Line 50: | Line 50: |
=== 2018/4/6(Fri.) === | === 2018/4/9(Mon.) === |
Line 52: | Line 52: |
* Remote participants by eZuce: Kimura | * Remote participants by eZuce: |
Line 56: | Line 56: |
* Both light was confirmed at ETMX last night. * BS model was split, and no glitch was seen. Upper model is running at 4kHz and lower model is running at 16kHz. * Connection between k1lsc and k1bs is still something wrong. * Quality of ETMX looks much better than EMY. No bright spot was seen. |
* Light from ETMY was seen at the REFL. No light was confirmed from ETMX due to the work at ETMX. * Connection between k1lsc and k1bs was done. |
Line 61: | Line 59: |
* ETMY: *Miyamoto * Covered on Oplev. |
* DAQ: *Miyakawa * Minute raw date is being shifted to k1tw0. k1fw0 currently writing full and science and minute data seems to be working very well. |
Line 66: | Line 65: |
* Alignment: Izumi * No light is used in the daytime. Start using beam from evening. |
* Alignment: Enomoto * Alignment to ETMX will be verified Tuesday evening. |
Line 69: | Line 68: |
* DAQ: *Miyakawa * Memory will be increased today. SSD might be tested today at k1tw0. * Vacuum: *Kimura * Closing door will be performed in the next week as planned. |
* Vacuum: Kimura * Disassembling outer frames today * Closing will be done tomorrow. * Installation of Illuminator and viewport are still remaining. It will be done today. * Laser will be stopped day time during this week. |
Line 78: | Line 76: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: off |
Line 81: | Line 79: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: off |
Line 85: | Line 83: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: off |
Line 90: | Line 88: |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * 4/5 12:30 at fan hut: Meeting before pump down 1 |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/9(Mon.)
* Remote participants by eZuce:
Report of work (*:responsible person)
- IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto
- Light from ETMY was seen at the REFL. No light was confirmed from ETMX due to the work at ETMX.
- Connection between k1lsc and k1bs was done.
- DAQ: *Miyakawa
- Minute raw date is being shifted to k1tw0. k1fw0 currently writing full and science and minute data seems to be working very well.
Work plan (*:responsible person)
- Alignment: Enomoto
- Alignment to ETMX will be verified Tuesday evening.
- Vacuum: Kimura
- Disassembling outer frames today
- Closing will be done tomorrow.
- Installation of Illuminator and viewport are still remaining. It will be done today.
- Laser will be stopped day time during this week.
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: off
- [PM]
- IR: PSL, Yend 1F
- Green: off
- [night]
- IR: PSL, Yend 1F
- Green: off
Weekly
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC
Issues
KAGRA/Commissioning/DailyWork << < 2025 / 5 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | |||
5 | 6 | 7 | 8 | 9 | 10 | 11 |
12 | 13 | 14 | 15 | 16 | 17 | 18 |
19 | 20 | 21 | 22 | 23 | 24 | 25 |
26 | 27 | 28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)