |
* Oplev at ETMX: *Akutsu, Simon * Once first contact is removed, opelev will be aligned. |
Line 82: | Line 78: |
* BRT: *Akutsu, Yokogawa, Sugimoto, Nagano, Yamamoto * Alignment |
|
Line 86: | Line 84: |
* Green: around PR2 | * Green: PR2 |
Line 88: | Line 86: |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F. * Green: Xend 1F. |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 92: | Line 90: |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F. * Green: Xend 1F. |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 97: | Line 95: |
* week of 3/19 * TMS alignment using green light at ETMY. * 3/21~: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa |
|
Line 104: | Line 97: |
* Rough alignment of ETMX is planed using IR. | |
Line 106: | Line 98: |
* Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa * week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * week of 4/9 |
|
Line 120: | Line 122: |
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/3/27(Tue.)
- Remote participants by eZuce: Yokozawa
Report of work (*:responsible person)
- Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi + CRY
- All are free except for Pre-isolator.
- Cable connections seemed to be fine.
- First contact will be removed.
- Oplev at ETMX: Akutsu
- Preparation is almost done.
- BS: *Enomoto
- Oplev servo servo oscillation was fixed by fixing channel assignment on digital system by restarting RT model.
Work plan (*:responsible person)
- Camera: *Inoue, Yokozawa
- ETMX PD will be removed.
- GigE camera will be removed today and placed next week.
- Oplev at ETMX: *Akutsu, Simon
- Once first contact is removed, opelev will be aligned.
- BRT: *Akutsu, Yokogawa, Sugimoto, Nagano, Yamamoto
- Alignment
Laser hazard
- [AM]
- IR: PSL
- Green: PR2
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 3/26
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- 3/27 EX PD will be removed.: *Yokozawa
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools