KAGRA Commissioning Wiki
Task list
Schedule
2017/4/10 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/11(Wed.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- IFO: Enomoto, Nagano, Nagano
- RF signal was extracted from fringe of Michelson.
- Ratio of ETMY and ETMX is not so large, roughly 1:1.
- We need more damping for both ETMY and ETMX.
- 4 front gate valve will be open.
- Power of coil driver is too small at ETMX marionette damping. It will be exchanged to HPCD.
- Camera: Yokozawa
- Illuminator at X end chamber was installed.
- DAQ: Miyakawa, Yamamoto
- k1tw0 started writing minute raw data.
Work plan (*:responsible person)
- Camera: Inoue, Yokozawa
- We check that nothing blocks the beam between EXA and EXC.
- DAQ: *Miyakawa
- Preparation to move writing minute raw of k1fw1 to a new k1tw1.
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: off
- [PM]
- IR: PSL, Yend 1F
- Green: off
- [night]
- IR: Upstream SR2-3 line, Yend 1F
- Green: off
Weekly
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC
- Some controls for Michelson
- 4/13~ Pump down
- week of 4/16
- Michelson control
- Leak check
- week of 4/23
- Operation
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 5 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | ||
6 | 7 | 8 | 9 | 10 | 11 | 12 |
13 | 14 | 15 | 16 | 17 | 18 | 19 |
20 | 21 | 22 | 23 | 24 | 25 | 26 |
27 | 28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)