2017/4/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}} |
2017/5/01 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180501.png||width=1200}} |
Line 24: | Line 24: |
* Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 |
|
Line 50: | Line 39: |
=== 2018/4/13(Fri.) === | === 2018/5/2(Wed.) === |
Line 52: | Line 41: |
* Remote participants by eZuce: Miyoki | * Remote participants by eZuce: None * 5th day of Phase 1 operation * Noise injection, CW injection * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] |
Line 55: | Line 48: |
* IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa * Last night, the beam from ETMX was lost caused by probably a shit at oplev. Installing a view port might introduce the shift on oplev yaw. * Centering of oplev was done this morning * Alignment was tuned IMC from 0.3/1.0->0.7/1.0 |
|
Line 60: | Line 49: |
* ETMY was improved a bit by Nakano. Now ~3urad. | * IFO: *Izumi, Enomoto + many * k1iy0 rebooted since timing was injected on Sunday. However coherence measurement had still problem. Missing digits of diaggui looking at k1iy0 might be a problem, but still the problem is not fixed. |
Line 62: | Line 52: |
* VAC: *Kimura * View port for oplev at ETMX was attached yesterday's afternoon. * All the preparation was done and the door of EXC was closed. |
* ETMX TF measurements: Miyamoto, Okutomi * 2/3 of TFs were measured well. 1/3 will be measured around the last stage of this operation if we have time. * Vibration isolation ratio was measured and matched to model pretty well. |
Line 68: | Line 59: |
* IFO: damping work or others. | |
Line 70: | Line 60: |
* VAC: *Kimura * Pumping down will start ~10am today. |
* PEM, noise injection: *Nagano, Tanaka, Miyo, Kozu, Hasegawa, Tanioka, Takano, Miyazaki, Kita, Yamamoto, Mori, Kaihotsu, Kurumiya, Ito, Tomaru, Yokozawa * CW injection |
Line 76: | Line 65: |
* IR: PSL, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 79: | Line 68: |
* IR: Upstream SR2-3 line, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 83: | Line 72: |
* IR: Upstream SR2-3 line, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 89: | Line 78: |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2. * Closing EXC. * Some controls for Michelson. * 4/13 morning: Pump down starts. * week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. * week of 4/23 * Operation |
* week of 4/30 * Operation continues. |
Line 117: | Line 95: |
||28||2018/5/1||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| || ||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/5/01 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/5/2(Wed.)
* Remote participants by eZuce: None * 5th day of Phase 1 operation
- Noise injection, CW injection
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto + many
- k1iy0 rebooted since timing was injected on Sunday. However coherence measurement had still problem. Missing digits of diaggui looking at k1iy0 might be a problem, but still the problem is not fixed.
- ETMX TF measurements: Miyamoto, Okutomi
- 2/3 of TFs were measured well. 1/3 will be measured around the last stage of this operation if we have time.
- Vibration isolation ratio was measured and matched to model pretty well.
Work plan (*:responsible person)
- PEM, noise injection: *Nagano, Tanaka, Miyo, Kozu, Hasegawa, Tanioka, Takano, Miyazaki, Kita, Yamamoto, Mori, Kaihotsu, Kurumiya, Ito, Tomaru, Yokozawa
- CW injection
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/30
- Operation continues.
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)