Size: 11289
Comment:
|
Size: 10606
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
2017/5/01 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180501.png||width=1200}} |
Line 39: | Line 39: |
=== 2018/4/27(Fri.) === | === 2018/5/7(Mon.) === |
Line 41: | Line 41: |
* Remote participants by eZuce: None | * Remote participants by eZuce: Miyoki * Operation of phase1 was done! * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] |
Line 45: | Line 49: |
* IFO: *Izumi, Enomoto + many * Michelson lock lasted longer than 2 and half hours! * Alignment control from IFO to ETMX was implemented by dithering ETMX. * RT models for PR2 and PR3 were down sampled from 16kHz to 2kHz. (Ushiba) * PR3 alignment was implemented by baffle signal. * ETMX damping might be a cause of lock lost. * ETMY yaw damping inclease pitch motion by coupling. It will be improved today.(Ushiba) * BS oplev is fed back to not only TM but also IM. (Arai) |
* IFO: *Enomoto + many * Lock was not stable due to an earthquake at Hachijo-jima. * Hammering at ETMY did not show any signal at the IFO signal. * TF of IM to TM of ETMX. |
Line 54: | Line 54: |
* WAB: *Akutsu * Heat consumption is estimated well. 10ppm produce 4W and it will be absorbed by WAB and now it is simulated by heater. * Equilibrium temperature was 21K. * Damping became to strong in low temperature. * SR: *Mark, Enzo, Tanioka, Kozu * Wire of RM was broken on SR3 during tightening clamp. There was no damage. * CAL: *Yamamoto * Line injection is being tested. * UGF serve will not be implemented, so change of optical gain is compensated in off line. * Operaton: * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] is opened. * Operation schedule and emergency contact list is put on the white board in the control room. |
* Shunup asymmetry: Enomoto * Result: asymmetry was estimated 3.8+/-1.4m. * It will be measured this morning again to reduce error bar. |
Line 72: | Line 60: |
* IFO: *Izumi, Enomoto, Nakano + many * Measurement without locking morning, measurement with locking in the afternoon. |
* VAC: *Uchiyama * 7 gate valve will open this morning. * Venting center area. |
Line 78: | Line 66: |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: None |
Line 81: | Line 69: |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: None |
Line 85: | Line 73: |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: None |
Line 91: | Line 79: |
* week of 4/23 * Michelson control. * 4/28 Operation start |
* week of 5/7 * 5/7 8-9am: Close 7 gate valves. |
Line 109: | Line 97: |
||28||2018/5/1||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/5/01 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/5/7(Mon.)
- Remote participants by eZuce: Miyoki
- Operation of phase1 was done!
Report of work (*:responsible person)
- IFO: *Enomoto + many
- Lock was not stable due to an earthquake at Hachijo-jima.
- Hammering at ETMY did not show any signal at the IFO signal.
- TF of IM to TM of ETMX.
- Shunup asymmetry: Enomoto
- Result: asymmetry was estimated 3.8+/-1.4m.
- It will be measured this morning again to reduce error bar.
Work plan (*:responsible person)
- VAC: *Uchiyama
- 7 gate valve will open this morning.
- Venting center area.
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: None
- [PM]
- IR: PSL, Yend 1F
- Green: None
- [night]
- IR: PSL, Yend 1F
- Green: None
Weekly
- week of 5/7
- 5/7 8-9am: Close 7 gate valves.
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 7 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
8 | 9 | 10 | 11 | 12 | 13 | 14 |
15 | 16 | 17 | 18 | 19 | 20 | 21 |
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools