Size: 11255
Comment:
|
Size: 10748
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 24: | Line 24: |
* Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 |
|
Line 50: | Line 39: |
=== 2018/4/19(Thur.) === | === 2018/4/29(Sun.) === |
Line 52: | Line 41: |
* Remote participants by eZuce: Miyoki | * Remote participants by eZuce: None * 2nd day of Phase 1 operation * TF of Type A * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] |
Line 55: | Line 48: |
* Phase 1 operation was postponed to 4/28 start. | |
Line 57: | Line 49: |
* VAC: *Kimura * Large leak was found at the door on the cross tube, and started venting ~15:00. It takes almost one day to start fix the door, will be afternoon today. Pump down will start tomorrow morning. * Leak test will be performed on Sunday morning. |
* IFO: *Izumi, Enomoto + many * OLG was measured in the daytime. * Error of TF of actuator is ~20%. * 120usec delay exists in the MICH loop. * BS oplev sensitivity was improved by increasing whitening gain. * Longest lock of the last night was ~8hour. * Baffle PD signal is used to BS alignment. |
Line 61: | Line 57: |
* ETMX: *Hasegawa * Transfer function of TM to BF is being investigated. |
* 40Hz periodic noise was seen every 16min. It is air compressor. * It can be stopped during operation. * Timing to IY0 will be connected today. |
Line 64: | Line 61: |
* ETMY: *Nakano, Shishido * One of the 1.64 and 1.66 Hz peak was suppressed but other one was not. 1-2urad in yaw, 10urad in pitch. * RMS motion at REFL port is still dominated by ETMY. |
* WAB: Akutsu * Heater was turned off ~10am. |
Line 68: | Line 64: |
* BS: *Eleonora, Izumi * We are optimizing diagonalization of L2P filter. Needs more time. RMS ~urad |
* IYC: Tomaru * Cooler was turned off at 4pm and the vacuum level got worse to 1e-3Pa order. |
Line 74: | Line 70: |
* IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora * Damping, BS L2P, restoring alignment. |
* TF of Type A * Some of DOF of ETMY to L. |
Line 77: | Line 73: |
* VAC: *Kimura * To fix large and small leaks. |
|
Line 96: | Line 90: |
* week of 4/16 * Michelson control. * Leak check, and fix leaks. * week of 4/23 * Opening the last gate valve. * 4/28 Operation start |
* week of 4/30 * Operation continues. |
Line 105: | Line 94: |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/29(Sun.)
* Remote participants by eZuce: None * 2nd day of Phase 1 operation
- TF of Type A
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto + many
- OLG was measured in the daytime.
- Error of TF of actuator is ~20%.
- 120usec delay exists in the MICH loop.
- BS oplev sensitivity was improved by increasing whitening gain.
- Longest lock of the last night was ~8hour.
- Baffle PD signal is used to BS alignment.
- OLG was measured in the daytime.
- 40Hz periodic noise was seen every 16min. It is air compressor.
- It can be stopped during operation.
- Timing to IY0 will be connected today.
- WAB: Akutsu
- Heater was turned off ~10am.
- IYC: Tomaru
- Cooler was turned off at 4pm and the vacuum level got worse to 1e-3Pa order.
Work plan (*:responsible person)
- TF of Type A
- Some of DOF of ETMY to L.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/30
- Operation continues.
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools