Line 11: Line 11:
2017/3/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}}
2017/4/17 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}}
Line 50: Line 50:
=== 2018/4/2(Fri.) === === 2018/4/25(Wed.) ===
Line 52: Line 52:
* Remote participants by eZuce: Enomoto * Remote participants by eZuce: None
Line 55: Line 55:
* ETMX: *Ushiba
 * Confirmed the returned beam at REFL
 * Calibration of OpLev is on going (mostly finished)
 * Start Characterization
Line 60: Line 56:
* ETMY: *Miyamoto
  * Damping is working well. Less than 2urad RMS.
 * IFO: *Izumi, Enomoto, Nakano + many
  * Michelson lock lasted ~40min with Guardian.
   * ETMX had some drift. It may cause lock down.
Line 63: Line 60:
* BS: *Enomoto
 * Two different problems identified
  * Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone
  * Glitches -> Looks like the same problem as ETMY: DAC output goes to zero
  * Modulation frequency was not tuned yet to iMC length.
   * Measurement of AM conversion can know the matching of mod. freq. to iMC length.
Line 68: Line 63:
* PCal: Binhua
 * Aligned the beam within the PCal module
 
* ETMX camera: Yokozawa
 * Ready but not installed
  * PR3: Oplev has glitch. The laser source of oplev may be a cause. Needs fiber cleaner to exchange the laser.
Line 74: Line 65:
* TMS: no one to report  * BS: *Eleonora, Izumi, Arai
  * BS IM feed back was engaged.
   * Target crossover was originally 3Hz but actual crossover was limited up to ~0.1Hz, because 1.25Hz peak disturbed control.
  * Gain of some loops of oplev servo changed stronger.

 * CAL: *Yamamoto, Enomoto, Izumi
  * Optical measumremnt was measured.
  * Sensitivity is shown in the control room, being calculated from H(t).

 * Injection: *Miyamoto, Yokozawa

 * Noise budget: *Michimura, Enomoto

 * IOO: *Kokeyama, Enomoto
  * MCE trans was clipped. Output PSL was going down to bottom direction, and it was a cause of clipping. This clipping does not affect to IFO control.

 * ETMX: *Hasegawa, Nakano, Enomoto
  * ETMX has some drift for 10-20urad.

 * ETMY: *Nakano, *Shishido, Ushiba, Miyamoto
  * ETMY need L damping.
  * Gardian was implemented.
Line 78: Line 91:
* ETMX: *Ushiba, Miyamoto
  * Start Characterization
 * BS: *Eleonora, Izumi, Arai
  * Opleve loop gains will change stronger.
Line 81: Line 94:
* BS: Enomoto
 * Check the glitches over the weekend
 * CAL: *Yamamoto, Enomoto, Izumi
  * Cal signal will be injected.
Line 84: Line 97:
* PCal: Binhua
  * Measure PCal transfer functions

* ETMX Camera: Yokozawa
  * Set up necessary components to take high frame rate pictures

==== Laser hazard ====
* [AM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
* [PM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

* [night]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F


2017/3/30(Fri.)

 * Remote participants by eZuce: None

==== Report of work (*:responsible person) ====

 * ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto, Nagano
  * Mirror will be aligned with beam today to REFL. But IR and green are not overlapped well.
  * Oplev is placed but not calibrated.
  * LVDT of BF seems to be something wrong. It could be satellite box.

 * BS: *Enomoto, Enzo
  * Hightower coil driver and satellite box was replaced. Satellite box was something wrong. Oplev jump disappeared. But still glitch remains.
  * Hyper threading should be off.

 * BRT: Nagano
  * TMS was seen and aligned to QPD.


 *

==== Work plan (*:responsible person) ====

 * ETMX: *Ushiba, Takahashi
  * Beam will be aligned more precisely with aligned IR.

 * CAL: *Yamamoto
  * CAL model is tested using iMC.

 * Camera: Yokozawa
  * EX camera takes every one hour. It is necessary 1 sec picture in the weekend.
 * IFO: *Izumi, Enomoto, Nakano + many
  * Measurement without locking morning, measurement with locking in the afternoon.
Line 138: Line 103:
  * IR: SR2-3 line, Xend 1F, Yend 1F   * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
Line 141: Line 106:
  * IR: SR2-3 line, Xend 1F, Yend 1F   * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
Line 145: Line 110:
  * IR: SR2-3 line, Xend 1F, Yend 1F   * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
Line 147: Line 112:
Line 150: Line 116:
 * week of 3/26
  * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  * Connection of cable at ETMX and starting control.
  * Rough alignment of ETMX using IR.
   * 3/27 EX PD will be removed.: *Yokozawa

 * week of 4/2
  * ETMY damping.
  * Rough alignment of ETMX using IR, and control MICH if can.

 * week of 4/9
  * Closing EXC
 * week of 4/23
  * Michelson control.
  * 4/28 Operation start
Line 164: Line 121:

 * BS: DAC had some glitches but if DAC is off, no glitch was found.
Line 178: Line 133:
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
Line 205: Line 163:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])  * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/17 updated KAGRA/Commissioning/Commissioning_schedule_20180417.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/25(Wed.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • IFO: *Izumi, Enomoto, Nakano + many
    • Michelson lock lasted ~40min with Guardian.
      • ETMX had some drift. It may cause lock down.
    • Modulation frequency was not tuned yet to iMC length.
      • Measurement of AM conversion can know the matching of mod. freq. to iMC length.
    • PR3: Oplev has glitch. The laser source of oplev may be a cause. Needs fiber cleaner to exchange the laser.
  • BS: *Eleonora, Izumi, Arai
    • BS IM feed back was engaged.
      • Target crossover was originally 3Hz but actual crossover was limited up to ~0.1Hz, because 1.25Hz peak disturbed control.
    • Gain of some loops of oplev servo changed stronger.
  • CAL: *Yamamoto, Enomoto, Izumi
    • Optical measumremnt was measured.
    • Sensitivity is shown in the control room, being calculated from H(t).
  • Injection: *Miyamoto, Yokozawa
  • Noise budget: *Michimura, Enomoto
  • IOO: *Kokeyama, Enomoto
    • MCE trans was clipped. Output PSL was going down to bottom direction, and it was a cause of clipping. This clipping does not affect to IFO control.
  • ETMX: *Hasegawa, Nakano, Enomoto
    • ETMX has some drift for 10-20urad.
  • ETMY: *Nakano, *Shishido, Ushiba, Miyamoto
    • ETMY need L damping.
    • Gardian was implemented.

Work plan (*:responsible person)

  • BS: *Eleonora, Izumi, Arai
    • Opleve loop gains will change stronger.
  • CAL: *Yamamoto, Enomoto, Izumi
    • Cal signal will be injected.
  • IFO: *Izumi, Enomoto, Nakano + many
    • Measurement without locking morning, measurement with locking in the afternoon.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/23
    • Michelson control.
    • 4/28 Operation start

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1