Line 12: Line 12:
2018/9/18 updated
Line 15: Line 14:
 * 8/16(Thur) 12:30 meeting at fan hut.
 * 8/23(Thur) 13:10 meeting at fan hut.
 * 8/30(Thur) 13:10 meeting at fan hut.
 * 9/10: 停電対策
 * 9/10, 11: 復電作業
Line 21: Line 15:
 * ITMX:
  * 8/20の週: アルミホイルを外す。鏡の測定の位置確認、WABの設定。
  * 8/21: IPリリース、調整
  * 8/27(Mon) : Closing IXC、同日cryostatの掃除をする。
  * 8/28-30: NAB commissioning at IXA
  * 8/30(Wed) : Closing IXA by Mira-Pro
  * 8/30(Thur)夕方- : pump down、30日にポンプ一台で粗挽き、31日金曜日に本引き
  * 9/3-5: leak check
  * 9/11: IXC:φ800及びIXAのフランジ開け
  * 9/12,13~ メインビームのアラインメントをIXAで行う
  * 9/19: Type-Aを下げる。CRY立会い(牛場、都丸)
   * ~ 9/20: Type-A作業終了。もとの高さに戻す。CRY立会い(牛場、都丸)
  * 9/11-13 WAB finalize
   * 9/12 WAB温度計などの残り作業
   * 9/19 ITMX heat link防振 -> 牛場、山田
   * 9/25 プロテクター取り外し
   * その後WAB protector外し

  * 9/25~26: IXC:φ800及びIXAのフランジ閉止及び真空引き立ち上げ
  * 10/1~2: IXC 真空リーク試験

 * ETMX:
  * 8/31 冷凍機停止、真空引き続けて加温
  * 9/3 or 4 少しだけ大気開放
  * 9/5~ 中の様子を見て判断してフル大気開放
  * 9/7 大気開放ストップ
  * 9-8-10 放置
  * 9/11-10/3の期間EXCチェンバーが開く
  * 9/11大気開放直後:
   * PCalミラー設置(井上)
   * EXAの横の扉を開けて、PD設置(横澤)
  * 9/19 BRT運搬、それまでに通路撤去
  * 9/24 - 9/28:
   * PCalビームアラインメント(井上)
   * ETMXラフアラインメント(EXA内に入る、榎本)
   * EXCにBuffle PDインストール(榎本)
  * 10/4~5: EXC φ800フランジ閉止及び真空引き立ち上げ
  * 10/9~10: EXC 真空リーク試験、又は10/15~16: EXC 真空リーク試験

 * ITMY:
  * 10/19 鏡を神岡に輸送
Line 80: Line 33:
Zoom URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]]
Line 88: Line 43:
=== 2018/9/27(Thur.) === === 2018/11/6(Tue.) ===
Line 91: Line 46:
 * Control room: Miyakawa, Lucian, Anna, Oshino, Yamamoto, Kozakawa, Ogaki, Yokozawa
 * Fan hut: Furuta
 * eZuce:
 * Control room: Miyakawa, Nakano, Lucia, Oshino
 * Fan hut:
 * Zoom: Enomoto
Line 98: Line 53:
|||| || |||| |||| || || ||
Line 100: Line 55:
||Center||upstream IMM ||IR ||IR ||
Line 102: Line 56:
||Center||behinde SR2-3 line||N/A ||IR & Green||
||||X end 1F ||N/A      ||IR & Green||
||Center||behinde SR2&Yfront||IR ||IR       ||
||||X end 1F ||IR & Green||IR & Green||
Line 106: Line 60:
==== Night workers ==== ==== Night workers in the mine ====
Line 108: Line 62:
 * Commissioning: Izumi, Enomoto, Yokogawa, Sugimoto, Midooka
 * CAL: Kozakai, Ogai, Tomaru
 * MIF: Enomoto, Oshino

=== Weekend ===

 * Mio, Nakano, Enomoto
Line 112: Line 69:
 * Measurement of ETMX is going on until 3pm.
Line 115: Line 72:
 * EYA is opening now.
Line 119: Line 75:
 * Need ETMX calm, so AC will be stopped.  * After 5pm, fine alignment green and IR.
 * Beam is off centered in horizontal direction on ITMX.
Line 121: Line 78:
  
Line 133: Line 89:
||49||2018/11/5||[[KAGRA/Commissioning/Weekly/20181105/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181105/Minute|Minute]]|| ||
||48||2018/10/30||[[KAGRA/Commissioning/Weekly/20181030/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181030/Minute|Minute]]|| ||
||47||2018/10/23||[[KAGRA/Commissioning/Weekly/20181023/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181023/Minute|Minute]]|| ||
||46||2018/10/16||[[KAGRA/Commissioning/Weekly/20181016/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181016/Minute|Minute]]|| ||
||45||2018/10/9||[[KAGRA/Commissioning/Weekly/20181009/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181009/Minute|Minute]]|| ||
||44||2018/10/2||[[KAGRA/Commissioning/Weekly/20181002/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181002/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule


Working people assignment



Meetings

Zoom URL: https://zoom.us/j/7631499341


Daily meeting

  • Date and time: Every weekday, 1PM
  • ~10min, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2018/11/6(Tue.)

Attendance

  • Control room: Miyakawa, Nakano, Lucia, Oshino
  • Fan hut:
  • Zoom: Enomoto

Laser hazard

Before 3PM

After 3PM

Center

PSL

IR & Green

IR & Green

Center

around PR2

IR & Green

IR & Green

Center

behinde SR2&Yfront

IR

IR

X end 1F

IR & Green

IR & Green

Y end 1F

N/A

N/A

Night workers in the mine

  • MIF: Enomoto, Oshino

Weekend

  • Mio, Nakano, Enomoto

Transition from morning work (*:responsible person)

Report of work (*:responsible person)

Work plan (*:responsible person)

  • After 5pm, fine alignment green and IR.
  • Beam is off centered in horizontal direction on ITMX.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

49

2018/11/5

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)