Differences between revisions 397 and 398
Revision 397 as of 2018-04-20 09:28:03
Size: 11650
Comment:
Revision 398 as of 2018-04-25 09:29:26
Size: 11821
Comment:
Deletions are marked like this. Additions are marked like this.
Line 50: Line 50:
=== 2018/4/20(Fri.) === === 2018/4/25(Wed.) ===
Line 55: Line 55:
 * Phase 1 operation was postponed to 4/28 start and 5/6 end.
Line 57: Line 56:
 * VAC: *Kimura
  * Leak was caused wrong positioned O-ring. The shape of O-ring was deformed.
  * Pump down started 15:50 yesterday.
  * Now vacuum gage shows ~30Pa.
 * IFO: *Izumi, Enomoto, Nakano + many
  * Michelson lock lasted ~40min with Guardian.
   * ETMX had some drift. It may cause lock down.
Line 62: Line 60:
 * VAC: *Inoue, Yokozawa
  * Vacuum monitor is ready! except for Y arm monitor.
  * Modulation frequency was not tuned yet to iMC length.
   * Measurement of AM conversion can know the matching of mod. freq. to iMC length.
Line 65: Line 63:
 * ETMX: *Hasegawa
  * 0.07Hz was damped well!
  * Yaw and pitch are < 1urad.
  * PR3: Oplev has glitch. The laser source of oplev may be a cause. Needs fiber cleaner to exchange the laser.
Line 69: Line 65:
 * ETMY: *Nakano, Shishido
  * Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow.
  * Possibility of heat link for 1.6Hz still remains.
  * Beam at REFL seemed to be OK.
 * BS: *Eleonora, Izumi, Arai
  * BS IM feed back was engaged.
   * Target crossover was originally 3Hz but actual crossover was limited up to ~0.1Hz, because 1.25Hz peak disturbed control.
  * Gain of some loops of oplev servo changed stronger.
Line 74: Line 70:
 * BS: *Eleonora, Izumi
  * Implementation of L2P filter worked well and they are well decoupled now!
  * Global injection point for length control is ready.
 * CAL: *Yamamoto, Enomoto, Izumi
  * Optical measumremnt was measured.
  * Sensitivity is shown in the control room, being calculated from H(t).
Line 78: Line 74:
 * Injection: *Miyamoto, Yokozawa

 * Noise budget: *Michimura, Enomoto

 * IOO: *Kokeyama, Enomoto
  * MCE trans was clipped. Output PSL was going down to bottom direction, and it was a cause of clipping. This clipping does not affect to IFO control.

 * ETMX: *Hasegawa, Nakano, Enomoto
  * ETMX has some drift for 10-20urad.

 * ETMY: *Nakano, *Shishido, Ushiba, Miyamoto
  * ETMY need L damping.
  * Gardian was implemented.
Line 82: Line 91:
 * IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
  * Damping, BS L2P, restoring alignment.
 * BS: *Eleonora, Izumi, Arai
  * Opleve loop gains will change stronger.
Line 85: Line 94:
 * VAC: *Kimura
  * Leak test will be performed and the gate valve will open on weekend if no problem.
 * CAL: *Yamamoto, Enomoto, Izumi
  * Cal signal will be injected.
Line 88: Line 97:
 * Camera: *Inoue, Yokozawa
  * Tcam of Y end will be ready today.


 * We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday.
  * DMG needs some maintenance for DAQ.
 * IFO: *Izumi, Enomoto, Nakano + many
  * Measurement without locking morning, measurement with locking in the afternoon.
Line 111: Line 115:

 * week of 4/16
  * Michelson control.
  * Leak check, and fix leaks.
  * Opening the last gate valve weekend.

KAGRA Commissioning Wiki


Task list


Schedule

2017/4/17 updated KAGRA/Commissioning/Commissioning_schedule_20180417.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/4/25(Wed.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • IFO: *Izumi, Enomoto, Nakano + many
    • Michelson lock lasted ~40min with Guardian.
      • ETMX had some drift. It may cause lock down.
    • Modulation frequency was not tuned yet to iMC length.
      • Measurement of AM conversion can know the matching of mod. freq. to iMC length.
    • PR3: Oplev has glitch. The laser source of oplev may be a cause. Needs fiber cleaner to exchange the laser.
  • BS: *Eleonora, Izumi, Arai
    • BS IM feed back was engaged.
      • Target crossover was originally 3Hz but actual crossover was limited up to ~0.1Hz, because 1.25Hz peak disturbed control.
    • Gain of some loops of oplev servo changed stronger.
  • CAL: *Yamamoto, Enomoto, Izumi
    • Optical measumremnt was measured.
    • Sensitivity is shown in the control room, being calculated from H(t).
  • Injection: *Miyamoto, Yokozawa
  • Noise budget: *Michimura, Enomoto
  • IOO: *Kokeyama, Enomoto
    • MCE trans was clipped. Output PSL was going down to bottom direction, and it was a cause of clipping. This clipping does not affect to IFO control.
  • ETMX: *Hasegawa, Nakano, Enomoto
    • ETMX has some drift for 10-20urad.
  • ETMY: *Nakano, *Shishido, Ushiba, Miyamoto
    • ETMY need L damping.
    • Gardian was implemented.

Work plan (*:responsible person)

  • BS: *Eleonora, Izumi, Arai
    • Opleve loop gains will change stronger.
  • CAL: *Yamamoto, Enomoto, Izumi
    • Cal signal will be injected.
  • IFO: *Izumi, Enomoto, Nakano + many
    • Measurement without locking morning, measurement with locking in the afternoon.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/23
    • Michelson control.
    • 4/28 Operation start

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 5 >  >>
Mon Tue Wed Thu Fri Sat Sun
    1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 29 30 31    


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)