Size: 10494
Comment:
|
Size: 11605
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/20(Fri.) === | |
Line 51: | Line 52: |
2017/3/29(Thur.) * Remote participants by eZuce: None |
* Remote participants by eZuce: None |
Line 56: | Line 55: |
* Phase 1 operation was postponed to 4/28 start and 5/6 end. | |
Line 57: | Line 57: |
* ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto * Jump of GAS filter was compensated and fixed. * Yaw was roughly aligned by top filter. * First contact was removed. * Top chamber was closed. * Beam reached at the ETMX. * Baffle PD was tested well. |
* VAC: *Kimura * Leak was caused wrong positioned O-ring. The shape of O-ring was deformed. * Pump down started 15:50 yesterday. * Now vacuum gage shows ~30Pa. |
Line 65: | Line 62: |
* BS: *Enomoto * We found that the glitches happened upstream of high power coil driver. It seems that only one channel has glitch. |
* VAC: *Inoue, Yokozawa * Vacuum monitor is ready! except for Y arm monitor. |
Line 68: | Line 65: |
* BRT: Akutsu * Light is collimated well. |
* ETMX: *Hasegawa * 0.07Hz was damped well! * Yaw and pitch are < 1urad. |
Line 71: | Line 69: |
* Camera: Yokozawa * EX camera takes every one hour. |
* ETMY: *Nakano, Shishido * Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow. * Possibility of heat link for 1.6Hz still remains. * Beam at REFL seemed to be OK. * BS: *Eleonora, Izumi * L2P has been well decoupled! * Global injection point for length control is ready. |
Line 77: | Line 82: |
* ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto * Mirror will be aligned with beam today. |
* IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora * Damping, BS L2P, restoring alignment. |
Line 80: | Line 85: |
* CAL: *Yamamoto * CAL model is tested using iMC. |
* VAC: *Kimura * Leak test will be performed and the gate valve will open on weekend if no problem. * Camera: *Inoue, Yokozawa * Tcam of Y end will be ready today. * We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday. * DMG needs some maintenance for DAQ. |
Line 86: | Line 99: |
* IR: SR2-3 line, Xend 1F, Yend 1F | * IR: Upstream SR2-3 line, Xend 1F, Yend 1F |
Line 89: | Line 102: |
* IR: SR2-3 line, Xend 1F, Yend 1F | * IR: Upstream SR2-3 line, Xend 1F, Yend 1F |
Line 93: | Line 106: |
* IR: SR2-3 line, Xend 1F, Yend 1F | * IR: Upstream SR2-3 line, Xend 1F, Yend 1F |
Line 95: | Line 108: |
Line 98: | Line 112: |
* week of 4/16 * Michelson control. * Leak check, and fix leaks. * Opening the last gate valve weekend. |
|
Line 99: | Line 117: |
* week of 3/26 * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa |
* week of 4/23 * Michelson control. * 4/28 Operation start |
Line 105: | Line 121: |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * week of 4/9 * Issues * ETMX Type A: GAS filter had a sudden jump, and it is being fixed today. * BS: DAC had some glitches with no output (even dac kill and master SW are off). |
==== Issues ==== |
Line 128: | Line 134: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || |
|
Line 155: | Line 164: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/20(Fri.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- Phase 1 operation was postponed to 4/28 start and 5/6 end.
- VAC: *Kimura
- Leak was caused wrong positioned O-ring. The shape of O-ring was deformed.
- Pump down started 15:50 yesterday.
- Now vacuum gage shows ~30Pa.
- VAC: *Inoue, Yokozawa
- Vacuum monitor is ready! except for Y arm monitor.
- ETMX: *Hasegawa
- 0.07Hz was damped well!
Yaw and pitch are < 1urad.
- ETMY: *Nakano, Shishido
- Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow.
- Possibility of heat link for 1.6Hz still remains.
- Beam at REFL seemed to be OK.
- BS: *Eleonora, Izumi
- L2P has been well decoupled!
- Global injection point for length control is ready.
Work plan (*:responsible person)
- IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
- Damping, BS L2P, restoring alignment.
- VAC: *Kimura
- Leak test will be performed and the gate valve will open on weekend if no problem.
- Camera: *Inoue, Yokozawa
- Tcam of Y end will be ready today.
- We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday.
- DMG needs some maintenance for DAQ.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/16
- Michelson control.
- Leak check, and fix leaks.
- Opening the last gate valve weekend.
- week of 4/23
- Michelson control.
- 4/28 Operation start
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools