Line 11: | Line 11: |
2017/4/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}} |
2017/5/01 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180501.png||width=1200}} |
Line 24: | Line 24: |
* Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 |
|
Line 50: | Line 39: |
=== 2018/4/11(Wed.) === | === 2018/5/8(Tue.) === |
Line 52: | Line 41: |
* Remote participants by eZuce: None | * Remote participants by eZuce: None |
Line 55: | Line 44: |
* IFO: Enomoto, Nagano, Nagano * RF signal was extracted from fringe of Michelson. * Ratio of ETMY and ETMX is not so large, roughly 1:1. * We need more damping for both ETMY and ETMX. * 4 front gate valve will be open. * Power of coil driver is too small at ETMX marionette damping. It will be exchanged to HPCD. |
|
Line 62: | Line 45: |
* Camera: Yokozawa * Illuminator at X end chamber was installed. |
* VAC: *Uchiyama * 7 gate valve opened. * Venting started at the center area. * Yend cooling stopped. |
Line 65: | Line 50: |
* DAQ: Miyakawa, Yamamoto * k1tw0 started writing minute raw data. |
* Trial of release of ETMY f3 did not succeed. * Looking at power of oplev of ETMY during switch off of cooler, but did not succeed. |
Line 69: | Line 56: |
* Camera: Inoue, Yokozawa * We check that nothing blocks the beam between EXA and EXC. * DAQ: *Miyakawa * Preparation to move writing minute raw of k1fw1 to a new k1tw1. |
|
Line 78: | Line 60: |
* Green: off | * Green: None |
Line 81: | Line 63: |
* Green: off | * Green: None |
Line 84: | Line 66: |
* IR: Upstream SR2-3 line, Yend 1F * Green: off |
* IR: PSL, Yend 1F * Green: None |
Line 90: | Line 72: |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC * Some controls for Michelson * 4/13~ Pump down |
* week of 5/7 * 5/7 8-9am: Close 7 gate valves. |
Line 96: | Line 75: |
* week of 4/16 * Michelson control * Leak check * week of 4/23 * Operation |
|
Line 117: | Line 90: |
||29||2018/5/8||[[KAGRA/Commissioning/Weekly/20180508/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180508.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180508/Minute|Minute]]|| || ||28||2018/5/1||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| || ||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/5/01 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/5/8(Tue.)
- Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Uchiyama
- 7 gate valve opened.
- Venting started at the center area.
- Yend cooling stopped.
- Trial of release of ETMY f3 did not succeed.
- Looking at power of oplev of ETMY during switch off of cooler, but did not succeed.
Work plan (*:responsible person)
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: None
- [PM]
- IR: PSL, Yend 1F
- Green: None
- [night]
- IR: PSL, Yend 1F
- Green: None
Weekly
- week of 5/7
- 5/7 8-9am: Close 7 gate valves.
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)