Differences between revisions 380 and 385 (spanning 5 versions)
Revision 380 as of 2018-04-10 10:19:20
Size: 10495
Comment:
Revision 385 as of 2018-04-13 09:01:16
Size: 10701
Comment:
Deletions are marked like this. Additions are marked like this.
Line 50: Line 50:
=== 2018/4/11(Tue.) === === 2018/4/13(Fri.) ===
Line 52: Line 52:
* Remote participants by eZuce: None * Remote participants by eZuce: Miyoki
Line 55: Line 55:
 * IFO: Enomoto, Nagano, Machimura, Takano
  * Michelson fringe was seen at the REFL port.
  * ETMY is still moving a lot.
  * IMC was aligned again. PLS is going lower. Then PR3 was aligned.
  * Oplev of EMX was a good reference to align to REFL.
  * REFL port has been aligned roughly.
 * IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
  * Last night, beam was lost caused by a shit at oplev. Installing a view port might introduce the shift on oplev yaw.
Line 62: Line 58:
 * DGS: Yamamoto
  * We have found how to stop/start Dolphin without stopping RT models connected to Dolphin.
 * VAC: *Kimura
  * View port for oplev at ETMX was attached yesterday's afternoon.
  * All the preparation was done and the door of EXC was closed.
  * Damping of ETMX will be tested with HPCD.
Line 67: Line 64:
 * Camera: Inoue, Yokozawa
  * Illuminator will be installed.
  * We check that nothing blocks the beam between EXA and EXC.
 * IFO: damping work or others.
Line 71: Line 66:
 * DAQ: *Miyakawa
  * Recording minute raw date will start again at k1tw0 this morning.
 * VAC: *Kimura
  * Pumping down will start ~10am today.
Line 80: Line 75:
  * IR: PSL, Yend 1F   * IR: Upstream SR2-3 line, Yend 1F
Line 84: Line 79:
  * IR: PSL, Yend 1F   * IR: Upstream SR2-3 line, Yend 1F
Line 91: Line 86:
  * 4/11 12:30 at fan hut: Meeting before pump down 2
  * Closing EXC
  * Some controls for Michelson
  * 4/11 12:30 at fan hut: Meeting before pump down 2.
  * Closing EXC.
  * Some controls for Michelson.
  * 4/13 morning: Pump down starts.

 * week of 4/16
  * Michelson control.
  * Leak check.
  * Opening the last gate valve.

 * week of 4/23
  * Operation
Line 138: Line 142:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/10 updated KAGRA/Commissioning/Commissioning_schedule_20180410.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/13(Fri.)

* Remote participants by eZuce: Miyoki

Report of work (*:responsible person)

  • IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
    • Last night, beam was lost caused by a shit at oplev. Installing a view port might introduce the shift on oplev yaw.
  • VAC: *Kimura
    • View port for oplev at ETMX was attached yesterday's afternoon.
    • All the preparation was done and the door of EXC was closed.
    • Damping of ETMX will be tested with HPCD.

Work plan (*:responsible person)

  • IFO: damping work or others.
  • VAC: *Kimura
    • Pumping down will start ~10am today.

Laser hazard

  • [AM]
    • IR: PSL, Yend 1F
    • Green: off
  • [PM]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off
  • [night]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off

Weekly

  • week of 4/9
    • 4/11 12:30 at fan hut: Meeting before pump down 2.
    • Closing EXC.
    • Some controls for Michelson.
    • 4/13 morning: Pump down starts.
  • week of 4/16
    • Michelson control.
    • Leak check.
    • Opening the last gate valve.
  • week of 4/23
    • Operation

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 6 >  >>
Mon Tue Wed Thu Fri Sat Sun
          1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)