Line 11: | Line 11: |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 24: | Line 24: |
* Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 |
|
Line 50: | Line 39: |
=== 2018/4/28(Sat.) === | |
Line 51: | Line 41: |
2017/3/27(Tue.) * Remote participants by eZuce: Yokozawa |
* Remote participants by eZuce: None * 1st day of Phase 1 operation * OLG by |
Line 57: | Line 47: |
* Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi + CRY * All are free except for Pre-isolator. * Cable connections seemed to be fine. * First contact will be removed. |
* IFO: *Izumi, Enomoto + many * ETMY damping filter was back to what was best. Fluctuation is ~1urad. * ETMX damping filter changed a bit. Fluctuation is < 1urad. * BS alignment noise was improved around 10-30Hz 8 at most. * Gain bump can be seen around UGF of MICH. * Lock of the last night was ~1hour. Lock was lost because of L to oplev coupling seems to exist. |
Line 62: | Line 54: |
* Oplev at ETMX: Akutsu * Preparation is almost done. |
|
Line 65: | Line 55: |
* BS: *Enomoto * Oplev servo servo oscillation was fixed by fixing channel assignment on digital system by restarting RT model. |
* Camera: Yokozawa, Inoue * IYA camera could not see BS, because some clipping may exist. |
Line 68: | Line 58: |
* WAB: Akutsu * Heater off. * IYC: Tomaru * Cooler off. * Operaton: * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] is opened. |
|
Line 71: | Line 69: |
* Camera: *Inoue, Yokozawa * ETMX PD will be removed. * GigE camera will be removed today and placed next week. |
* CAL: Yamamoto * Optical gain measurement * Open loot TF. * Amplitude tuning for injection. * Sensitivity. * BS to MICH TF, if can. |
Line 75: | Line 76: |
* Oplev at ETMX: *Akutsu, Simon * Once first contact is removed, opelev will be aligned. |
* IFO: *Izumi, Enomoto + many * Higher BS oplev gain will be tried today by the gain switch on opec board or the gain setting on whitening board. |
Line 78: | Line 79: |
* BRT: *Akutsu, Yokogawa, Sugimoto, Nagano, Yamamoto * Alignment |
|
Line 83: | Line 82: |
* IR: PSL * Green: PR2 |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 86: | Line 85: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 90: | Line 89: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 95: | Line 95: |
* week of 4/23 * Michelson control. * 4/28 Operation start |
|
Line 96: | Line 99: |
* week of 3/26 * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa |
* week of 4/30 * Operation continues. |
Line 102: | Line 102: |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. |
==== Issues ==== |
Line 106: | Line 104: |
* week of 4/9 * Issues |
|
Line 122: | Line 116: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || |
|
Line 149: | Line 146: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/28(Sat.)
* Remote participants by eZuce: None * 1st day of Phase 1 operation
- OLG by
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto + many
- ETMY damping filter was back to what was best. Fluctuation is ~1urad.
ETMX damping filter changed a bit. Fluctuation is < 1urad.
- BS alignment noise was improved around 10-30Hz 8 at most.
- Gain bump can be seen around UGF of MICH.
- Lock of the last night was ~1hour. Lock was lost because of L to oplev coupling seems to exist.
- Camera: Yokozawa, Inoue
- IYA camera could not see BS, because some clipping may exist.
- WAB: Akutsu
- Heater off.
- IYC: Tomaru
- Cooler off.
- Operaton:
Operation wiki page is opened.
Work plan (*:responsible person)
- CAL: Yamamoto
- Optical gain measurement
- Open loot TF.
- Amplitude tuning for injection.
- Sensitivity.
- BS to MICH TF, if can.
- IFO: *Izumi, Enomoto + many
- Higher BS oplev gain will be tried today by the gain switch on opec board or the gain setting on whitening board.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/23
- Michelson control.
- 4/28 Operation start
- week of 4/30
- Operation continues.
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)