Line 52: | Line 52: |
=== 2019/1/21(Mon.) === | === 2019/2/28(Thur.) === === Schedule === * Center * --(2/26-27: Venting)-- * 2/28: Fixing PRM, PR3 and SRM * 2/29-5: Re-alignment * 3/5-6: Closing * Yend * --(1/25-2/20: Yend Pcal finalization)-- * 2/25-3/4: Yend WAB finalization * 3/5-6: Closing * 3/6~ : Yend pumpdown 3/6~ * 3/7,8: leak test * Xend * --(2/11-2/14: Xend NAB installation)-- * --(2/21: Removing FC, Payload release)-- * 2/23-3/10: Xend Pcal finalization 1 * Periscope installation * Beam position by IR and Green * 2/27: ETMX release * 3/5: ETMX aligned * 3/5-3/10: Xend Pcal finalization 2 * 3/11,12 Xend WAB finalization * 3/19,20, Heatlink etc. * 3/22 Pumping down * Leak test * 3/11~ : Night work starts * 2/18-3/22 DRMI commissioning * 3/11-4/5 Y arm commissioning * 3/25-4/5 FPMI commissioning ==== Note ==== * Takoyaki party at 6pm. |
Line 55: | Line 93: |
* Nakano, Enomoto, Yokozawa, Yokogawa, Tomaru, Ushiba Guiguo : Some work for Y arm alignment. ==== Transition from morning work (*:responsible person) ==== * Haibo starts joining commissioning work. He will stay 20days. ==== Report of work (*:responsible person) ==== * BS: something may be touching or some one of the actuation is not available. It was known by TF measurement. * GEO phone was something wrong, and it was replaced and it will be checked soon. * SR3(dust) and SR2(FC is left) is something dirty. Hirose-san will look at it on Tuesday. * COMM: PD installation at Yend. * IR and Green reached to ETMX. * It was found that PR3 surface was dirty. Hirose-san will look at it on Tuesday. * Ondotori was something wrong. Connector of power supply may be broken. It will be checked by Yokozawa-kun soon. ==== Work plan (*:responsible person) ==== |
==== Report of work ==== * PRM: Vibration measurement of cooler. * DGS: replaced RTPC of BS to V4 and PRM to V3. ==== Work plan ==== * VIS: Fixing PRM, PR3 and SRM * COM: Alignment of central area after tomorrow. |
Line 87: | Line 116: |
||61||2019/2/19||[[KAGRA/Commissioning/Weekly/20190219/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190219/Minute|Minute]]|| || ||60||2019/2/5||[[KAGRA/Commissioning/Weekly/20190205/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190205/Minute|Minute]]|| || ||59||2019/1/29||[[KAGRA/Commissioning/Weekly/20190129/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190129/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
Working people assignment
Readiness for the X arm commissioning
https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing
Meetings
Daily Meetings (9AM)
Zoom URL: https://zoom.us/j/7631499341
Weekly Meetings (Tuesday 11AM)
Zoom URL: https://zoom.us/j/6676627462
Daily meeting
- Date and time: Every weekday, 9AM
- First ~10min in the morning meeting, as short as possible
- Location: Control room and Fan hut connected by eZuce
2019/2/28(Thur.)
Schedule
- Center
2/26-27: Venting
- 2/28: Fixing PRM, PR3 and SRM
- 2/29-5: Re-alignment
- 3/5-6: Closing
- Yend
1/25-2/20: Yend Pcal finalization
- 2/25-3/4: Yend WAB finalization
- 3/5-6: Closing
- 3/6~ : Yend pumpdown 3/6~
- 3/7,8: leak test
- Xend
2/11-2/14: Xend NAB installation
2/21: Removing FC, Payload release
- 2/23-3/10: Xend Pcal finalization 1
- Periscope installation
- Beam position by IR and Green
- 2/27: ETMX release
- 3/5: ETMX aligned
- 3/5-3/10: Xend Pcal finalization 2
- 3/11,12 Xend WAB finalization
- 3/19,20, Heatlink etc.
- 3/22 Pumping down
- Leak test
- 3/11~ : Night work starts
- 2/18-3/22 DRMI commissioning
- 3/11-4/5 Y arm commissioning
- 3/25-4/5 FPMI commissioning
Note
- Takoyaki party at 6pm.
Weekend
Report of work
- PRM: Vibration measurement of cooler.
- DGS: replaced RTPC of BS to V4 and PRM to V3.
Work plan
- VIS: Fixing PRM, PR3 and SRM
- COM: Alignment of central area after tomorrow.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
61 |
2019/2/19 |
See agenda page |
|
||
60 |
2019/2/5 |
See agenda page |
|
||
59 |
2019/1/29 |
|
|
||
58 |
2019/1/22 |
|
|
||
57 |
2019/1/8 |
|
|
||
56 |
2018/12/25 |
|
|
||
55 |
2018/12/17 |
|
|
||
54 |
2018/12/11 |
|
|
||
53 |
2018/12/4 |
|
|
||
52 |
2018/11/27 |
|
|
||
51 |
2018/11/20 |
|
|
||
50 |
2018/11/13 |
|
|
||
49 |
2018/11/6 |
|
|
||
48 |
2018/10/30 |
|
|
||
47 |
2018/10/23 |
|
|
||
46 |
2018/10/16 |
|
|
||
45 |
2018/10/9 |
|
|||
44 |
2018/10/2 |
|
|||
43 |
2018/9/18 |
|
|||
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
|||
35 |
2018/7/3 |
|
|||
34 |
2018/6/26 |
|
|||
33 |
2018/6/19 |
|
|||
32 |
2018/6/12 |
|
|||
31 |
2018/6/5 |
|
|||
30 |
2018/5/22 |
|
|||
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
2018/9/3: Extended chief meeting for Arm commissioning Agenda, Minute
2018/8/30: 3rd Meeting for pump down at ITMX (Minute, Check list)
2018/8/23: 2nd Meeting for pump down at ITMX (Minute, Check list)
2018/8/16: Meeting for pump down at ITMX (Minute, Check list)
2018/5/28: Meeting for looking back to phase1 for future of KAGRA as an extended chief meeting.
2018/4/11: Meeting for pump down test at ETMX 2 (Minute, Check list)
2018/4/5: Meeting for pump down test at ETMX 1 (Minute, Check list)
2018/3/14: Meeting for pump down test at Center are (Minute, Check list)
2018/1/18: Meeting for pump down and cooling at ETMY3 (Minute, Check list)
2018/1/17: Meeting for pump down and cooling at ETMY2 (Minute, Check list)
2018/1/10: Meeting for pump down and cooling at ETMY1 (Minute, Check list)
2017/12/13: Meeting for pump down at ETMY (Minute, schedule)
2017/11/27~12/1Commissioning Workshop 2017
2017/11/17: Meeting for closing ETY (Minute)
2017/10/12: Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools