Differences between revisions 398 and 409 (spanning 11 versions)
Revision 398 as of 2018-04-25 09:29:26
Size: 11821
Comment:
Revision 409 as of 2018-05-01 10:37:20
Size: 10926
Comment:
Deletions are marked like this. Additions are marked like this.
Line 11: Line 11:
2017/4/17 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}}
2017/5/01 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180501.png||width=1200}}
Line 24: Line 24:
 * Laser, Ref''''''Cav, IMC: 苔山、中野
 * IMMT: 大石
 * VIS
  * Type Bp: 正田、三代
  * Type B: Mark
  * Type A: 奥富、宮本
 * Pico''''''Motor: 三代
 * Digital: 山本、宮川
 * 回路: 上泉、霜出
 * DC電源関連: 宮川
 * AC電源関連: 粟井
 * 水漏れなど: 古田、早河
Line 50: Line 39:
=== 2018/4/25(Wed.) === === 2018/5/1(Tue.) ===
Line 53: Line 42:
* 4th day of Phase 1 operation
 * TF of ETMX
 * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]]
Line 56: Line 49:
 * IFO: *Izumi, Enomoto, Nakano + many
  * Michelson lock lasted ~40min with Guardian.
   * ETMX had some drift. It may cause lock down.
 * IFO: *Izumi, Enomoto + many
  * DAC on PR3: Yamamoto
   * PR3 DAC was dead. Reboot of k1pr3 fixed, but we are not sure the cause.
   * lock lost was ~100min, including guardian misrecording.
   * DAQ was dead 2-3min.
Line 60: Line 55:
  * Modulation frequency was not tuned yet to iMC length.
   * Measurement of AM conversion can know the matching of mod. freq. to iMC length.
  * Noise budged: *Tanioka, Izumi, Enomono
   * PR2 oplev loop was improved, and MICH noise around 10-20Hz was improved.
   * 100Hz noise seems to be dominated by beam position of BS or ETMY.
Line 63: Line 59:
  * PR3: Oplev has glitch. The laser source of oplev may be a cause. Needs fiber cleaner to exchange the laser.  * TF of BS was well done.
 * CBC injection was well done.
Line 65: Line 62:
 * BS: *Eleonora, Izumi, Arai
  * BS IM feed back was engaged.
   * Target crossover was originally 3Hz but actual crossover was limited up to ~0.1Hz, because 1.25Hz peak disturbed control.
  * Gain of some loops of oplev servo changed stronger.

 * CAL: *Yamamoto, Enomoto, Izumi
  * Optical measumremnt was measured.
  * Sensitivity is shown in the control room, being calculated from H(t).

 * Injection: *Miyamoto, Yokozawa

 * Noise budget: *Michimura, Enomoto

 * IOO: *Kokeyama, Enomoto
  * MCE trans was clipped. Output PSL was going down to bottom direction, and it was a cause of clipping. This clipping does not affect to IFO control.

 * ETMX: *Hasegawa, Nakano, Enomoto
  * ETMX has some drift for 10-20urad.

 * ETMY: *Nakano, *Shishido, Ushiba, Miyamoto
  * ETMY need L damping.
  * Gardian was implemented.
 * DGS: *Miyakawa
  * Timing signal was connected k1iy0 on Sunday, it requires a reboot of RT PC of k1iy0 once.
Line 91: Line 67:
 * BS: *Eleonora, Izumi, Arai
  * Opleve loop gains will change stronger.
 * TF of Type A: Okutomi, Miyamoto
Line 94: Line 69:
 * CAL: *Yamamoto, Enomoto, Izumi
  * Cal signal will be injected.

 * IFO: *Izumi, Enomoto, Nakano + many
  * Measurement without locking morning, measurement with locking in the afternoon.
Line 116: Line 86:
 * week of 4/23
  * Michelson control.
  * 4/28
Operation start
 * week of 4/30
  * Operation continues.
Line 121: Line 90:
Line 133: Line 103:
||28||2018/5/1||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule

2017/5/01 updated KAGRA/Commissioning/Commissioning_schedule_20180501.png


Working people assignment

  • *: responsible person



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2018/5/1(Tue.)

* Remote participants by eZuce: None * 4th day of Phase 1 operation

Report of work (*:responsible person)

  • IFO: *Izumi, Enomoto + many
    • DAC on PR3: Yamamoto
      • PR3 DAC was dead. Reboot of k1pr3 fixed, but we are not sure the cause.
      • lock lost was ~100min, including guardian misrecording.
      • DAQ was dead 2-3min.
    • Noise budged: *Tanioka, Izumi, Enomono
      • PR2 oplev loop was improved, and MICH noise around 10-20Hz was improved.
      • 100Hz noise seems to be dominated by beam position of BS or ETMY.
  • TF of BS was well done.
  • CBC injection was well done.
  • DGS: *Miyakawa
    • Timing signal was connected k1iy0 on Sunday, it requires a reboot of RT PC of k1iy0 once.

Work plan (*:responsible person)

  • TF of Type A: Okutomi, Miyamoto

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/30
    • Operation continues.

Issues

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)