4623
Comment:
|
10606
|
Deletions are marked like this. | Additions are marked like this. |
Line 3: | Line 3: |
== Task list == * [[KAGRA/Commissioning/Phase1/Task|Phase1]] * [[KAGRA/Commissioning/Phase2/Task|Phase2]] ----- == Schedule == 2017/5/01 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180501.png||width=1200}} ----- |
|
Line 4: | Line 17: |
* MIF + VIS | * *: responsible person |
Line 6: | Line 19: |
* 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か . |
{{{#!wiki comment/dotted ----- <<Anchor(EmergencyContactPerson)>> == Emergency contact person for subsystem == |
Line 13: | Line 24: |
. * 責任者 | }}} |
Line 15: | Line 27: |
<<Anchor(Meetings)>> |
|
Line 19: | Line 33: |
<<Anchor(MorningMeetings)>> | |
Line 22: | Line 37: |
* Location: Control room, or educe | * Location: Control room, or eZuce === 2018/5/7(Mon.) === * Remote participants by eZuce: Miyoki * Operation of phase1 was done! * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] |
Line 25: | Line 47: |
2017/10/20(Fri) | ==== Report of work (*:responsible person) ==== |
Line 27: | Line 49: |
* Daily * 作業人員(*:責任者) * MIF+VIS: *和泉、榎本、新井、正田、井上、灰野、横澤、土田、Fabian、Enzo、平田 (PHS: V-3(榎本), V-7(), V-12(横澤)) |
* IFO: *Enomoto + many * Lock was not stable due to an earthquake at Hachijo-jima. * Hammering at ETMY did not show any signal at the IFO signal. * TF of IM to TM of ETMX. |
Line 31: | Line 54: |
* Laser hazard * PSL直後で120mW、IMC出口で1000mW程度、PRM以降は10mW程度。 * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。中央実験室のSRラインより向こうににいる人はそれ以降全員保護メガネの着用をお願いします。 * Yエンド、Yアームに行く方は、最初にSRラインの安全パネルの前に置いてある保護メガネを使い通過して下さい。メガネはそのまま持って行って、帰りに中央エリアを通る際は再び保護メガネの着用をお願いします。 * EXA, EYAの真空槽まわりで作業する人は保護メガネをかけください。そばを通るだけの方は保護メガネは必要ありません。 |
* Shunup asymmetry: Enomoto * Result: asymmetry was estimated 3.8+/-1.4m. * It will be measured this morning again to reduce error bar. |
Line 37: | Line 58: |
* 作業 * アラインメント(和泉) * 日に日にアラインメントがずれているようだったので、Oplevをキャリブレーションし直した。IMMTなどファクター3とか10間違っていた。 * Xエンドまで光が通った。直接光かどうかはまだ不明。PDのゲイン調整と、センサーカードで確認予定。 * PR2が100urad程度揺れている模様。 * X/Y end * EXAにカメラがインストールされた。 * 200HzのノイズはLEDと判明。リモートでオンオフできないので、現在は消してある。 * EYAにもビューポーを設置した。EYAにもカメラをつけるかどうか検討する。(井上) |
==== Work plan (*:responsible person) ==== |
Line 47: | Line 60: |
* Weekly * 10/16の週の後半:PR3からの光をBSまで送る。さらにXエンドに送る。->ほぼ目標達成。 * 10/23の週: Yエンドに光を送る。 |
* VAC: *Uchiyama * 7 gate valve will open this morning. * Venting center area. |
Line 51: | Line 64: |
* 問題点など * コーチフィルターが不調。 |
==== Laser hazard ==== * [AM] * IR: PSL, Yend 1F * Green: None * [PM] * IR: PSL, Yend 1F * Green: None * [night] * IR: PSL, Yend 1F * Green: None ==== Weekly ==== * week of 5/7 * 5/7 8-9am: Close 7 gate valves. ==== Issues ==== |
Line 58: | Line 91: |
==== Weekly meeting ==== | <<Anchor(WeeklyMeetings)>> === Weekly meeting === |
Line 60: | Line 94: |
* Location: Meeting room at Hokum , or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| ||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
* Location: Meeting room at Hokubukaikan, or eZuce, Polycom ||No.||Date||Agenda||Schedule||Minute||Files|| || || || || || || || ||28||2018/5/1||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| || ||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || ||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| || ||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| || ||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| || ||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| || ||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| || ||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| || ||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || ||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| || ||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| || ||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| || ||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
Line 71: | Line 128: |
* Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]]) * Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]]) |
|
Line 72: | Line 137: |
* [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]] | |
Line 80: | Line 146: |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
* [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]] * wiki * Task list (Phase base, stage base) * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]]) * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]] * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]]) * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]] * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/5/01 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/5/7(Mon.)
- Remote participants by eZuce: Miyoki
- Operation of phase1 was done!
Report of work (*:responsible person)
- IFO: *Enomoto + many
- Lock was not stable due to an earthquake at Hachijo-jima.
- Hammering at ETMY did not show any signal at the IFO signal.
- TF of IM to TM of ETMX.
- Shunup asymmetry: Enomoto
- Result: asymmetry was estimated 3.8+/-1.4m.
- It will be measured this morning again to reduce error bar.
Work plan (*:responsible person)
- VAC: *Uchiyama
- 7 gate valve will open this morning.
- Venting center area.
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: None
- [PM]
- IR: PSL, Yend 1F
- Green: None
- [night]
- IR: PSL, Yend 1F
- Green: None
Weekly
- week of 5/7
- 5/7 8-9am: Close 7 gate valves.
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools