Line 11: | Line 11: |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
2017/5/01 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180501.png||width=1200}} |
Line 39: | Line 39: |
=== 2018/5/1(Tue.) === | === 2018/5/8(Tue.) === |
Line 41: | Line 41: |
* Remote participants by eZuce: None * 4th day of Phase 1 operation * TF of ETMX * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] |
* Remote participants by eZuce: Miyoki |
Line 49: | Line 45: |
* IFO: *Izumi, Enomoto + many * DAC on PR3: Yamamoto * PR3 DAC was dead. Reboot of k1pr3 fixed, but we are not sure the cause. * lock lost was ~100min, including guardian misrecording. * DAQ was dead 2-3min. |
* VAC: *Uchiyama * 7 gate valve opened. * Venting started at the center area. * Yend cooling stopped. |
Line 55: | Line 50: |
* Noise budged: *Tanioka, Izumi, Enomono * PR2 oplev loop was improved, and MICH noise around 10-20Hz was improved. * 100Hz noise seems to be dominated by beam position of BS or ETMY. |
* Trial of release of ETMY f3 did not succeed. * Looked at power of oplev of ETMY during switch off of cooler, but it did not succeed because of power meter for high power. |
Line 59: | Line 53: |
* TF of BS was well done. * CBC injection was well done. |
|
Line 62: | Line 54: |
* DGS: *Miyakawa * Timing signal was connected k1iy0 on Sunday, it requires a reboot of RT PC of k1iy0 once. |
|
Line 67: | Line 57: |
* TF of Type A: Okutomi, Miyamoto |
|
Line 73: | Line 59: |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: None |
Line 76: | Line 62: |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: None |
Line 80: | Line 66: |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: None |
Line 86: | Line 72: |
* week of 4/30 * Operation continues. |
* week of 5/7 * 5/7 8-9am: Close 7 gate valves. |
Line 103: | Line 90: |
||29||2018/5/8||[[KAGRA/Commissioning/Weekly/20180508/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180508.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180508/Minute|Minute]]|| || ||28||2018/5/1||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/5/01 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/5/8(Tue.)
- Remote participants by eZuce: Miyoki
Report of work (*:responsible person)
- VAC: *Uchiyama
- 7 gate valve opened.
- Venting started at the center area.
- Yend cooling stopped.
- Trial of release of ETMY f3 did not succeed.
- Looked at power of oplev of ETMY during switch off of cooler, but it did not succeed because of power meter for high power.
Work plan (*:responsible person)
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: None
- [PM]
- IR: PSL, Yend 1F
- Green: None
- [night]
- IR: PSL, Yend 1F
- Green: None
Weekly
- week of 5/7
- 5/7 8-9am: Close 7 gate valves.
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)