Line 51: | Line 51: |
=== 2019/1/17(Thur.) === | === 2019/1/23(Wed.) === |
Line 54: | Line 55: |
* Nakano, Enomoto: Some work for Y arm alignment. | |
Line 57: | Line 58: |
* We have maintenance today. |
* Schedule * Current status as of 1/22: IR and Green reached X end PD. * --(1/22 Surface inspection for PR mirrors.)-- Cleaning will be done after 1/31. * 1/22 or 23 Surface inspection for SR mirrors. * 1/23 Cleaning HR of SR2. * 1/23 BS will be aligned to Y-end PD by IR. * 1/24-25 ITMX will be aligned to REFL by IR. * 1/24-25 ITMY will be aligned to REFL by IR. * 1/26 Beam position of IR at SR3 will be confirmed how far from the center. * 1/28-29 SR3 will be aligned to SR2 center by IR. * 1/30 Green beam will be injected from SR2 AR surface to Y end PD. * 1/31-2/1 Removing bellows at PR and SR area. * 1/31-2/1 Cleaning HR of PR3 and AR of SR2 * 2/4-8 Alignment of SR2 -> SRM by IR, SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR * 2/4-8 Alignment of ETMY -> POS by Green * 2/12-15 Closing door for central area, pumping down * needs drift monitor for VIS |
Line 61: | Line 84: |
* IOO: MC was recovered. Finesse was almost the same as before or slightly. * VIS: PR2 was almost recovered. * BS is almost ready. * AOS: WAB is being installed, needs alignment or something today. * SR: Measured SR hight was a bit lower than expected. * CAL: Y end PCal noise was improved drastically by 130dB as the same way of X end. We needs some small modifications for model or something. * DGS: Maintenance for RFM did not succeed to connect all center and both two ends. Needs investigation today. * DGS: X end rack maintenance will finish this Friday or beginning of next week. * VAC: Aluminum foil was removed at Y front. Only simple cover is placed to SR direction. |
* BS: needs to be fixed or replaced the GEO Phone. * BS is ready for alignment to ETMY. * MIR: PR3, PR2, PRM were checked and it was found that PR3 was dirty. PR3 will be cleaned eventually ~2/2. * COM: we did some preparation for POS table. * PEM: Ondotori has been recovered. |
Line 74: | Line 91: |
* COMM: Alignment will start this afternoon from FI. We need some iteration of alignment and adjustment of OSEM etc. for PRs and BS. |
* COM: we tried BS alignment yesterday night but we did not succeed. We will try it today again with centering to ITMY. * MIR: Cleaning of SR2 will be done today. * AOS, COMM: we need install a view port on SR2 chamber. * ISS: needs to work on optical table. |
Line 89: | Line 108: |
||59||2019/1/29||[[KAGRA/Commissioning/Weekly/20190129/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190129/Minute|Minute]]|| || ||58||2019/1/22||[[KAGRA/Commissioning/Weekly/20190122/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190122/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
Working people assignment
Readiness for the X arm commissioning
https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing
Meetings
Daily Meetings (9AM)
Zoom URL: https://zoom.us/j/7631499341
Weekly Meetings (Tuesday 11AM)
Zoom URL: https://zoom.us/j/6676627462
Daily meeting
- Date and time: Every weekday, 9AM
- First ~10min in the morning meeting, as short as possible
- Location: Control room and Fan hut connected by eZuce
2019/1/23(Wed.)
Weekend
Transition from morning work (*:responsible person)
- Schedule
- Current status as of 1/22: IR and Green reached X end PD.
1/22 Surface inspection for PR mirrors. Cleaning will be done after 1/31.
- 1/22 or 23 Surface inspection for SR mirrors.
- 1/23 Cleaning HR of SR2.
- 1/23 BS will be aligned to Y-end PD by IR.
- 1/24-25 ITMX will be aligned to REFL by IR.
- 1/24-25 ITMY will be aligned to REFL by IR.
- 1/26 Beam position of IR at SR3 will be confirmed how far from the center.
- 1/28-29 SR3 will be aligned to SR2 center by IR.
- 1/30 Green beam will be injected from SR2 AR surface to Y end PD.
- 1/31-2/1 Removing bellows at PR and SR area.
- 1/31-2/1 Cleaning HR of PR3 and AR of SR2
2/4-8 Alignment of SR2 -> SRM by IR, SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR
2/4-8 Alignment of ETMY -> POS by Green
- 2/12-15 Closing door for central area, pumping down
- needs drift monitor for VIS
Report of work (*:responsible person)
- BS: needs to be fixed or replaced the GEO Phone.
- BS is ready for alignment to ETMY.
- MIR: PR3, PR2, PRM were checked and it was found that PR3 was dirty. PR3 will be cleaned eventually ~2/2.
- COM: we did some preparation for POS table.
- PEM: Ondotori has been recovered.
Work plan (*:responsible person)
- COM: we tried BS alignment yesterday night but we did not succeed. We will try it today again with centering to ITMY.
- MIR: Cleaning of SR2 will be done today.
- AOS, COMM: we need install a view port on SR2 chamber.
- ISS: needs to work on optical table.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
59 |
2019/1/29 |
|
|
||
58 |
2019/1/22 |
|
|
||
57 |
2019/1/8 |
|
|
||
56 |
2018/12/25 |
|
|
||
55 |
2018/12/17 |
|
|
||
54 |
2018/12/11 |
|
|
||
53 |
2018/12/4 |
|
|
||
52 |
2018/11/27 |
|
|
||
51 |
2018/11/20 |
|
|
||
50 |
2018/11/13 |
|
|
||
49 |
2018/11/6 |
|
|
||
48 |
2018/10/30 |
|
|
||
47 |
2018/10/23 |
|
|
||
46 |
2018/10/16 |
|
|
||
45 |
2018/10/9 |
|
|||
44 |
2018/10/2 |
|
|||
43 |
2018/9/18 |
|
|||
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
|||
35 |
2018/7/3 |
|
|||
34 |
2018/6/26 |
|
|||
33 |
2018/6/19 |
|
|||
32 |
2018/6/12 |
|
|||
31 |
2018/6/5 |
|
|||
30 |
2018/5/22 |
|
|||
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
2018/9/3: Extended chief meeting for Arm commissioning Agenda, Minute
2018/8/30: 3rd Meeting for pump down at ITMX (Minute, Check list)
2018/8/23: 2nd Meeting for pump down at ITMX (Minute, Check list)
2018/8/16: Meeting for pump down at ITMX (Minute, Check list)
2018/5/28: Meeting for looking back to phase1 for future of KAGRA as an extended chief meeting.
2018/4/11: Meeting for pump down test at ETMX 2 (Minute, Check list)
2018/4/5: Meeting for pump down test at ETMX 1 (Minute, Check list)
2018/3/14: Meeting for pump down test at Center are (Minute, Check list)
2018/1/18: Meeting for pump down and cooling at ETMY3 (Minute, Check list)
2018/1/17: Meeting for pump down and cooling at ETMY2 (Minute, Check list)
2018/1/10: Meeting for pump down and cooling at ETMY1 (Minute, Check list)
2017/12/13: Meeting for pump down at ETMY (Minute, schedule)
2017/11/27~12/1Commissioning Workshop 2017
2017/11/17: Meeting for closing ETY (Minute)
2017/10/12: Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools