Line 24: | Line 24: |
* Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 |
|
Line 50: | Line 39: |
=== 2018/4/20(Fri.) === | === 2018/4/29(Sun.) === |
Line 53: | Line 42: |
* 2nd day of Phase 1 operation * TF of Type A * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] |
|
Line 55: | Line 48: |
* Phase 1 operation was postponed to 4/28 start and 5/6 end. | |
Line 57: | Line 49: |
* VAC: *Kimura * Leak was caused wrong positioned O-ring. The shape of O-ring was deformed. * Pump down started 15:50 yesterday. * Now vacuum gage shows ~30Pa. |
* IFO: *Izumi, Enomoto + many * OLG was measured in the daytime. * Error of TF of actuator is ~20%. * 120usec delay exists in the MICH loop. * BS oplev sensitivity was improved by increasing whitening gain. * Longest lock of the last night was ~8hour. * Baffle PD signal is used to BS alignment. |
Line 62: | Line 57: |
* VAC: *Inoue, Yokozawa * Vacuum monitor is ready! except for Y arm monitor. |
* 40Hz periodic noise was seen every 16min. It is air compressor. * It can be stopped during operation. * Timing to IY0 will be connected today. |
Line 65: | Line 61: |
* ETMX: *Hasegawa * 0.07Hz was damped well! * Yaw and pitch are < 1urad. |
* WAB: Akutsu * Heater was turned off ~10am. |
Line 69: | Line 64: |
* ETMY: *Nakano, Shishido * Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow. * Possibility of heat link for 1.6Hz still remains. * Beam at REFL seemed to be OK. * BS: *Eleonora, Izumi * Implementation of L2P filter worked well and they are well decoupled now! * Global injection point for length control is ready. |
* IYC: Tomaru * Cooler was turned off at 4pm and the vacuum level got worse to 1e-3Pa order. |
Line 82: | Line 70: |
* IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora * Damping, BS L2P, restoring alignment. * VAC: *Kimura * Leak test will be performed and the gate valve will open on weekend if no problem. * Camera: *Inoue, Yokozawa * Tcam of Y end will be ready today. * We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday. * DMG needs some maintenance for DAQ. |
* TF of Type A * Some of DOF of ETMY to L. |
Line 112: | Line 90: |
* week of 4/16 * Michelson control. * Leak check, and fix leaks. * Opening the last gate valve weekend. * week of 4/23 * Michelson control. * 4/28 Operation start |
* week of 4/30 * Operation continues. |
Line 122: | Line 94: |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/29(Sun.)
* Remote participants by eZuce: None * 2nd day of Phase 1 operation
- TF of Type A
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto + many
- OLG was measured in the daytime.
- Error of TF of actuator is ~20%.
- 120usec delay exists in the MICH loop.
- BS oplev sensitivity was improved by increasing whitening gain.
- Longest lock of the last night was ~8hour.
- Baffle PD signal is used to BS alignment.
- OLG was measured in the daytime.
- 40Hz periodic noise was seen every 16min. It is air compressor.
- It can be stopped during operation.
- Timing to IY0 will be connected today.
- WAB: Akutsu
- Heater was turned off ~10am.
- IYC: Tomaru
- Cooler was turned off at 4pm and the vacuum level got worse to 1e-3Pa order.
Work plan (*:responsible person)
- TF of Type A
- Some of DOF of ETMY to L.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/30
- Operation continues.
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)