Line 11: Line 11:
2017/4/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}}
2017/4/17 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}}
Line 50: Line 50:
=== 2018/4/11(Tue.) === === 2018/4/25(Wed.) ===
Line 55: Line 55:
 * IFO: Enomoto, Nagano, Machimura, Takano
  * Michelson fringe was seen at the REFL port.
  * ETMY is still moving a lot.
  * IMC was aligned again. PLS is going lower. Then PR3 was aligned.
  * Oplev of EMX was a good reference to align to REFL.
  * REFL port has been aligned roughly.
Line 62: Line 56:
 * DGS: Yamamoto
  * We have found how to stop/start Dolphin without stopping RT models connected to Dolphin.
 * IFO: *Izumi, Enomoto, Nakano + many
  * Michelson lock lasted ~40min with Guardian.
   * ETMX had some drift. It may cause lock down.

  * Modulation frequency was not tuned yet to iMC length.
   * Measurement of AM conversion can know the matching of mod. freq. to iMC length.

  * PR3: Oplev has glitch. The laser source of oplev may be a cause. Needs fiber cleaner to exchange the laser.

 * BS: *Eleonora, Izumi, Arai
  * BS IM feed back was engaged.
   * Target crossover was originally 3Hz but actual crossover was limited up to ~0.1Hz, because 1.25Hz peak disturbed control.
  * Gain of some loops of oplev servo changed stronger.

 * CAL: *Yamamoto, Enomoto, Izumi
  * Optical measumremnt was measured.
  * Sensitivity is shown in the control room, being calculated from H(t).

 * Injection: *Miyamoto, Yokozawa

 * Noise budget: *Michimura, Enomoto

 * IOO: *Kokeyama, Enomoto
  * MCE trans was clipped. Output PSL was going down to bottom direction, and it was a cause of clipping. This clipping does not affect to IFO control.

 * ETMX: *Hasegawa, Nakano, Enomoto
  * ETMX has some drift for 10-20urad.

 * ETMY: *Nakano, *Shishido, Ushiba, Miyamoto
  * ETMY need L damping.
  * Gardian was implemented.
Line 67: Line 90:
 * Camera: Inoue, Yokozawa
  * Illuminator will be installed.
  * We check that nothing blocks the beam between IXA and IXC.
Line 71: Line 91:
 * DAQ: *Miyakawa
  * Recording minute raw date will start again at k1tw0 this morning.
 * BS: *Eleonora, Izumi, Arai
  * Opleve loop gains will change stronger.

 * CAL: *Yamamoto, Enomoto, Izumi
  * Cal signal will be injected.

 * IFO: *Izumi, Enomoto, Nakano + many
  * Measurement without locking morning, measurement with locking in the afternoon.
Line 77: Line 103:
  * IR: PSL, Yend 1F
  * Green: off
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 80: Line 106:
  * IR: PSL, Yend 1F
  * Green: off
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 84: Line 110:
  * IR: PSL, Yend 1F
  * Green: off
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 90: Line 116:
 * week of 4/9
  * 4/11 12:30 at fan hut: Meeting before pump down 2
  * Closing EXC
  * Some controls for Michelson
 * week of 4/23
  * Michelson control.
  * 4/28 Operation start
Line 96: Line 121:
Line 109: Line 133:
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
Line 138: Line 163:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/17 updated KAGRA/Commissioning/Commissioning_schedule_20180417.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/25(Wed.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • IFO: *Izumi, Enomoto, Nakano + many
    • Michelson lock lasted ~40min with Guardian.
      • ETMX had some drift. It may cause lock down.
    • Modulation frequency was not tuned yet to iMC length.
      • Measurement of AM conversion can know the matching of mod. freq. to iMC length.
    • PR3: Oplev has glitch. The laser source of oplev may be a cause. Needs fiber cleaner to exchange the laser.
  • BS: *Eleonora, Izumi, Arai
    • BS IM feed back was engaged.
      • Target crossover was originally 3Hz but actual crossover was limited up to ~0.1Hz, because 1.25Hz peak disturbed control.
    • Gain of some loops of oplev servo changed stronger.
  • CAL: *Yamamoto, Enomoto, Izumi
    • Optical measumremnt was measured.
    • Sensitivity is shown in the control room, being calculated from H(t).
  • Injection: *Miyamoto, Yokozawa
  • Noise budget: *Michimura, Enomoto
  • IOO: *Kokeyama, Enomoto
    • MCE trans was clipped. Output PSL was going down to bottom direction, and it was a cause of clipping. This clipping does not affect to IFO control.
  • ETMX: *Hasegawa, Nakano, Enomoto
    • ETMX has some drift for 10-20urad.
  • ETMY: *Nakano, *Shishido, Ushiba, Miyamoto
    • ETMY need L damping.
    • Gardian was implemented.

Work plan (*:responsible person)

  • BS: *Eleonora, Izumi, Arai
    • Opleve loop gains will change stronger.
  • CAL: *Yamamoto, Enomoto, Izumi
    • Cal signal will be injected.
  • IFO: *Izumi, Enomoto, Nakano + many
    • Measurement without locking morning, measurement with locking in the afternoon.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/23
    • Michelson control.
    • 4/28 Operation start

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1