== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
<<Anchor(Schedule)>>
=== Schedule ===

2018/10/9 updated


 * 8/16(Thur) 12:30 meeting at fan hut.
 * 8/23(Thur) 13:10 meeting at fan hut.
 * 8/30(Thur) 13:10 meeting at fan hut.
 * 9/10: 停電対策
 * 9/10, 11: 復電作業

 * ITMX:
  * 8/20の週: アルミホイルを外す。鏡の測定の位置確認、WABの設定。
  * 8/21: IPリリース、調整
  * 8/27(Mon) : Closing IXC、同日cryostatの掃除をする。
  * 8/28-30: NAB commissioning at IXA
  * 8/30(Wed) : Closing IXA by Mira-Pro
  * 8/30(Thur)夕方- : pump down、30日にポンプ一台で粗挽き、31日金曜日に本引き
  * 9/3-5: leak check
  * 9/11: IXC:φ800及びIXAのフランジ開け
  * 9/12,13~ メインビームのアラインメントをIXAで行う
  * 9/19: Type-Aを下げる。CRY立会い(牛場、都丸)
   * ~ 9/20: Type-A作業終了。もとの高さに戻す。CRY立会い(牛場、都丸)
  * 9/11-13 WAB finalize
   * 9/12 WAB温度計などの残り作業
   * 9/19 ITMX heat link防振 -> 牛場、山田
   * 9/25 プロテクター取り外し
   * その後WAB protector外し

  * 9/25~26: IXC:φ800及びIXAのフランジ閉止及び真空引き立ち上げ
  * 10/1~2: IXC 真空リーク試験
  * 10月4-5日: Xエンドフランジ封止及び真空排気
  * 10月3-11日: XフロントVIS部品交換作業
   * 10/3: 大気導入
   * 10/4: フランジ開放/部品交換
   * 10/4-5: Type-A towerリカバリー
   * 10/9: CRYによる最終調整・確認作業 
  * 10/10: AOSによるWABファイナライズ 
  * 10/11 or 12: フランジ閉止真空排気作業(業者発注)
  * 10/17~18: EXC 真空リーク試験


 * ETMX:
  * 8/31 冷凍機停止、真空引き続けて加温
  * 9/3 or 4 少しだけ大気開放
  * 9/5~ 中の様子を見て判断してフル大気開放
  * 9/7 大気開放ストップ
  * 9-8-10 放置
  * 9/11-10/3の期間EXCチェンバーが開く
  * 9/11大気開放直後:
   * PCalミラー設置(井上)
   * EXAの横の扉を開けて、PD設置(横澤)
  * 9/19 BRT運搬、それまでに通路撤去
  * 9/24 - 9/28:
   * PCalビームアラインメント(井上)
   * ETMXラフアラインメント(EXA内に入る、榎本)
   * EXCにBuffle PDインストール(榎本)
  * 10/11~12: EXC φ800フランジ閉止及び真空引き立ち上げ
  * 10/16~17: EXC 真空リーク試験

 * ITMY:
  * 10/19 鏡を神岡に輸送


-----
== Working people assignment ==
 * [[https://teamup.com/kswnmta8p18h6u1uab|KAGRA Commissioning Planner]]
  
{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==


}}}
-----

<<Anchor(Meetings)>>
-----
== Meetings ==

Zoom URL: [[https://zoom.us/j/8678936825|https://zoom.us/j/8678936825]]

----
<<Anchor(MorningMeetings)>>
=== Daily meeting ===

 * Date and time: Every weekday, 1PM
 * ~10min, as short as possible
 * Location: Control room and Fan hut connected by eZuce

=== 2018/10/18(Thur.) ===

==== Attendance ====
 * Control room: Miyakawa, Yamamoto, Yuzurihara, Miyo, nakano, Tanaka, Yokozawa, Oshino, Dankan, Lucia, Fujii, Yokogawa, Enomoto, Kokeyama
 * Fan hut:
 * eZuce:
 * Zoom: Hayakawa

==== Laser hazard ====

|||| ||Before 3PM||After 3PM ||
|||| || ||||
||Center||PSL ||IR & Green||IR & Green||
||Center||around PR2 ||IR & Green||IR & Green||
||Center||behinde SR2&Yfront||IR ||IR ||
||||X end 1F ||IR & Green||IR & Green||
||||Y end 1F ||N/A ||N/A ||

==== Night workers ====

 * MIF: Enomoto, Yokogawa, Kozakai

=== Weekend ===


==== Transition from morning work (*:responsible person) ====

 * IPs of ETMX are freely moving. Oplev at ETMX has still no light.
 * ITMX alignment seems to be fine already. We can see green light at REFL port.
 * Leak test is going on.

==== Report of work (*:responsible person) ====
 * KAGRA summary pages are available now.

==== Work plan (*:responsible person) ====

 * Green is hitting ETM. Alignment of ITM will be done.
 * Needs damping of ITMX and ETMX.
 * Marionet oplev light are not existing for both ITMX/ETMX.
  
<<MonthCalendar(KAGRA/Commissioning/DailyWork)>>


----
<<Anchor(WeeklyMeetings)>>
=== Weekly meeting ===
 * Date and time: Every Tuesday, 11AM
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom

||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||45||2018/10/9||[[KAGRA/Commissioning/Weekly/20181016/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181016/Minute|Minute]]|| ||
||45||2018/10/9||[[KAGRA/Commissioning/Weekly/20181009/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181009/Minute|Minute]]|| ||
||44||2018/10/2||[[KAGRA/Commissioning/Weekly/20181002/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181002/Minute|Minute]]|| ||
||43||2018/9/18||[[KAGRA/Commissioning/Weekly/20180918/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180918/Minute|Minute]]|| ||
||42||2018/9/4||[[KAGRA/Commissioning/Weekly/20180904/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180904/Minute|Minute]]|| ||
||41||2018/8/28||[[KAGRA/Commissioning/Weekly/20180828/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180828/Minute|Minute]]|| ||
||40||2018/8/21||[[KAGRA/Commissioning/Weekly/20180821/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180821.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180821/Minute|Minute]]|| ||
||39||2018/8/7||[[KAGRA/Commissioning/Weekly/20180807/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180807.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180807/Minute|Minute]]|| ||
||38||2018/7/31||[[KAGRA/Commissioning/Weekly/201807031/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180731.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180731/Minute|Minute]]|| ||
||37||2018/7/24||[[KAGRA/Commissioning/Weekly/201807024/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180724.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180724/Minute|Minute]]|| ||
||36||2018/7/17||[[KAGRA/Commissioning/Weekly/201807017/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180717.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180717/Minute|Minute]]|| ||
||35||2018/7/3||[[KAGRA/Commissioning/Weekly/20180703/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180703.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180703/Minute|Minute]]|| ||
||34||2018/6/26||[[KAGRA/Commissioning/Weekly/20180626/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180626.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180626/Minute|Minute]]|| ||
||33||2018/6/19||[[KAGRA/Commissioning/Weekly/20180619/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180619.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180619/Minute|Minute]]|| ||
||32||2018/6/12||[[KAGRA/Commissioning/Weekly/20180612/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180612.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180612/Minute|Minute]]|| ||
||31||2018/6/5||[[KAGRA/Commissioning/Weekly/20180605/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180605.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180605/Minute|Minute]]|| ||
||30||2018/5/22||[[KAGRA/Commissioning/Weekly/20180522/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180522.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180522/Minute|Minute]]|| ||
||29||2018/5/8||[[KAGRA/Commissioning/Weekly/20180508/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180508.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180508/Minute|Minute]]|| ||
||28||2018/5/1||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| ||
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
||19||2018/2/20||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||

----
=== Other meetings ===

 * 2018/9/3: Extended chief meeting for Arm commissioning [[/Meetings/Others/20180903/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20180903/Agenda/memo|Minute]]
 * 2018/8/30: 3rd Meeting for pump down at ITMX ([[/Meetings/Others/20180830|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]])
 * 2018/8/23: 2nd Meeting for pump down at ITMX ([[/Meetings/Others/20180823|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]])
 * 2018/8/16: Meeting for pump down at ITMX ([[/Meetings/Others/20180816|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]])
 * 2018/5/28: [[KAGRA/Commissioning/Meetings/Others/20180528/Phase1|Meeting for looking back to phase1 for future of KAGRA]] as an extended chief meeting.
 * 2018/4/11: Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * 2018/4/5: Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * 2018/3/14: Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])
 * 2018/1/18: Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * 2018/1/17: Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * 2018/1/10: Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * 2017/12/13: Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * 2017/11/27~12/1[[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]
 * 2017/11/17: Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
 * 2017/10/12: Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])


-----
== Documents ==
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for Phase1]]

== Communication tools ==

   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)



------
Line 6: Line 239:
 * [[KAGRA/Commissioning/ML|Joining commissioning mailing list]]  * [[KAGRA/Commissioning/ML|Joining commissioning Mailing List]]

KAGRA Commissioning Wiki


Task list


Schedule

2018/10/9 updated

  • 8/16(Thur) 12:30 meeting at fan hut.
  • 8/23(Thur) 13:10 meeting at fan hut.
  • 8/30(Thur) 13:10 meeting at fan hut.
  • 9/10: 停電対策
  • 9/10, 11: 復電作業
  • ITMX:
    • 8/20の週: アルミホイルを外す。鏡の測定の位置確認、WABの設定。
    • 8/21: IPリリース、調整
    • 8/27(Mon) : Closing IXC、同日cryostatの掃除をする。
    • 8/28-30: NAB commissioning at IXA
    • 8/30(Wed) : Closing IXA by Mira-Pro
    • 8/30(Thur)夕方- : pump down、30日にポンプ一台で粗挽き、31日金曜日に本引き
    • 9/3-5: leak check
    • 9/11: IXC:φ800及びIXAのフランジ開け

    • 9/12,13~ メインビームのアラインメントをIXAで行う
    • 9/19: Type-Aを下げる。CRY立会い(牛場、都丸)
      • ~ 9/20: Type-A作業終了。もとの高さに戻す。CRY立会い(牛場、都丸)
    • 9/11-13 WAB finalize
      • 9/12 WAB温度計などの残り作業
      • 9/19 ITMX heat link防振 -> 牛場、山田

      • 9/25 プロテクター取り外し
      • その後WAB protector外し
    • 9/25~26: IXC:φ800及びIXAのフランジ閉止及び真空引き立ち上げ

    • 10/1~2: IXC 真空リーク試験
    • 10月4-5日: Xエンドフランジ封止及び真空排気
    • 10月3-11日: XフロントVIS部品交換作業
      • 10/3: 大気導入
      • 10/4: フランジ開放/部品交換
      • 10/4-5: Type-A towerリカバリー
      • 10/9: CRYによる最終調整・確認作業 
    • 10/10: AOSによるWABファイナライズ 
    • 10/11 or 12: フランジ閉止真空排気作業(業者発注)
    • 10/17~18: EXC 真空リーク試験
  • ETMX:
    • 8/31 冷凍機停止、真空引き続けて加温
    • 9/3 or 4 少しだけ大気開放
    • 9/5~ 中の様子を見て判断してフル大気開放
    • 9/7 大気開放ストップ
    • 9-8-10 放置
    • 9/11-10/3の期間EXCチェンバーが開く
    • 9/11大気開放直後:
      • PCalミラー設置(井上)
      • EXAの横の扉を開けて、PD設置(横澤)
    • 9/19 BRT運搬、それまでに通路撤去
    • 9/24 - 9/28:
      • PCalビームアラインメント(井上)
      • ETMXラフアラインメント(EXA内に入る、榎本)
      • EXCにBuffle PDインストール(榎本)
    • 10/11~12: EXC φ800フランジ閉止及び真空引き立ち上げ
    • 10/16~17: EXC 真空リーク試験
  • ITMY:
    • 10/19 鏡を神岡に輸送


Working people assignment



Meetings

Zoom URL: https://zoom.us/j/8678936825


Daily meeting

  • Date and time: Every weekday, 1PM
  • ~10min, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2018/10/18(Thur.)

Attendance

  • Control room: Miyakawa, Yamamoto, Yuzurihara, Miyo, nakano, Tanaka, Yokozawa, Oshino, Dankan, Lucia, Fujii, Yokogawa, Enomoto, Kokeyama
  • Fan hut:
  • eZuce:
  • Zoom: Hayakawa

Laser hazard

Before 3PM

After 3PM

Center

PSL

IR & Green

IR & Green

Center

around PR2

IR & Green

IR & Green

Center

behinde SR2&Yfront

IR

IR

X end 1F

IR & Green

IR & Green

Y end 1F

N/A

N/A

Night workers

  • MIF: Enomoto, Yokogawa, Kozakai

Weekend

Transition from morning work (*:responsible person)

  • IPs of ETMX are freely moving. Oplev at ETMX has still no light.
  • ITMX alignment seems to be fine already. We can see green light at REFL port.
  • Leak test is going on.

Report of work (*:responsible person)

  • KAGRA summary pages are available now.

Work plan (*:responsible person)

  • Green is hitting ETM. Alignment of ITM will be done.
  • Needs damping of ITMX and ETMX.
  • Marionet oplev light are not existing for both ITMX/ETMX.

KAGRA/Commissioning/DailyWork
<< <  2024 / 4 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30          


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

45

2018/10/9

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1