Line 12: | Line 12: |
2018/9/12 updated |
|
Line 16: | Line 18: |
* 9/10: 停電対策で真空関係の対応 | * 9/10: 停電対策 * 9/10, 11: 復電作業 |
Line 28: | Line 32: |
* 9/12 WAB温度計などの残り作業 * 9/19 ITMX heat link防振 -> 牛場、山田 * その後WAB protector外し |
|
Line 75: | Line 83: |
=== 2018/9/7(Fri.) === * How about the day and night work on Saturday or Sunday? |
=== 2018/9/12(Wed.) === |
Line 79: | Line 86: |
* Control room: Miyakawa, Eleonora. Licia, Fujii * Fan hut: Izumi, Takahashi(ICRR), Enomoto, Izumi, Akutsu * eZuce: Yokozawa |
* Control room: Miyakawa, Machimura, Enomoto, Yamamoto, Fujii, Miyo, Takeda, Oshino, * Fan hut: * eZuce: Kozakai |
Line 87: | Line 94: |
||Center||PSL ||IR & Green||IR & Green|| ||Center||upstream IMM ||IR ||IR || |
||Center||PSL ||IR ||IR & Green|| ||Center||upstream IMM ||IR ||IR & Green|| |
Line 91: | Line 98: |
||||X end 1F ||N/A ||IR & Green|| | ||||X end 1F ||N/A ||Green || |
Line 96: | Line 103: |
* Izumi, Enomoto, Eleonora, Yokozawa | * Enomoto, Michimura, Takeda, Yokogawa, Sugimoto, Kozakai, Darhan, Bin-hua |
Line 99: | Line 106: |
* ETMs, ITMs, BS, SR2 will be shutdown this afternoon. * PRMs and SR3, SRM will be shutdown later. * Laser will shutdown later. |
* Measurement of MZ was performed. * MC will be aligned until 3PM. |
Line 104: | Line 110: |
* Clean up the fiber coupler for ALS. * FSS did not work and it was tuned by Nakano and got locked. |
* Alignment for IR reached center of PR3. * Green hit the center of IXA. * Periscope alignment |
Line 109: | Line 115: |
* IR and Green will be overlapped. * Beams will reach X end today. * Cal green may reach X end. |
KAGRA Commissioning Wiki
Task list
Schedule
2018/9/12 updated
- 8/16(Thur) 12:30 meeting at fan hut.
- 8/23(Thur) 13:10 meeting at fan hut.
- 8/30(Thur) 13:10 meeting at fan hut.
- 9/10: 停電対策
- 9/10, 11: 復電作業
- ITMX:
- 8/20の週: アルミホイルを外す。鏡の測定の位置確認、WABの設定。
- 8/21: IPリリース、調整
- 8/27(Mon) : Closing IXC、同日cryostatの掃除をする。
- 8/28-30: NAB commissioning at IXA
- 8/30(Wed) : Closing IXA by Mira-Pro
- 8/30(Thur)夕方- : pump down、30日にポンプ一台で粗挽き、31日金曜日に本引き
- 9/3-5: leak check
9/11: IXC:φ800及びIXAのフランジ開け
- 9/18,19~ メインビームのアラインメントをIXAで行う(横澤)
- 9/11-13 WAB finalize
- 9/12 WAB温度計などの残り作業
9/19 ITMX heat link防振 -> 牛場、山田
- その後WAB protector外し
9/25~26: IXC:φ800及びIXAのフランジ閉止及び真空引き立ち上げ
- 10/1~2: IXC 真空リーク試験
- ETMX:
- 8/31 冷凍機停止、真空引き続けて加温
- 9/3 or 4 少しだけ大気開放
- 9/5~ 中の様子を見て判断してフル大気開放
- 9/7 大気開放ストップ
- 9-8-10 放置
- 9/11-10/3の期間EXCチェンバーが開く
- 9/11大気開放直後:
- PCalミラー設置(井上)
- EXAの横の扉を開けて、PD設置(横澤)
- 9/18: Type-Aを下げる。CRY立会い(牛場、都丸)
- ~ 9/21: Type-A作業終了。もとの高さに戻す。CRY立会い(牛場、都丸)
- 9/24 - 9/28:
- PCalビームアラインメント(井上)
- ETMXラフアラインメント(EXA内に入る、榎本)
- EXCにBuffle PDインストール(榎本)
- 10/4~5: EXC φ800フランジ閉止及び真空引き立ち上げ
- 10/9~10: EXC 真空リーク試験、又は10/15~16: EXC 真空リーク試験
Working people assignment
Meetings
Daily meeting
- Date and time: Every weekday, 1PM
- ~10min, as short as possible
- Location: Control room and Fan hut connected by eZuce
2018/9/12(Wed.)
Attendance
- Control room: Miyakawa, Machimura, Enomoto, Yamamoto, Fujii, Miyo, Takeda, Oshino,
- Fan hut:
- eZuce: Kozakai
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
||
Center |
PSL |
IR |
IR & Green |
Center |
upstream IMM |
IR |
IR & Green |
Center |
around PR2 |
IR & Green |
IR & Green |
Center |
behinde SR2-3 line |
N/A |
IR & Green |
X end 1F |
N/A |
Green |
|
Y end 1F |
N/A |
N/A |
Night workers
- Enomoto, Michimura, Takeda, Yokogawa, Sugimoto, Kozakai, Darhan, Bin-hua
Transition from morning work (*:responsible person)
- Measurement of MZ was performed.
- MC will be aligned until 3PM.
Report of work (*:responsible person)
- Alignment for IR reached center of PR3.
- Green hit the center of IXA.
- Periscope alignment
Work plan (*:responsible person)
- IR and Green will be overlapped.
- Beams will reach X end today.
- Cal green may reach X end.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
|||
35 |
2018/7/3 |
|
|||
34 |
2018/6/26 |
|
|||
33 |
2018/6/19 |
|
|||
32 |
2018/6/12 |
|
|||
31 |
2018/6/5 |
|
|||
30 |
2018/5/22 |
|
|||
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
2018/9/3: Extended chief meeting for Arm commissioning Agenda, Minute
2018/8/30: 3rd Meeting for pump down at ITMX (Minute, Check list)
2018/8/23: 2nd Meeting for pump down at ITMX (Minute, Check list)
2018/8/16: Meeting for pump down at ITMX (Minute, Check list)
2018/5/28: Meeting for looking back to phase1 for future of KAGRA as an extended chief meeting.
2018/4/11: Meeting for pump down test at ETMX 2 (Minute, Check list)
2018/4/5: Meeting for pump down test at ETMX 1 (Minute, Check list)
2018/3/14: Meeting for pump down test at Center are (Minute, Check list)
2018/1/18: Meeting for pump down and cooling at ETMY3 (Minute, Check list)
2018/1/17: Meeting for pump down and cooling at ETMY2 (Minute, Check list)
2018/1/10: Meeting for pump down and cooling at ETMY1 (Minute, Check list)
2017/12/13: Meeting for pump down at ETMY (Minute, schedule)
2017/11/27~12/1Commissioning Workshop 2017
2017/11/17: Meeting for closing ETY (Minute)
2017/10/12: Meeting about PR2 pitch misalignment (Minute)