Line 12: | Line 12: |
2018/8/28 updated | |
Line 26: | Line 25: |
* 9/5-7: IXC:φ800及びIXAのフランジ開け * 9/11~ どこかでメインビームのアラインメントをIXAで行う(横澤) |
* 9/11: IXC:φ800及びIXAのフランジ開け * 9/18,19~ メインビームのアラインメントをIXAで行う(横澤) |
Line 50: | Line 49: |
Line 77: | Line 75: |
=== 2018/8/28(Tue.) === | === 2018/9/4(Tue.) === |
Line 79: | Line 77: |
* PSL for high-power laser will finish by 8/31 and they provides the high power laser to the interferometer. * Actual night work will start 9/3 (9/1, 9/2 are weekends). * We will have a daily meeting on 9/3 that is the first day of night work managed by Izumi. * One Car (Serena) will be assigned to commissioning work. |
* We do not have night work today. |
Line 85: | Line 80: |
* Control room: Miyakawa, Yamamoto, Nakano, Kokeyama, Uchiyama | * Control room: |
Line 87: | Line 82: |
* educe: Enomoto, Ushiba, Kimura, Yokozawa, Suzuki | * educe: |
Line 91: | Line 86: |
|||| ||Before 3PM ||After 3PM|| |||| || |||| ||Center||PSL ||IR & Green||IR & Green|| ||Center||upstream IMM ||IR ||IR || ||Center||around PR2 ||IR & Green||IR & Green|| ||Center||behinde SR2-3 line||N/A ||IR || ||||X end 1F ||N/A ||N/A || ||||Y end 1F ||N/A ||N/A || |
|
Line 93: | Line 97: |
* Safety for the high power laser should be announced. * Furuta-san should attend this meeting to tell the laser hazard for Engineers. |
* We should discuss that we move IMMT1. |
Line 97: | Line 101: |
* IMMT moved to 2cm. | |
Line 99: | Line 104: |
* Laser will be shutdown on afternoon of 9/7. |
* N/A due to typhoon. |
Line 112: | Line 117: |
||42||2018/9/4||[[KAGRA/Commissioning/Weekly/20180904/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180904/Minute|Minute]]|| || | |
Line 157: | Line 163: |
* 2018/9/3: Extended chief meeting for Arm commissioning [[/Meetings/Others/20180903/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20180903/Minute|Minute]] | * 2018/9/3: Extended chief meeting for Arm commissioning [[/Meetings/Others/20180903/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20180903/Agenda/memo|Minute]] |
KAGRA Commissioning Wiki
Task list
Schedule
- 8/16(Thur) 12:30 meeting at fan hut.
- 8/23(Thur) 13:10 meeting at fan hut.
- 8/30(Thur) 13:10 meeting at fan hut.
- 9/10: 停電対策で真空関係の対応
- ITMX:
- 8/20の週: アルミホイルを外す。鏡の測定の位置確認、WABの設定。
- 8/21: IPリリース、調整
- 8/27(Mon) : Closing IXC、同日cryostatの掃除をする。
- 8/28-30: NAB commissioning at IXA
- 8/30(Wed) : Closing IXA by Mira-Pro
- 8/30(Thur)夕方- : pump down、30日にポンプ一台で粗挽き、31日金曜日に本引き
- 9/3-5: leak check
9/11: IXC:φ800及びIXAのフランジ開け
- 9/18,19~ メインビームのアラインメントをIXAで行う(横澤)
- 9/11-13 WAB finalize
9/25~26: IXC:φ800及びIXAのフランジ閉止及び真空引き立ち上げ
- 10/1~2: IXC 真空リーク試験
- ETMX:
- 8/31 冷凍機停止、真空引き続けて加温
- 9/3 or 4 少しだけ大気開放
- 9/5~ 中の様子を見て判断してフル大気開放
- 9/7 大気開放ストップ
- 9-8-10 放置
- 9/11-10/3の期間EXCチェンバーが開く
- 9/11大気開放直後:
- PCalミラー設置(井上)
- EXAの横の扉を開けて、PD設置(横澤)
- 9/18: Type-Aを下げる。CRY立会い(牛場、都丸)
- ~ 9/21: Type-A作業終了。もとの高さに戻す。CRY立会い(牛場、都丸)
- 9/24 - 9/28:
- PCalビームアラインメント(井上)
- ETMXラフアラインメント(EXA内に入る、榎本)
- EXCにBuffle PDインストール(榎本)
- 10/4~5: EXC φ800フランジ閉止及び真空引き立ち上げ
- 10/9~10: EXC 真空リーク試験、又は10/15~16: EXC 真空リーク試験
Working people assignment
Meetings
Daily meeting
- Date and time: Every weekday, 1PM
- ~10min, as short as possible
- Location: Control room and Fan hut connected by eZuce
2018/9/4(Tue.)
- We do not have night work today.
Attendance
- Control room:
- Fan hut:
- educe:
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
||
Center |
PSL |
IR & Green |
IR & Green |
Center |
upstream IMM |
IR |
IR |
Center |
around PR2 |
IR & Green |
IR & Green |
Center |
behinde SR2-3 line |
N/A |
IR |
X end 1F |
N/A |
N/A |
|
Y end 1F |
N/A |
N/A |
Transition from morning work (*:responsible person)
- We should discuss that we move IMMT1.
Report of work (*:responsible person)
- IMMT moved to 2cm.
Work plan (*:responsible person)
- N/A due to typhoon.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
|||
35 |
2018/7/3 |
|
|||
34 |
2018/6/26 |
|
|||
33 |
2018/6/19 |
|
|||
32 |
2018/6/12 |
|
|||
31 |
2018/6/5 |
|
|||
30 |
2018/5/22 |
|
|||
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
2018/9/3: Extended chief meeting for Arm commissioning Agenda, Minute
2018/8/30: 3rd Meeting for pump down at ITMX (Minute, Check list)
2018/8/23: 2nd Meeting for pump down at ITMX (Minute, Check list)
2018/8/16: Meeting for pump down at ITMX (Minute, Check list)
2018/5/28: Meeting for looking back to phase1 for future of KAGRA as an extended chief meeting.
2018/4/11: Meeting for pump down test at ETMX 2 (Minute, Check list)
2018/4/5: Meeting for pump down test at ETMX 1 (Minute, Check list)
2018/3/14: Meeting for pump down test at Center are (Minute, Check list)
2018/1/18: Meeting for pump down and cooling at ETMY3 (Minute, Check list)
2018/1/17: Meeting for pump down and cooling at ETMY2 (Minute, Check list)
2018/1/10: Meeting for pump down and cooling at ETMY1 (Minute, Check list)
2017/12/13: Meeting for pump down at ETMY (Minute, schedule)
2017/11/27~12/1Commissioning Workshop 2017
2017/11/17: Meeting for closing ETY (Minute)
2017/10/12: Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools