Differences between revisions 380 and 409 (spanning 29 versions)
Revision 380 as of 2018-04-10 10:19:20
Size: 10495
Comment:
Revision 409 as of 2018-05-01 10:37:20
Size: 10926
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/4/10 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}}
2017/5/01 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180501.png||width=1200}}
Line 24: Line 24:
 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
Line 50: Line 39:
=== 2018/4/11(Tue.) === === 2018/5/1(Tue.) ===
Line 53: Line 42:
* 4th day of Phase 1 operation
 * TF of ETMX
 * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]]
Line 55: Line 48:
 * IFO: Enomoto, Nagano, Machimura, Takano
  * Michelson fringe was seen at the REFL port.
  * ETMY is still moving a lot.
  * IMC was aligned again. PLS is going lower. Then PR3 was aligned.
  * Oplev of EMX was a good reference to align to REFL.
  * REFL port has been aligned roughly.
Line 62: Line 49:
 * DGS: Yamamoto
  * We have found how to stop/start Dolphin without stopping RT models connected to Dolphin.
 * IFO: *Izumi, Enomoto + many
  * DAC on PR3: Yamamoto
   * PR3 DAC was dead. Reboot of k1pr3 fixed, but we are not sure the cause.
   * lock lost was ~100min, including guardian misrecording.
   * DAQ was dead 2-3min.
Line 65: Line 55:
  * Noise budged: *Tanioka, Izumi, Enomono
   * PR2 oplev loop was improved, and MICH noise around 10-20Hz was improved.
   * 100Hz noise seems to be dominated by beam position of BS or ETMY.

 * TF of BS was well done.
 * CBC injection was well done.

 * DGS: *Miyakawa
  * Timing signal was connected k1iy0 on Sunday, it requires a reboot of RT PC of k1iy0 once.
Line 67: Line 66:
 * Camera: Inoue, Yokozawa
  * Illuminator will be installed.
  * We check that nothing blocks the beam between EXA and EXC.
Line 71: Line 67:
 * DAQ: *Miyakawa
  * Recording minute raw date will start again at k1tw0 this morning.
 * TF of Type A: Okutomi, Miyamoto
Line 77: Line 73:
  * IR: PSL, Yend 1F
  * Green: off
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 80: Line 76:
  * IR: PSL, Yend 1F
  * Green: off
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 84: Line 80:
  * IR: PSL, Yend 1F
  * Green: off
  * IR: Upstream SR2-3 line, Xend 1F, Yend 1F
  * Green: PR2, Xend 1F
Line 90: Line 86:
 * week of 4/9
  * 4/11 12:30 at fan hut: Meeting before pump down 2
  * Closing EXC
  * Some controls for Michelson
 * week of 4/30
  * Operation continues.
Line 109: Line 103:
||28||2018/5/1||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| ||
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
Line 138: Line 134:
 * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/5/01 updated KAGRA/Commissioning/Commissioning_schedule_20180501.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/5/1(Tue.)

* Remote participants by eZuce: None * 4th day of Phase 1 operation

Report of work (*:responsible person)

  • IFO: *Izumi, Enomoto + many
    • DAC on PR3: Yamamoto
      • PR3 DAC was dead. Reboot of k1pr3 fixed, but we are not sure the cause.
      • lock lost was ~100min, including guardian misrecording.
      • DAQ was dead 2-3min.
    • Noise budged: *Tanioka, Izumi, Enomono
      • PR2 oplev loop was improved, and MICH noise around 10-20Hz was improved.
      • 100Hz noise seems to be dominated by beam position of BS or ETMY.
  • TF of BS was well done.
  • CBC injection was well done.
  • DGS: *Miyakawa
    • Timing signal was connected k1iy0 on Sunday, it requires a reboot of RT PC of k1iy0 once.

Work plan (*:responsible person)

  • TF of Type A: Okutomi, Miyamoto

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/30
    • Operation continues.

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)