Line 10: Line 10:
== Schedule ==
2017/7/3 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20180703.png||width=1200}}
<<Anchor(Schedule)>>
=== Schedule ===

Line 29: Line 30:
-----
Line 31: Line 32:

==== Daily Meetings (1PM) ====
Zoom URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]]

==== Weekly Meetings (Tuesday 11AM) ====
Zoom URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]]
Line 40: Line 47:
=== 2018/8/27(Mon.) ===

 * PSL for high-power laser will finish by 8/31 and they provides the high power laser to the interferometer.
 * Actual night work will start 9/3 (9/1, 9/2 are weekends).
 * We will have a daily meeting on 9/3 that is the first day of night work managed by Izumi.
 * One Car (Serena) will be assigned to commissioning work.
=== 2018/11/13(Tue.) ===
Line 48: Line 50:
 * Control room: Enomoto, Miyakawa, Ushiba
 * Fan hut:
 * educe:
----
==== Transition from morning work (*:responsible person) ====
 * Control room: Oshino, Enomoto, Lucia, Eleonora, Yokogawa, Sugimoto
 * Fan hut: Kozakai, Tomaru, Yamada, Ushiba, Tomigami, Akutsu
 * Zoom:

==== Laser hazard ====

|||| ||Before 3PM||After 3PM ||
|||| || || ||
||Center||PSL ||IR & Green||IR & Green||
||Center||around PR2 ||IR & Green||IR & Green||
||Center||behinde SR2&Yfront||IR ||IR ||
||||X end 1F ||IR & Green||IR & Green||
||||Y end 1F ||N/A ||N/A ||

==== Night workers in the mine ====

 * MIF: Enomoto, Miyoki, Yokogawa, Sugimoto
 * CAL: Kozakai, Tomigami

=== Weekend ===
Line 55: Line 73:
==== Transition from morning work (*:responsible person) ====

 * MZ was fixed. SR560 had AD couple.
Line 56: Line 78:
 * Alignment procedure was updated.
 *
Line 60: Line 81:
 * Watchdog of 4 coil driver for CRY should be removed.
 * optical setting of REFL table.
 * Let's close the analog CARM loop.
Line 73: Line 96:
||41||2018/8/28||[[KAGRA/Commissioning/Weekly/20180828/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180828.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180828/Minute|Minute]]|| || ||50||2018/11/13||[[KAGRA/Commissioning/Weekly/20181113/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181113/Minute|Minute]]|| ||
||49||2018/11/6||[[KAGRA/Commissioning/Weekly/20181105/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181105/Minute|Minute]]|| ||
||48||2018/10/30||[[KAGRA/Commissioning/Weekly/20181030/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181030/Minute|Minute]]|| ||
||47||2018/10/23||[[KAGRA/Commissioning/Weekly/20181023/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181023/Minute|Minute]]|| ||
||46||2018/10/16||[[KAGRA/Commissioning/Weekly/20181016/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181016/Minute|Minute]]|| ||
||45||2018/10/9||[[KAGRA/Commissioning/Weekly/20181009/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181009/Minute|Minute]]|| ||
||44||2018/10/2||[[KAGRA/Commissioning/Weekly/20181002/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181002/Minute|Minute]]|| ||
||43||2018/9/18||[[KAGRA/Commissioning/Weekly/20180918/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180918/Minute|Minute]]|| ||
||42||2018/9/4||[[KAGRA/Commissioning/Weekly/20180904/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180904/Minute|Minute]]|| ||
||41||2018/8/28||[[KAGRA/Commissioning/Weekly/20180828/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180828/Minute|Minute]]|| ||
Line 118: Line 150:
 * 2018/9/3: Extended chief meeting for Arm commissioning [[/Meetings/Others/20180903/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20180903/Minute|Minute]]
 * 2018/8/23: Meeting for pump down at ITMX ([[/Meetings/Others/20180823|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]])
 * 2018/9/3: Extended chief meeting for Arm commissioning [[/Meetings/Others/20180903/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20180903/Agenda/memo|Minute]]
 * 2018/8/30: 3rd Meeting for pump down at ITMX ([[/Meetings/Others/20180830|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]])
 * 2018/8/23: 2nd Meeting for pump down at ITMX ([[/Meetings/Others/20180823|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]])

KAGRA Commissioning Wiki


Task list


Schedule


Working people assignment


Meetings

Daily Meetings (1PM)

Zoom URL: https://zoom.us/j/7631499341

Weekly Meetings (Tuesday 11AM)

Zoom URL: https://zoom.us/j/6676627462


Daily meeting

  • Date and time: Every weekday, 1PM
  • ~10min, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2018/11/13(Tue.)

Attendance

  • Control room: Oshino, Enomoto, Lucia, Eleonora, Yokogawa, Sugimoto
  • Fan hut: Kozakai, Tomaru, Yamada, Ushiba, Tomigami, Akutsu
  • Zoom:

Laser hazard

Before 3PM

After 3PM

Center

PSL

IR & Green

IR & Green

Center

around PR2

IR & Green

IR & Green

Center

behinde SR2&Yfront

IR

IR

X end 1F

IR & Green

IR & Green

Y end 1F

N/A

N/A

Night workers in the mine

  • MIF: Enomoto, Miyoki, Yokogawa, Sugimoto
  • CAL: Kozakai, Tomigami

Weekend

Transition from morning work (*:responsible person)

  • MZ was fixed. SR560 had AD couple.

Report of work (*:responsible person)

Work plan (*:responsible person)

  • optical setting of REFL table.
  • Let's close the analog CARM loop.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

50

2018/11/13

Agenda

Minute

49

2018/11/6

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1