Line 11: Line 11:
2017/3/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}}
2017/4/17 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}}
Line 24: Line 24:
 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
Line 50: Line 39:
=== 2018/4/2(Mon.) === === 2018/4/29(Sun.) ===
Line 52: Line 41:
* Remote participants by eZuce: Enomoto * Remote participants by eZuce: None
* 2nd day of Phase 1 operation
 * TF of Type A
 * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]]
Line 55: Line 48:
* ETMX: *Ushiba
 * Confirmed the returned beam at REFL
 * Calibration of OpLev is on going (mostly finished)
 * Start Characterization
Line 60: Line 49:
* ETMY: *Miyamoto
  * Damping is working well. Less than 2urad RMS.
 * IFO: *Izumi, Enomoto + many
  * OLG was measured in the daytime.
   * Error of TF of actuator is ~20%.
   * 120usec delay exists in the MICH loop.
  * BS oplev sensitivity was improved by increasing whitening gain.
  * Longest lock of the last night was ~8hour.
   * Baffle PD signal is used to BS alignment.
Line 63: Line 57:
* BS: *Enomoto
 * Two different problems identified
  * Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone
  * Glitches -> Looks like the same problem as ETMY: DAC output goes to zero
 * 40Hz periodic noise was seen every 16min. It is air compressor.
  * It can be stopped during operation.
  * Timing to IY0 will be connected today.
Line 68: Line 61:
* PCal: Binhua
 * Aligned the beam within the PCal module
 
* ETMX camera: Yokozawa
 * Ready but not installed
 * WAB: Akutsu
  * Heater was turned off ~10am.
Line 74: Line 64:
* TMS: no one to report

==== Work plan (*:responsible person) ====

* ETMX: *Ushiba, Miyamoto
  * Start Characterization

* BS: Enomoto
 * Check the glitches over the weekend

* PCal: Binhua
  * Measure PCal transfer functions

* ETMX Camera: Yokozawa
  * Set up necessary components to take high frame rate pictures

==== Laser hazard ====
* [AM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
* [PM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

* [night]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F

 * IYC: Tomaru
  * Cooler was turned off at 4pm and the vacuum level got worse to 1e-3Pa order.
Line 107: Line 70:
 * ETMX: *Ushiba, Takahashi
  * Beam will be aligned more precisely with aligned IR.
 * TF of Type A
  * Some of DOF of ETMY to L.
Line 110: Line 73:
 * CAL: *Yamamoto
  * CAL model is tested using iMC.

 * Camera: Yokozawa
  * EX camera takes every one hour. It is necessary 1 sec picture in the weekend.
Line 119: Line 77:
  * IR: SR2-3 line, Xend 1F, Yend 1F   * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
Line 122: Line 80:
  * IR: SR2-3 line, Xend 1F, Yend 1F   * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
Line 126: Line 84:
  * IR: SR2-3 line, Xend 1F, Yend 1F   * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
Line 128: Line 86:
Line 131: Line 90:
 * week of 4/2
  * ETMY damping.
  * Rough alignment of ETMX using IR, and control MICH if can.

 * week of 4/9
  * Closing EXC
 * week of 4/30
  * Operation continues.
Line 140: Line 95:
 * BS: DAC had some glitches but if DAC is off, no glitch was found.
Line 153: Line 107:
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
Line 180: Line 137:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])  * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/17 updated KAGRA/Commissioning/Commissioning_schedule_20180417.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/29(Sun.)

* Remote participants by eZuce: None * 2nd day of Phase 1 operation

Report of work (*:responsible person)

  • IFO: *Izumi, Enomoto + many
    • OLG was measured in the daytime.
      • Error of TF of actuator is ~20%.
      • 120usec delay exists in the MICH loop.
    • BS oplev sensitivity was improved by increasing whitening gain.
    • Longest lock of the last night was ~8hour.
      • Baffle PD signal is used to BS alignment.
  • 40Hz periodic noise was seen every 16min. It is air compressor.
    • It can be stopped during operation.
    • Timing to IY0 will be connected today.
  • WAB: Akutsu
    • Heater was turned off ~10am.
  • IYC: Tomaru
    • Cooler was turned off at 4pm and the vacuum level got worse to 1e-3Pa order.

Work plan (*:responsible person)

  • TF of Type A
    • Some of DOF of ETMY to L.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/30
    • Operation continues.

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)