Line 11: | Line 11: |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
2017/4/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/5(Thur.) === | === 2018/4/16(Mon.) === |
Line 52: | Line 52: |
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa | * Remote participants by eZuce: Miyoki |
Line 55: | Line 55: |
* Alignment: Izumi * Both light had been confirmed at REFL yesterday morning. * IR beam was lost at REFL evening, but green was still seen. * Both IR and green were still seen at Y end. |
* VAC: *Kimura * Pump down started ~10am. |
Line 60: | Line 58: |
* ETMX: *Ushiba * Circuits and connection are still being checked. |
* IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa * Beams from ETMX and ETMY were seen at REFL and showed some interference. |
Line 63: | Line 61: |
* Dolphin: *Yamamoto * Connected IMC, IOO and BS. * Error indicator is seen on BS. * DAQ: *Yamamoto * Memory will be increased today. SSD might be tested today at k1tw0. * Data stream of ITMX and SR3 are stopped for a while until the end of phase 1. * k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many. * Vacuum: *Kimura * Closing door will be performed in the next week. * PCal: no one to report * TMS: no one to report |
* DAQ: *Miyakawa * k1tw1 started writing minute_raw. All DAQ servers are working stably over the last weekend. |
Line 80: | Line 65: |
* Alignment: Izumi * IR will be re-aligned this morning. It requires green off evening. |
* Extended chief meeting at Toyama Univ. |
Line 83: | Line 67: |
* ETMY: *Miyamoto * Cover on Oplev will be set this morning. * DAQ: *Miyakawa * Memory will be increased today. SSD might be tested today at k1tw0. |
* VAC: *Kimura * Pumping down will start ~10am today. |
Line 91: | Line 72: |
* [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* [AM] * IR: PSL, Yend 1F * Green: off * [PM] * IR: Upstream SR2-3 line, Yend 1F * Green: off |
Line 98: | Line 79: |
* [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* [night] * IR: Upstream SR2-3 line, Yend 1F * Green: off |
Line 105: | Line 86: |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * 4/5 12:30 at fan hut: Meeting before pump down 1 |
* week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. |
Line 110: | Line 91: |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC |
* week of 4/23 * Operation |
Line 115: | Line 95: |
Line 128: | Line 106: |
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || | |
Line 156: | Line 135: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/10 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/16(Mon.)
* Remote participants by eZuce: Miyoki
Report of work (*:responsible person)
- VAC: *Kimura
- Pump down started ~10am.
- IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
- Beams from ETMX and ETMY were seen at REFL and showed some interference.
- DAQ: *Miyakawa
- k1tw1 started writing minute_raw. All DAQ servers are working stably over the last weekend.
Work plan (*:responsible person)
- Extended chief meeting at Toyama Univ.
- VAC: *Kimura
- Pumping down will start ~10am today.
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: off
- [PM]
- IR: Upstream SR2-3 line, Yend 1F
- Green: off
- [night]
- IR: Upstream SR2-3 line, Yend 1F
- Green: off
Weekly
- week of 4/16
- Michelson control.
- Leak check.
- Opening the last gate valve.
- week of 4/23
- Operation
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)