Line 50: | Line 50: |
=== 2018/4/11(Tue.) === | === 2018/4/13(Fri.) === |
Line 52: | Line 52: |
* Remote participants by eZuce: None | * Remote participants by eZuce: Miyoki |
Line 55: | Line 55: |
* IFO: Enomoto, Nagano, Machimura, Takano * Michelson fringe was seen at the REFL port. * ETMY is still moving a lot. * IMC was aligned again. PLS is going lower. Then PR3 was aligned. * Oplev of EMX was a good reference to align to REFL. * REFL port has been aligned roughly. |
* IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa * Last night, beam was lost caused by a shit at oplev. Installing a view port might introduce the shift on oplev yaw. |
Line 62: | Line 58: |
* DGS: Yamamoto * We have found how to stop/start Dolphin without stopping RT models connected to Dolphin. |
* VAC: *Kimura * View port for oplev at ETMX was attached yesterday's afternoon. * All the preparation was done and the door of EXC was closed. * Damping of ETMX will be tested with HPCD. |
Line 67: | Line 64: |
* Camera: Inoue, Yokozawa * Illuminator will be installed. * We check that nothing blocks the beam between EXA and EXC. |
* IFO: damping work or others. |
Line 71: | Line 66: |
* DAQ: *Miyakawa * Recording minute raw date will start again at k1tw0 this morning. |
* VAC: *Kimura * Pumping down will start ~10am today. |
Line 80: | Line 75: |
* IR: PSL, Yend 1F | * IR: Upstream SR2-3 line, Yend 1F |
Line 84: | Line 79: |
* IR: PSL, Yend 1F | * IR: Upstream SR2-3 line, Yend 1F |
Line 91: | Line 86: |
* 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC * Some controls for Michelson |
* 4/11 12:30 at fan hut: Meeting before pump down 2. * Closing EXC. * Some controls for Michelson. * 4/13 morning: Pump down starts. * week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. * week of 4/23 * Operation |
Line 138: | Line 142: |
* Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/10 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/13(Fri.)
* Remote participants by eZuce: Miyoki
Report of work (*:responsible person)
- IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
- Last night, beam was lost caused by a shit at oplev. Installing a view port might introduce the shift on oplev yaw.
- VAC: *Kimura
- View port for oplev at ETMX was attached yesterday's afternoon.
- All the preparation was done and the door of EXC was closed.
- Damping of ETMX will be tested with HPCD.
Work plan (*:responsible person)
- IFO: damping work or others.
- VAC: *Kimura
- Pumping down will start ~10am today.
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: off
- [PM]
- IR: Upstream SR2-3 line, Yend 1F
- Green: off
- [night]
- IR: Upstream SR2-3 line, Yend 1F
- Green: off
Weekly
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2.
- Closing EXC.
- Some controls for Michelson.
- 4/13 morning: Pump down starts.
- week of 4/16
- Michelson control.
- Leak check.
- Opening the last gate valve.
- week of 4/23
- Operation
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 6 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | |||||
3 | 4 | 5 | 6 | 7 | 8 | 9 |
10 | 11 | 12 | 13 | 14 | 15 | 16 |
17 | 18 | 19 | 20 | 21 | 22 | 23 |
24 | 25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools