Size: 10806
Comment:
|
Size: 10283
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 50: | Line 50: |
=== 2018/4/2(Mon.) === | === 2018/4/9(Mon.) === |
Line 52: | Line 52: |
* Remote participants by eZuce: Enomoto | * Remote participants by eZuce: |
Line 55: | Line 55: |
* ETMX: *Ushiba * Confirmed the returned beam at REFL * Calibration of OpLev is on going (mostly finished) * Start Characterization * ETMY: *Miyamoto * Damping is working well. Less than 2urad RMS. * BS: *Enomoto * Two different problems identified * Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone * Glitches -> Looks like the same problem as ETMY: DAC output goes to zero * PCal: Binhua * Aligned the beam within the PCal module * ETMX camera: Yokozawa * Ready but not installed * TMS: no one to report ==== Work plan (*:responsible person) ==== * ETMX: *Ushiba, Miyamoto * Start Characterization * BS: Enomoto * Check the glitches over the weekend * PCal: Binhua * Measure PCal transfer functions * ETMX Camera: Yokozawa * Set up necessary components to take high frame rate pictures ==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto * Light from ETMY was seen at the REFL. No light was confirmed from ETMX due to the work at ETMX. * Connection between k1lsc and k1bs was done. |
Line 103: | Line 60: |
* DAQ: *Miyakawa * Minute raw date is being shifted to k1tw0. k1fw0 currently writing full and science and minute data seems to be working very well. |
|
Line 106: | Line 65: |
* Alignment: Enomoto * Alignment to ETMX will be verified Tuesday evening. |
|
Line 107: | Line 68: |
* ETMX: *Ushiba, Takahashi * Beam will be aligned more precisely with aligned IR. * CAL: *Yamamoto * CAL model is tested using iMC. * Camera: Yokozawa * EX camera takes every one hour. It is necessary 1 sec picture in the weekend. |
* Vacuum: Kimura * Disassembling outer frames today * Closing will be done tomorrow. * Installation of Illuminator and viewport are still remaining. It will be done today. * Laser will be stopped day time during this week. |
Line 119: | Line 76: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: off |
Line 122: | Line 79: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: off |
Line 126: | Line 83: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: off |
Line 131: | Line 89: |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. |
|
Line 136: | Line 90: |
* 4/11 12:30 at fan hut: Meeting before pump down 2 | |
Line 140: | Line 95: |
* BS: DAC had some glitches but if DAC is off, no glitch was found. | |
Line 153: | Line 107: |
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || | |
Line 180: | Line 135: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/9(Mon.)
* Remote participants by eZuce:
Report of work (*:responsible person)
- IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto
- Light from ETMY was seen at the REFL. No light was confirmed from ETMX due to the work at ETMX.
- Connection between k1lsc and k1bs was done.
- DAQ: *Miyakawa
- Minute raw date is being shifted to k1tw0. k1fw0 currently writing full and science and minute data seems to be working very well.
Work plan (*:responsible person)
- Alignment: Enomoto
- Alignment to ETMX will be verified Tuesday evening.
- Vacuum: Kimura
- Disassembling outer frames today
- Closing will be done tomorrow.
- Installation of Illuminator and viewport are still remaining. It will be done today.
- Laser will be stopped day time during this week.
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: off
- [PM]
- IR: PSL, Yend 1F
- Green: off
- [night]
- IR: PSL, Yend 1F
- Green: off
Weekly
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools