11137
Comment:
|
11847
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/2(Mon.) === | === 2018/4/18(Wed.) === |
Line 52: | Line 52: |
* Remote participants by eZuce: Enomoto | * Remote participants by eZuce: None |
Line 55: | Line 55: |
* ETMX: *Ushiba * Confirmed the returned beam at REFL * Calibration of OpLev is on going (mostly finished) * Start Characterization |
|
Line 60: | Line 56: |
* ETMY: *Miyamoto * Damping is working well. Less than 2urad RMS. |
* VAC: *Kimura * One of the small leak was found where it was, but another large leak seems to exist. Leak hunting will last today. * There are 3 ways; * Leak location will be found and fixed without vent. -> ETMX gate valve will open, no delay. * Leak location will be found and not fixed without vent. -> Vent on Wednesday and Thursday, fix leak on Friday, pump down on Friday. -> ETMX gate valve will open, delay for several days. * Leak location will not be found and not fixed. -> ETMX gate valve will not open, no delay, but it will be difficult to find beam at ETMX. |
Line 63: | Line 63: |
* BS: *Enomoto * Two different problems identified * Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone * Glitches -> Looks like the same problem as ETMY: DAC output goes to zero |
* ETMX: *Hasegawa * TF for MM coupling of photo sensor was found. * RMS motion seems to be OK if the mirror is not kicked. Even if the mirror is kicked, damping speed is ~10min or something. |
Line 68: | Line 67: |
* PCal: Binhua * Aligned the beam within the PCal module * ETMX camera: Yokozawa * Ready but not installed |
|
Line 74: | Line 68: |
* TMS: no one to report | * ETMY: *Nakano, Shishido * Yaw dampins seems to be OK. Coupling between pitch and yaw exists. After ~10min or so, oscillation starts up to 10urad. |
Line 76: | Line 71: |
==== Work plan (*:responsible person) ==== | * IFO: *Enomoto, Izumi * Trial lock of Michelson did not succeed because of too much motion of ETMY. |
Line 78: | Line 74: |
* ETMX: *Ushiba, Miyamoto * Start Characterization |
* BS: Eleonora, Izumi * We are optimizing diagonalization of L2P filter. Needs more time. |
Line 81: | Line 77: |
* BS: Enomoto * Check the glitches over the weekend * PCal: Binhua * Measure PCal transfer functions * ETMX Camera: Yokozawa * Set up necessary components to take high frame rate pictures ==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* DGS: *Yamamoto * Interface card for PCIe on k1ioo was exchanged and connection between RTPC and IO chassis was established again. |
Line 107: | Line 84: |
* ETMX: *Ushiba, Takahashi * Beam will be aligned more precisely with aligned IR. |
* IFO: Enomoto, Nakano * Damping, BS L2P, restoring alignment. |
Line 110: | Line 87: |
* CAL: *Yamamoto * CAL model is tested using iMC. * Camera: Yokozawa * EX camera takes every one hour. It is necessary 1 sec picture in the weekend. |
* VAC: *Kimura * Identifies the location of leak. |
Line 119: | Line 93: |
* IR: SR2-3 line, Xend 1F, Yend 1F | * IR: Upstream SR2-3 line, Xend 1F, Yend 1F |
Line 122: | Line 96: |
* IR: SR2-3 line, Xend 1F, Yend 1F | * IR: Upstream SR2-3 line, Xend 1F, Yend 1F |
Line 126: | Line 100: |
* IR: SR2-3 line, Xend 1F, Yend 1F | * IR: Upstream SR2-3 line, Xend 1F, Yend 1F |
Line 128: | Line 102: |
Line 131: | Line 106: |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * 4/5 12:30 at fan hut: Meeting before pump down 1 |
* week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. |
Line 136: | Line 111: |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC |
* week of 4/23 * Operation |
Line 142: | Line 116: |
* BS: DAC had some glitches but if DAC is off, no glitch was found. | * Large leak was found but it is not identified where it is. |
Line 155: | Line 129: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || |
|
Line 183: | Line 159: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/18(Wed.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Kimura
- One of the small leak was found where it was, but another large leak seems to exist. Leak hunting will last today.
- There are 3 ways;
Leak location will be found and fixed without vent. -> ETMX gate valve will open, no delay.
Leak location will be found and not fixed without vent. -> Vent on Wednesday and Thursday, fix leak on Friday, pump down on Friday. -> ETMX gate valve will open, delay for several days.
Leak location will not be found and not fixed. -> ETMX gate valve will not open, no delay, but it will be difficult to find beam at ETMX.
- ETMX: *Hasegawa
- TF for MM coupling of photo sensor was found.
- RMS motion seems to be OK if the mirror is not kicked. Even if the mirror is kicked, damping speed is ~10min or something.
- ETMY: *Nakano, Shishido
- Yaw dampins seems to be OK. Coupling between pitch and yaw exists. After ~10min or so, oscillation starts up to 10urad.
- IFO: *Enomoto, Izumi
- Trial lock of Michelson did not succeed because of too much motion of ETMY.
- BS: Eleonora, Izumi
- We are optimizing diagonalization of L2P filter. Needs more time.
- DGS: *Yamamoto
- Interface card for PCIe on k1ioo was exchanged and connection between RTPC and IO chassis was established again.
Work plan (*:responsible person)
- IFO: Enomoto, Nakano
- Damping, BS L2P, restoring alignment.
- VAC: *Kimura
- Identifies the location of leak.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/16
- Michelson control.
- Leak check.
- Opening the last gate valve.
- week of 4/23
- Operation
Issues
- Large leak was found but it is not identified where it is.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)