Revision 392 as of 2018-04-18 09:20:52
Size: 11847
Comment:
Revision 397 as of 2018-04-20 09:28:03
Size: 11650
Comment:
Deletions are marked like this. Additions are marked like this.
Line 50: Line 50:
=== 2018/4/18(Wed.) === === 2018/4/20(Fri.) ===
Line 55: Line 55:
 * Phase 1 operation was postponed to 4/28 start and 5/6 end.
Line 57: Line 58:
  * One of the small leak was found where it was, but another large leak seems to exist. Leak hunting will last today.
  * There are 3 ways;
   * Leak location will be found and fixed without vent. -> ETMX gate valve will open, no delay.
   * Leak location will be found and not fixed without vent. -> Vent on Wednesday and Thursday, fix leak on Friday, pump down on Friday. -> ETMX gate valve will open, delay for several days.
   * Leak location will not be found and not fixed. -> ETMX gate valve will not open, no delay, but it will be difficult to find beam at ETMX.
  * Leak was caused wrong positioned O-ring. The shape of O-ring was deformed.
  * Pump down started 15:50 yesterday.
  * Now vacuum gage shows ~30Pa.

 * VAC: *Inoue, Yokozawa
  * Vacuum monitor is ready! except for Y arm monitor.
Line 64: Line 66:
  * TF for MM coupling of photo sensor was found.
  * RMS motion seems to be OK if the mirror is not kicked. Even if the mirror is kicked, damping speed is ~10min or something.
  * 0.07Hz was damped well!
  * Yaw and pitch are < 1urad.
Line 69: Line 70:
  * Yaw dampins seems to be OK. Coupling between pitch and yaw exists. After ~10min or so, oscillation starts up to 10urad.   * Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow.
  * Possibility of heat link for 1.6Hz still remains.
  * Beam at REFL seemed to be OK.
Line 71: Line 74:
 * IFO: *Enomoto, Izumi
  * Trial lock of Michelson did not succeed because of too much motion of ETMY.

 * BS: Eleonora, Izumi
  * We are optimizing diagonalization of L2P filter. Needs more time.

 * DGS: *Yamamoto
  * Interface card for PCIe on k1ioo was exchanged and connection between RTPC and IO chassis was established again.
 * BS: *Eleonora, Izumi
  * Implementation of L2P filter worked well and they are well decoupled now!
  * Global injection point for length control is ready.
Line 84: Line 82:
 * IFO: Enomoto, Nakano  * IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
Line 88: Line 86:
  * Identifies the location of leak.   * Leak test will be performed and the gate valve will open on weekend if no problem.

 * Camera: *Inoue, Yokozawa
  * Tcam of Y end will be ready today.


 * We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday.
  * DMG needs some maintenance for DAQ.
Line 108: Line 114:
  * Leak check.
  * Opening the last gate valve.
  * Leak check, and fix leaks.
  * Opening the last gate valve weekend.
Line 112: Line 118:
  * Operation   * Michelson control.
  * 4/28 Operation start
Line 115: Line 122:

  * Large leak was found but it is not identified where it is.

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/17 updated KAGRA/Commissioning/Commissioning_schedule_20180417.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/20(Fri.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • Phase 1 operation was postponed to 4/28 start and 5/6 end.
  • VAC: *Kimura
    • Leak was caused wrong positioned O-ring. The shape of O-ring was deformed.
    • Pump down started 15:50 yesterday.
    • Now vacuum gage shows ~30Pa.
  • VAC: *Inoue, Yokozawa
    • Vacuum monitor is ready! except for Y arm monitor.
  • ETMX: *Hasegawa
    • 0.07Hz was damped well!
    • Yaw and pitch are < 1urad.

  • ETMY: *Nakano, Shishido
    • Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow.
    • Possibility of heat link for 1.6Hz still remains.
    • Beam at REFL seemed to be OK.
  • BS: *Eleonora, Izumi
    • Implementation of L2P filter worked well and they are well decoupled now!
    • Global injection point for length control is ready.

Work plan (*:responsible person)

  • IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
    • Damping, BS L2P, restoring alignment.
  • VAC: *Kimura
    • Leak test will be performed and the gate valve will open on weekend if no problem.
  • Camera: *Inoue, Yokozawa
    • Tcam of Y end will be ready today.
  • We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday.
    • DMG needs some maintenance for DAQ.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/16
    • Michelson control.
    • Leak check, and fix leaks.
    • Opening the last gate valve weekend.
  • week of 4/23
    • Michelson control.
    • 4/28 Operation start

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)