Differences between revisions 599 and 608 (spanning 9 versions)
Revision 599 as of 2019-01-21 09:22:14
Size: 17394
Comment:
Revision 608 as of 2019-01-24 10:33:22
Size: 18608
Comment:
Deletions are marked like this. Additions are marked like this.
Line 52: Line 52:
=== 2019/1/21(Mon.) === === 2019/1/24(Thur.) ===
Line 55: Line 55:
 * Nakano, Enomoto, Yokozawa, Yokogawa, Tomaru, Ushiba Guiguo : Some work for Y arm alignment.
 * Sat: Nakano, Enomoto, Guiguo, Yokozawa, Sugimoto
 * Sun: Na
kano, Enomoto, Guiguo, Yokozawa
Line 59: Line 59:
 * Haibo starts joining commissioning work. He will stay 20days.
 * Schedule
  * Current status as of 1/22: IR and Green reached X end PD.
  * --(1/22 Surface inspection for PR mirrors.)-- Cleaning will be done after 1/31.
  * --(1/22 or 23 Surface inspection for SR mirrors.)--
  * 1/24-25 Cleaning HR of SRs.

  * --(1/23 BS is aligned to Y-end PD by IR.)--
  * 1/24-25 ITMY is aligned to REFL by IR.
  * 1/24-25 ITMX is aligned to REFL by IR.
  * 1/24-25 Beam position of IR at SR3 is confirmed how far from the center.

  * 1/28-29 SR3 is aligned to SR2 center by IR.
  * 1/30 Green beam is injected from SR2 AR surface to Y end PD.

  * 1/31-2/1 Removing bellows at PR and SR area.
  * 1/31-2/1 Cleaning HR of PR3 and AR of SR2

  * 2/4-8 Alignment of SR2 -> SRM by IR, SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR
  * 2/4-8 Alignment of ETMY -> POS by Green

  * 2/12-15 Closing door for central area, pumping down
   * needs drift monitor for VIS
Line 62: Line 85:

 * BS: something may be touching or some one of the actuation is not available. It was known by TF measurement.
  * GEO phone was something wrong, and it was replaced and it will be checked soon.
 * SR3(dust) and SR2(FC is left) is something dirty. Hirose-san will look at it on Tuesday.
 * COMM: PD installation at Yend.
  * IR and Green reached to ETMX.
  * It was found that PR3 surface was dirty. Hirose-san will look at it on Tuesday.

 * Ondotori was something wrong. Connector of power supply may be broken. It will be checked by Yokozawa-kun soon.
 * COM: IR beam reached at Y end
  * We checked Y-end PDA
  * Green beam for X arm was used for rough alignment of BS to center at ITMY
  * Then IR beam hit the Y end.

 * Type A:
  * IP position of ITMY is somehow OK, but stepping motor of BF or is not working well.
  * IP of ETMY is locked yesterday.

 * TYPE B: GEO phone amp was replaced and it seems to be fine. We need a little more time to replace other GEO phone.

 * MIR: HR of SRM cleaning is going on yesterday and today, HR of SR3 is the next.

 * DGS: RFM network is available for both X and Y arm.
  * CAM: k1cam0 was recovered.

 * OMC: It was found that the beam is blocked by Type C OSEM. We need some modifications at the frame.
Line 74: Line 104:

 * COM: Alignment of ITMY today.
 * Type A: Releasing ETMY lock.
Line 87: Line 120:
||59||2019/1/29||[[KAGRA/Commissioning/Weekly/20190129/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190129/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule


Working people assignment

Readiness for the X arm commissioning


Meetings

Daily Meetings (9AM)

Zoom URL: https://zoom.us/j/7631499341

Weekly Meetings (Tuesday 11AM)

Zoom URL: https://zoom.us/j/6676627462


Daily meeting

  • Date and time: Every weekday, 9AM
  • First ~10min in the morning meeting, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2019/1/24(Thur.)

Weekend

  • Sat: Nakano, Enomoto, Guiguo, Yokozawa, Sugimoto
  • Sun: Nakano, Enomoto, Guiguo, Yokozawa

Transition from morning work (*:responsible person)

  • Schedule
    • Current status as of 1/22: IR and Green reached X end PD.
    • 1/22 Surface inspection for PR mirrors. Cleaning will be done after 1/31.

    • 1/22 or 23 Surface inspection for SR mirrors.

    • 1/24-25 Cleaning HR of SRs.
    • 1/23 BS is aligned to Y-end PD by IR.

    • 1/24-25 ITMY is aligned to REFL by IR.
    • 1/24-25 ITMX is aligned to REFL by IR.
    • 1/24-25 Beam position of IR at SR3 is confirmed how far from the center.
    • 1/28-29 SR3 is aligned to SR2 center by IR.
    • 1/30 Green beam is injected from SR2 AR surface to Y end PD.
    • 1/31-2/1 Removing bellows at PR and SR area.
    • 1/31-2/1 Cleaning HR of PR3 and AR of SR2
    • 2/4-8 Alignment of SR2 -> SRM by IR, SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR

    • 2/4-8 Alignment of ETMY -> POS by Green

    • 2/12-15 Closing door for central area, pumping down
      • needs drift monitor for VIS

Report of work (*:responsible person)

  • COM: IR beam reached at Y end
    • We checked Y-end PDA
    • Green beam for X arm was used for rough alignment of BS to center at ITMY
    • Then IR beam hit the Y end.
  • Type A:
    • IP position of ITMY is somehow OK, but stepping motor of BF or is not working well.
    • IP of ETMY is locked yesterday.
  • TYPE B: GEO phone amp was replaced and it seems to be fine. We need a little more time to replace other GEO phone.
  • MIR: HR of SRM cleaning is going on yesterday and today, HR of SR3 is the next.
  • DGS: RFM network is available for both X and Y arm.
    • CAM: k1cam0 was recovered.
  • OMC: It was found that the beam is blocked by Type C OSEM. We need some modifications at the frame.

Work plan (*:responsible person)

  • COM: Alignment of ITMY today.
  • Type A: Releasing ETMY lock.

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

59

2019/1/29

Agenda

Minute

58

2019/1/22

Agenda

Minute

57

2019/1/8

Agenda

Minute

56

2018/12/25

Agenda

Minute

55

2018/12/17

Agenda

Minute

54

2018/12/11

Agenda

Minute

53

2018/12/4

Agenda

Minute

52

2018/11/27

Agenda

Minute

51

2018/11/20

Agenda

Minute

50

2018/11/13

Agenda

Minute

49

2018/11/6

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)