Comment:
|
10626
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
2017/4/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/5(Thur.) === | === 2018/4/12(Thur.) === |
Line 52: | Line 52: |
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa | * Remote participants by eZuce: None |
Line 55: | Line 55: |
* Alignment: Izumi * Both light had been confirmed at REFL yesterday morning. * IR beam was lost at REFL evening, but green was still seen. * Both IR and green were still seen at Y end. * ETMX: *Ushiba * Circuits and connection are still being checked. * Dolphin: *Yamamoto * Connected IMC, IOO and BS. * Error indicator is seen on BS. * DAQ: *Yamamoto * Memory will be increased today. SSD might be tested today at k1tw0. * Data stream of ITMX and SR3 are stopped for a while until the end of phase 1. * k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many. * Vacuum: *Kimura * Closing door will be performed in the next week. * PCal: no one to report * TMS: no one to report |
* IFO: Enomoto, Nagano, Nagano * 5 front gate valve opened and beam was verified at the Y end baffle PD. * Beam shift was only ~10urad when the gate valve opened. * One of the monitor of gate valve did not work. * Final check at X end was done. * Coil driver for Marionette was changed from low to high. * Damping of ETMX will be tested with HPCD. |
Line 80: | Line 64: |
* Alignment: Izumi * IR will be re-aligned this morning. It requires green off evening. * ETMY: *Miyamoto * Cover on Oplev will be set this morning. * DAQ: *Miyakawa * Memory will be increased today. SSD might be tested today at k1tw0. |
* IFO: damping work or others. * VAC: closing ETMX door. * Pumping starts tomorrow morning. |
Line 91: | Line 70: |
* [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* [AM] * IR: PSL, Yend 1F * Green: off * [PM] * IR: PSL, Yend 1F * Green: off |
Line 98: | Line 77: |
* [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* [night] * IR: Upstream SR2-3 line, Yend 1F * Green: off |
Line 105: | Line 84: |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * 4/5 12:30 at fan hut: Meeting before pump down 1 |
|
Line 113: | Line 87: |
* Some controls for Michelson * 4/13 moning Pump down * week of 4/16 * Michelson control * Leak check * week of 4/23 * Operation |
|
Line 128: | Line 111: |
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || | |
Line 156: | Line 140: |
* Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/10 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/12(Thur.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- IFO: Enomoto, Nagano, Nagano
- 5 front gate valve opened and beam was verified at the Y end baffle PD.
- Beam shift was only ~10urad when the gate valve opened.
- One of the monitor of gate valve did not work.
- Final check at X end was done.
- Coil driver for Marionette was changed from low to high.
- Damping of ETMX will be tested with HPCD.
Work plan (*:responsible person)
- IFO: damping work or others.
- VAC: closing ETMX door.
- Pumping starts tomorrow morning.
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: off
- [PM]
- IR: PSL, Yend 1F
- Green: off
- [night]
- IR: Upstream SR2-3 line, Yend 1F
- Green: off
Weekly
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC
- Some controls for Michelson
- 4/13 moning Pump down
- week of 4/16
- Michelson control
- Leak check
- week of 4/23
- Operation
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools