Differences between revisions 361 and 369 (spanning 8 versions)
Revision 361 as of 2018-03-28 09:17:17
Size: 10268
Comment:
Revision 369 as of 2018-04-03 10:43:16
Size: 11137
Comment:
Deletions are marked like this. Additions are marked like this.
Line 50: Line 50:

2017/3/28(Wed.)

 * Remote participants by eZuce: None
=== 2018/4/2(Mon.) ===

* Remote participants by eZuce: Enomoto
Line 56: Line 55:

 * Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto
  * Height was adjusted, and started yaw alignment. GAS filter had a sudden jump, and it is being fixed today.
  * First contact will be removed.
 * BS: *Enomoto
  * DAC had some glitches with no output (even dac kill and master SW are off).
  * It will be investigated more.

 * BRT: Akutsu
  * Alignment was done and BRT worked well, it means that the beam position can be controlled after BRT.
  * Beam shape looks elliptic a bit.
* ETMX: *Ushiba
 * Confirmed the returned beam at REFL
 * Calibration of OpLev is on going (mostly finished)
 * Start Characterization

* ETMY: *Miyamoto
  * Damping is working well. Less than 2urad RMS.

* BS: *Enomoto
 * Two different problems identified
  * Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone
  * Glitches -> Looks like the same problem as ETMY: DAC output goes to zero

* PCal: Binhua
 * Aligned the beam within the PCal module
 
* ETMX camera: Yokozawa
 * Ready but not installed

* TMS: no one to report
Line 70: Line 77:

* ETMX: *Ushiba, Miyamoto
  * Start Characterization

* BS: Enomoto
 * Check the glitches over the weekend

* PCal: Binhua
  * Measure PCal transfer functions

* ETMX Camera: Yokozawa
  * Set up necessary components to take high frame rate pictures

==== Laser hazard ====
* [AM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
* [PM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

* [night]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F




==== Work plan (*:responsible person) ====

 * ETMX: *Ushiba, Takahashi
  * Beam will be aligned more precisely with aligned IR.

 * CAL: *Yamamoto
  * CAL model is tested using iMC.

 * Camera: Yokozawa
  * EX camera takes every one hour. It is necessary 1 sec picture in the weekend.
Line 74: Line 119:
  * IR: PSL, Pend 1F
  * Green: PR2
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 78: Line 123:
  * Green: PR2, Xend 1F    * Green: PR2, Xend 1F
Line 82: Line 127:
  * Green: PR2, Xend 1F    * Green: PR2, Xend 1F
Line 85: Line 130:


 * week of 3/26
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  * Connection of cable at ETMX and starting control.
  * Rough alignment of ETMX using IR.
   * 3/27 EX PD will be removed.: *Yokozawa
Line 96: Line 134:
  * 4/5 12:30 at fan hut: Meeting before pump down 1
Line 98: Line 137:


 * Issues

 * ETMX Type A: GAS filter had a sudden jump, and it is being fixed today.
 * BS: DAC had some glitches with no output (even dac kill and master SW are off).
  * 4/11 12:30 at fan hut: Meeting before pump down 2
  * Closing EXC

==== Issues ====

 * BS: DAC had some glitches but if DAC is off, no glitch was found.
Line 116: Line 155:
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/3/26 updated KAGRA/Commissioning/Commissioning_schedule_20180327.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/2(Mon.)

* Remote participants by eZuce: Enomoto

Report of work (*:responsible person)

* ETMX: *Ushiba

  • Confirmed the returned beam at REFL
  • Calibration of OpLev is on going (mostly finished)

  • Start Characterization

* ETMY: *Miyamoto

  • Damping is working well. Less than 2urad RMS.

* BS: *Enomoto

  • Two different problems identified
    • Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone

    • Glitches -> Looks like the same problem as ETMY: DAC output goes to zero

* PCal: Binhua

  • Aligned the beam within the PCal module

* ETMX camera: Yokozawa

  • Ready but not installed

* TMS: no one to report

Work plan (*:responsible person)

* ETMX: *Ushiba, Miyamoto

  • Start Characterization

* BS: Enomoto

  • Check the glitches over the weekend

* PCal: Binhua

  • Measure PCal transfer functions

* ETMX Camera: Yokozawa

  • Set up necessary components to take high frame rate pictures

Laser hazard

* [AM]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

* [PM]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

* [night]

  • IR: SR2-3 line, Xend 1F, Yend 1F
  • Green: PR2, Xend 1F

Work plan (*:responsible person)

  • ETMX: *Ushiba, Takahashi
    • Beam will be aligned more precisely with aligned IR.
  • CAL: *Yamamoto
    • CAL model is tested using iMC.
  • Camera: Yokozawa
    • EX camera takes every one hour. It is necessary 1 sec picture in the weekend.

Laser hazard

  • [AM]
    • IR: SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/2
    • ETMY damping.
    • Rough alignment of ETMX using IR, and control MICH if can.
    • 4/5 12:30 at fan hut: Meeting before pump down 1
  • week of 4/9
    • 4/11 12:30 at fan hut: Meeting before pump down 2
    • Closing EXC

Issues

  • BS: DAC had some glitches but if DAC is off, no glitch was found.

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)