Differences between revisions 356 and 385 (spanning 29 versions)
Revision 356 as of 2018-03-26 09:29:27
Size: 9989
Comment:
Revision 385 as of 2018-04-13 09:01:16
Size: 10701
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/20 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}}
2017/4/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}}
Line 50: Line 50:
=== 2018/4/13(Fri.) ===
Line 51: Line 52:
2017/3/26(Mon.)

 
* Remote participants by eZuce: Shoda
* Remote participants by eZuce: Miyoki
Line 56: Line 55:
 * IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
  * Last night, beam was lost caused by a shit at oplev. Installing a view port might introduce the shift on oplev yaw.
Line 57: Line 58:
 * ETMY: *Miyamoto
  * Mirror motion has been suppressed to ~2urad. Requirement is 1urad, pretty close!

 * BS: *Eleonora, Yamamoto
  * DAQ had trouble. Channel number is assigned to wrong channel, that was because RT model was built and installed but not restarted, and DAQ was restarted independently.

 * Camera: *Inoue
  * X end camera was recovered, needs PC tuning.

 * Camera: Yokozawa, Yamamoto, Miyamoto
  * X end camera will be recovered.
  * IYC cooling started.
 * VAC: *Kimura
  * View port for oplev at ETMX was attached yesterday's afternoon.
  * All the preparation was done and the door of EXC was closed.
  * Damping of ETMX will be tested with HPCD.
Line 72: Line 64:
 * IFO: damping work or others.
Line 73: Line 66:
 * BS: *Enomonot
  * Once oplev servo servo was engaged, yaw oscillation started. It will be investigated this week.

 * AOS: *Akutsu, Yokogawa
  * BRT alignment is still going on.
  * Oplev work at EXC. It will be available early this week.
 * VAC: *Kimura
  * Pumping down will start ~10am today.
Line 83: Line 72:
  * IR: PSL
  * Green: none
  * IR: PSL, Yend 1F
  * Green: off
Line 86: Line 75:
  * IR: PSL
  * Green: none
  * IR: Upstream SR2-3 line, Yend 1F
  * Green: off
Line 90: Line 79:
  * IR: PSL
  * Green: none
  * IR: Upstream SR2-3 line, Yend 1F
  * Green: off
Line 95: Line 85:
 * week of 4/9
  * 4/11 12:30 at fan hut: Meeting before pump down 2.
  * Closing EXC.
  * Some controls for Michelson.
  * 4/13 morning: Pump down starts.
Line 96: Line 91:
 * week of 3/26
  * Connection of cable at ETMX and starting control.
  * Rough alignment of ETMX using IR.
   * EX PD will be removed.: *Yokozawa
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
 * week of 4/16
  * Michelson control.
  * Leak check.
  * Opening the last gate valve.
Line 102: Line 96:
 * week of 4/2
  * ETMY damping.
  * Rough alignment of ETMX using IR, and control MICH if can.
 * week of 4/23
  * Operation
Line 106: Line 99:
 * week of 4/9 ==== Issues ====
Line 108: Line 101:

 * Issues
Line 122: Line 113:
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
Line 148: Line 142:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])  * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/10 updated KAGRA/Commissioning/Commissioning_schedule_20180410.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/13(Fri.)

* Remote participants by eZuce: Miyoki

Report of work (*:responsible person)

  • IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
    • Last night, beam was lost caused by a shit at oplev. Installing a view port might introduce the shift on oplev yaw.
  • VAC: *Kimura
    • View port for oplev at ETMX was attached yesterday's afternoon.
    • All the preparation was done and the door of EXC was closed.
    • Damping of ETMX will be tested with HPCD.

Work plan (*:responsible person)

  • IFO: damping work or others.
  • VAC: *Kimura
    • Pumping down will start ~10am today.

Laser hazard

  • [AM]
    • IR: PSL, Yend 1F
    • Green: off
  • [PM]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off
  • [night]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off

Weekly

  • week of 4/9
    • 4/11 12:30 at fan hut: Meeting before pump down 2.
    • Closing EXC.
    • Some controls for Michelson.
    • 4/13 morning: Pump down starts.
  • week of 4/16
    • Michelson control.
    • Leak check.
    • Opening the last gate valve.
  • week of 4/23
    • Operation

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)