Line 50: | Line 50: |
=== 2018/4/20(Fri.) === | === 2018/4/26(Thur.) === |
Line 55: | Line 55: |
* Phase 1 operation was postponed to 4/28 start and 5/6 end. | |
Line 57: | Line 56: |
* VAC: *Kimura * Leak was caused wrong positioned O-ring. The shape of O-ring was deformed. * Pump down started 15:50 yesterday. * Now vacuum gage shows ~30Pa. * VAC: *Inoue, Yokozawa * Vacuum monitor is ready! except for Y arm monitor. * ETMX: *Hasegawa * 0.07Hz was damped well! * Yaw and pitch are < 1urad. * ETMY: *Nakano, Shishido * Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow. * Possibility of heat link for 1.6Hz still remains. * Beam at REFL seemed to be OK. * BS: *Eleonora, Izumi * Implementation of L2P filter worked well and they are well decoupled now! * Global injection point for length control is ready. |
* IFO: *Izumi, Enomoto + many * Michelson gardian was implemented. Lock is identified by the REFL and a tripped state of BS. * Lock lasts typically several of 10 minutes. * PR2 had a jump caused by a DAC glitch once a day. Sampling rate will be lowered? * PR3 also had jumps caused by DAC glitches. * Whitening filter was implemented at demodulated signal of RFPD. Sensitivity will be improved. * Modulation frequency was tuned to iMC length. Optical gain increased 1.4 times. |
Line 82: | Line 66: |
* IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora * Damping, BS L2P, restoring alignment. * VAC: *Kimura * Leak test will be performed and the gate valve will open on weekend if no problem. * Camera: *Inoue, Yokozawa * Tcam of Y end will be ready today. * We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday. * DMG needs some maintenance for DAQ. |
* IFO: *Izumi, Enomoto, Nakano + many * Measurement without locking morning, measurement with locking in the afternoon. |
Line 112: | Line 85: |
* week of 4/16 * Michelson control. * Leak check, and fix leaks. * Opening the last gate valve weekend. |
|
Line 122: | Line 90: |
* PR2 had a jump caused by a DAC glitch once a day. Sampling rate will be lowered? * PR3 also had jumps caused by DAC glitches. |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/26(Thur.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto + many
- Michelson gardian was implemented. Lock is identified by the REFL and a tripped state of BS.
- Lock lasts typically several of 10 minutes.
- PR2 had a jump caused by a DAC glitch once a day. Sampling rate will be lowered?
- PR3 also had jumps caused by DAC glitches.
- Whitening filter was implemented at demodulated signal of RFPD. Sensitivity will be improved.
- Modulation frequency was tuned to iMC length. Optical gain increased 1.4 times.
Work plan (*:responsible person)
- IFO: *Izumi, Enomoto, Nakano + many
- Measurement without locking morning, measurement with locking in the afternoon.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/23
- Michelson control.
- 4/28 Operation start
Issues
- PR2 had a jump caused by a DAC glitch once a day. Sampling rate will be lowered?
- PR3 also had jumps caused by DAC glitches.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools