Size: 11137
Comment:
|
Size: 10740
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 50: | Line 50: |
=== 2018/4/2(Mon.) === | === 2018/4/5(Thur.) === |
Line 52: | Line 52: |
* Remote participants by eZuce: Enomoto | * Remote participants by eZuce: Kimura, Miyoki, Yokozawa |
Line 55: | Line 55: |
* ETMX: *Ushiba * Confirmed the returned beam at REFL * Calibration of OpLev is on going (mostly finished) * Start Characterization |
* Alignment: Izumi * Both light had been confirmed at REFL yesterday morning. * IR beam was lost at REFL evening, but green was still seen. * Both IR and green were still seen at Y end. |
Line 60: | Line 60: |
* ETMY: *Miyamoto * Damping is working well. Less than 2urad RMS. |
* ETMX: *Ushiba * Circuits and connection are still being checked. |
Line 63: | Line 63: |
* BS: *Enomoto * Two different problems identified * Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone * Glitches -> Looks like the same problem as ETMY: DAC output goes to zero |
* Dolphin: *Yamamoto * Connected IMC, IOO and BS. * Error indicator is seen on BS. |
Line 68: | Line 67: |
* PCal: Binhua * Aligned the beam within the PCal module |
* DAQ: *Yamamoto * Memory will be increased today. SSD might be tested today at k1tw0. * Data stream of ITMX and SR3 are stopped for a while until the end of phase 1. * k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many. * Vacuum: *Kimura * Closing door will be performed in the next week. * PCal: no one to report |
Line 71: | Line 77: |
* ETMX camera: Yokozawa * Ready but not installed * TMS: no one to report |
* TMS: no one to report |
Line 77: | Line 80: |
* Alignment: Izumi * IR will be re-aligned this morning. It requires green off evening. |
|
Line 78: | Line 83: |
* ETMX: *Ushiba, Miyamoto * Start Characterization |
* ETMY: *Miyamoto * Cover on Oplev will be set this morning. |
Line 81: | Line 86: |
* BS: Enomoto * Check the glitches over the weekend |
* DAQ: *Miyakawa * Memory will be increased today. SSD might be tested today at k1tw0. |
Line 84: | Line 89: |
* PCal: Binhua * Measure PCal transfer functions * ETMX Camera: Yokozawa * Set up necessary components to take high frame rate pictures |
|
Line 103: | Line 103: |
==== Work plan (*:responsible person) ==== * ETMX: *Ushiba, Takahashi * Beam will be aligned more precisely with aligned IR. * CAL: *Yamamoto * CAL model is tested using iMC. * Camera: Yokozawa * EX camera takes every one hour. It is necessary 1 sec picture in the weekend. ==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
|
Line 142: | Line 116: |
* BS: DAC had some glitches but if DAC is off, no glitch was found. |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/5(Thur.)
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa
Report of work (*:responsible person)
- Alignment: Izumi
- Both light had been confirmed at REFL yesterday morning.
- IR beam was lost at REFL evening, but green was still seen.
- Both IR and green were still seen at Y end.
- ETMX: *Ushiba
- Circuits and connection are still being checked.
- Dolphin: *Yamamoto
- Connected IMC, IOO and BS.
- Error indicator is seen on BS.
- DAQ: *Yamamoto
- Memory will be increased today. SSD might be tested today at k1tw0.
- Data stream of ITMX and SR3 are stopped for a while until the end of phase 1.
- k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many.
- Vacuum: *Kimura
- Closing door will be performed in the next week.
- PCal: no one to report
- TMS: no one to report
Work plan (*:responsible person)
- Alignment: Izumi
- IR will be re-aligned this morning. It requires green off evening.
- ETMY: *Miyamoto
- Cover on Oplev will be set this morning.
- DAQ: *Miyakawa
- Memory will be increased today. SSD might be tested today at k1tw0.
Laser hazard
* [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- 4/5 12:30 at fan hut: Meeting before pump down 1
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC
Issues
KAGRA/Commissioning/DailyWork << < 2025 / 5 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | |||
5 | 6 | 7 | 8 | 9 | 10 | 11 |
12 | 13 | 14 | 15 | 16 | 17 | 18 |
19 | 20 | 21 | 22 | 23 | 24 | 25 |
26 | 27 | 28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools