Line 11: | Line 11: |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/25(Wed.) === | |
Line 51: | Line 52: |
2017/3/27(Tue.) * Remote participants by eZuce: Yokozawa |
* Remote participants by eZuce: None |
Line 57: | Line 56: |
* Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi + CRY * All are free except for Pre-isolator. * Cable connections seemed to be fine. * First contact will be removed. |
* IFO: *Izumi, Enomoto, Nakano + many * Michelson lock lasted ~40min with Guardian. * ETMX had some drift. It may cause lock down. |
Line 62: | Line 60: |
* Oplev at ETMX: Akutsu * Preparation is almost done. |
* Modulation frequency was not tuned yet to iMC length. * Measurement of AM conversion can know the matching of mod. freq. to iMC length. |
Line 65: | Line 63: |
* BS: *Enomoto * Oplev servo servo oscillation was fixed by fixing channel assignment on digital system by restarting RT model. |
* PR3: Oplev has glitch. The laser source of oplev may be a cause. Needs fiber cleaner to exchange the laser. * BS: *Eleonora, Izumi, Arai * BS IM feed back was engaged. * Target crossover was originally 3Hz but actual crossover was limited up to ~0.1Hz, because 1.25Hz peak disturbed control. * Gain of some loops of oplev servo changed stronger. * CAL: *Yamamoto, Enomoto, Izumi * Optical measumremnt was measured. * Sensitivity is shown in the control room, being calculated from H(t). * Injection: *Miyamoto, Yokozawa * Noise budget: *Michimura, Enomoto * IOO: *Kokeyama, Enomoto * MCE trans was clipped. Output PSL was going down to bottom direction, and it was a cause of clipping. This clipping does not affect to IFO control. * ETMX: *Hasegawa, Nakano, Enomoto * ETMX has some drift for 10-20urad. * ETMY: *Nakano, *Shishido, Ushiba, Miyamoto * ETMY need L damping. * Gardian was implemented. |
Line 71: | Line 91: |
* Camera: *Inoue, Yokozawa * ETMX PD will be removed. * GigE camera will be removed today and placed next week. |
* BS: *Eleonora, Izumi, Arai * Opleve loop gains will change stronger. |
Line 75: | Line 94: |
* Oplev at ETMX: *Akutsu, Simon * Once first contact is removed, opelev will be aligned. |
* CAL: *Yamamoto, Enomoto, Izumi * Cal signal will be injected. |
Line 78: | Line 97: |
* BRT: *Akutsu, Yokogawa, Sugimoto, Nagano, Yamamoto * Alignment |
* IFO: *Izumi, Enomoto, Nakano + many * Measurement without locking morning, measurement with locking in the afternoon. |
Line 83: | Line 103: |
* IR: PSL * Green: PR2 |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 86: | Line 106: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 90: | Line 110: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 95: | Line 116: |
* week of 4/23 * Michelson control. * 4/28 Operation start |
|
Line 96: | Line 120: |
* week of 3/26 * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa * week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * week of 4/9 * Issues |
==== Issues ==== |
Line 122: | Line 133: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || |
|
Line 149: | Line 163: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/25(Wed.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto, Nakano + many
- Michelson lock lasted ~40min with Guardian.
- ETMX had some drift. It may cause lock down.
- Modulation frequency was not tuned yet to iMC length.
- Measurement of AM conversion can know the matching of mod. freq. to iMC length.
- PR3: Oplev has glitch. The laser source of oplev may be a cause. Needs fiber cleaner to exchange the laser.
- Michelson lock lasted ~40min with Guardian.
- BS: *Eleonora, Izumi, Arai
- BS IM feed back was engaged.
- Target crossover was originally 3Hz but actual crossover was limited up to ~0.1Hz, because 1.25Hz peak disturbed control.
- Gain of some loops of oplev servo changed stronger.
- BS IM feed back was engaged.
- CAL: *Yamamoto, Enomoto, Izumi
- Optical measumremnt was measured.
- Sensitivity is shown in the control room, being calculated from H(t).
- Injection: *Miyamoto, Yokozawa
- Noise budget: *Michimura, Enomoto
- IOO: *Kokeyama, Enomoto
- MCE trans was clipped. Output PSL was going down to bottom direction, and it was a cause of clipping. This clipping does not affect to IFO control.
- ETMX: *Hasegawa, Nakano, Enomoto
- ETMX has some drift for 10-20urad.
- ETMY: *Nakano, *Shishido, Ushiba, Miyamoto
- ETMY need L damping.
- Gardian was implemented.
Work plan (*:responsible person)
- BS: *Eleonora, Izumi, Arai
- Opleve loop gains will change stronger.
- CAL: *Yamamoto, Enomoto, Izumi
- Cal signal will be injected.
- IFO: *Izumi, Enomoto, Nakano + many
- Measurement without locking morning, measurement with locking in the afternoon.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/23
- Michelson control.
- 4/28 Operation start
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools