Line 11: | Line 11: |
2017/4/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 24: | Line 24: |
* Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 |
|
Line 50: | Line 39: |
=== 2018/4/13(Fri.) === | === 2018/5/1(Tue.) === |
Line 52: | Line 41: |
* Remote participants by eZuce: Miyoki | * Remote participants by eZuce: None * 4th day of Phase 1 operation * TF of ETMX * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] |
Line 55: | Line 48: |
* IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa * Last night, beam was lost caused by a shit at oplev. Installing a view port might introduce the shift on oplev yaw. |
|
Line 58: | Line 49: |
* VAC: *Kimura * View port for oplev at ETMX was attached yesterday's afternoon. * All the preparation was done and the door of EXC was closed. * Damping of ETMX will be tested with HPCD. |
* IFO: *Izumi, Enomoto + many * DAC on PR3: Yamamoto * PR3 DAC was dead. Reboot of k1pr3 fixed, but we are not sure the cause. * lock lost was ~100min, including guardian misrecording. * DAQ was dead 2-3min. * Noise budged: *Tanioka, Izumi, Enomono * PR2 oplev loop was improved, and MICH noise around 10-20Hz was improved. * 100Hz noise seems to be dominated by beam position of BS or ETMY. * TF of BS was well done. * CBC injection was well done. * DGS: *Miyakawa * Timing signal was connected k1iy0 on Sunday, it requires a reboot of RT PC of k1iy0 once. |
Line 64: | Line 66: |
* IFO: damping work or others. | |
Line 66: | Line 67: |
* VAC: *Kimura * Pumping down will start ~10am today. |
* TF of Type A: Okutomi, Miyamoto |
Line 72: | Line 73: |
* IR: PSL, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 75: | Line 76: |
* IR: Upstream SR2-3 line, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 79: | Line 80: |
* IR: Upstream SR2-3 line, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 85: | Line 86: |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2. * Closing EXC. * Some controls for Michelson. * 4/13 morning: Pump down starts. * week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. * week of 4/23 * Operation |
* week of 4/30 * Operation continues. |
Line 113: | Line 103: |
||28||2018/5/1||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| || ||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/5/1(Tue.)
* Remote participants by eZuce: None * 4th day of Phase 1 operation
- TF of ETMX
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto + many
- DAC on PR3: Yamamoto
- PR3 DAC was dead. Reboot of k1pr3 fixed, but we are not sure the cause.
- lock lost was ~100min, including guardian misrecording.
- DAQ was dead 2-3min.
- Noise budged: *Tanioka, Izumi, Enomono
- PR2 oplev loop was improved, and MICH noise around 10-20Hz was improved.
- 100Hz noise seems to be dominated by beam position of BS or ETMY.
- DAC on PR3: Yamamoto
- TF of BS was well done.
- CBC injection was well done.
- DGS: *Miyakawa
- Timing signal was connected k1iy0 on Sunday, it requires a reboot of RT PC of k1iy0 once.
Work plan (*:responsible person)
- TF of Type A: Okutomi, Miyamoto
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/30
- Operation continues.
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)