Differences between revisions 370 and 386 (spanning 16 versions)
Revision 370 as of 2018-04-05 09:27:32
Size: 10740
Comment:
Revision 386 as of 2018-04-13 09:09:19
Size: 10829
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/3/26 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}}
2017/4/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}}
Line 50: Line 50:
=== 2018/4/5(Thur.) === === 2018/4/13(Fri.) ===
Line 52: Line 52:
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa * Remote participants by eZuce: Miyoki
Line 55: Line 55:
 * Alignment: Izumi
  * Both light had been confirmed at REFL yesterday morning.
  * IR beam was lost at REFL evening, but green was still seen.
  * Both IR and green were still seen at Y end.
 * IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
  * Last night, the beam from ETMX was lost caused by probably a shit at oplev. Installing a view port might introduce the shift on oplev yaw.
  * Centering of oplev was done this morning
  * Alignment was tuned IMC from 0.3/1.0->0.7/1.0
Line 60: Line 60:
 * ETMX: *Ushiba
  * Circuits and connection are still being checked.
 * ETMY was improved a bit by Nakano. Now ~3urad.
Line 63: Line 62:
 * Dolphin: *Yamamoto
  * Connected IMC, IOO and BS.
  * Error indicator is seen on BS.
 * VAC: *Kimura
  * View port for oplev at ETMX was attached yesterday's afternoon.
  * All the preparation was done and the door of EXC was closed.
Line 67: Line 66:
 * DAQ: *Yamamoto
  * Memory will be increased today. SSD might be tested today at k1tw0.
  * Data stream of ITMX and SR3 are stopped for a while until the end of phase 1.
  * k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many.

 * Vacuum: *Kimura
  * Closing door will be performed in the next week.

 * PCal: no one to report
 
 * TMS: no one to report
Line 80: Line 68:
 * Alignment: Izumi
  * IR will be re-aligned this morning. It requires green off evening.
 * IFO: damping work or others.
Line 83: Line 70:
 * ETMY: *Miyamoto
  * Cover on Oplev will be set this morning.

 * DAQ: *Miyakawa
  * Memory will be increased today. SSD might be tested today at k1tw0.
 * VAC: *Kimura
  * Pumping down will start ~10am today.
Line 91: Line 75:
* [AM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
* [PM]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [AM]
  * IR: PSL, Yend 1F
  * Green: off
* [PM]
  * IR: Upstream SR2-3 line, Yend 1F
  * Green: off
Line 98: Line 82:
* [night]
  * IR: SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
 * [night]
  * IR: Upstream SR2-3 line, Yend 1F
  * Green: off
Line 105: Line 89:
 * week of 4/2
  * ETMY damping.
  * Rough alignment of ETMX using IR, and control MICH if can.
  * 4/5 12:30 at fan hut: Meeting before pump down 1
 * week of 4/9
  * 4/11 12:30 at fan hut: Meeting before pump down 2.
  * Closing EXC.
  * Some controls for Michelson.
  * 4/13 morning: Pump down starts.
Line 110: Line 95:
 * week of 4/9
  * 4/11 12:30 at fan hut: Meeting before pump down 2
  * Closing EXC
 * week of 4/16
  * Michelson control.
  * Leak check.
  * Opening the last gate valve.

 * week of 4/23
  * Operation
Line 128: Line 117:
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
Line 156: Line 146:
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]])  * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/10 updated KAGRA/Commissioning/Commissioning_schedule_20180410.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/13(Fri.)

* Remote participants by eZuce: Miyoki

Report of work (*:responsible person)

  • IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
    • Last night, the beam from ETMX was lost caused by probably a shit at oplev. Installing a view port might introduce the shift on oplev yaw.
    • Centering of oplev was done this morning
    • Alignment was tuned IMC from 0.3/1.0->0.7/1.0

  • ETMY was improved a bit by Nakano. Now ~3urad.
  • VAC: *Kimura
    • View port for oplev at ETMX was attached yesterday's afternoon.
    • All the preparation was done and the door of EXC was closed.

Work plan (*:responsible person)

  • IFO: damping work or others.
  • VAC: *Kimura
    • Pumping down will start ~10am today.

Laser hazard

  • [AM]
    • IR: PSL, Yend 1F
    • Green: off
  • [PM]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off
  • [night]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off

Weekly

  • week of 4/9
    • 4/11 12:30 at fan hut: Meeting before pump down 2.
    • Closing EXC.
    • Some controls for Michelson.
    • 4/13 morning: Pump down starts.
  • week of 4/16
    • Michelson control.
    • Leak check.
    • Opening the last gate valve.
  • week of 4/23
    • Operation

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)