Line 52: Line 52:
=== 2019/1/22(Tue.) === === 2019/3/5(Tue.) ===

=== Schedule ===
 * Center
  * --(2/26-27: Venting)--
  * 2/28-3/5: Fixing PRMs and SRMs
  * 3/2-5: Re-alignment
  * 3/6-7: Closing

 * Yend
  * --(1/25-2/20: Yend Pcal finalization)--
  * 2/25-3/4: Yend WAB finalization
  * 3/5-6: Closing
  * 3/6~ : Yend pumpdown 3/6~
   * 3/7,8: leak test

 * Xend
  * --(2/11-2/14: Xend NAB installation)--
  * --(2/21: Removing FC, Payload release)--
   * --(2/27: ETMX release)--
  * 2/23-3/10: Xend Pcal finalization 1
   * Periscope installation
   * Beam position by IR and Green
  * 3/5: ETMX aligned
  * 3/5-3/10: Xend Pcal finalization 2
  * 3/11,12 Xend WAB finalization
  * 3/19,20, Heatlink etc.
  * 3/22 Pumping down
   * Leak test
 
 * 3/11~ : Night work starts

 * 2/18-3/22 DRMI commissioning
 * 3/11-4/5 Y arm commissioning
 * 3/25-4/5 FPMI commissioning

==== Note ====
Line 56: Line 92:

==== Transition from morning work (*:responsible person) ====
 * Haibo starts joining commissioning work. He will stay 20days.

==== Report of work (*:responsible person) ====

 * BS: Two cables were not connected well, so actuation was not correct when measuring TF day before yesterday.
  * TF was measured yesterday but still TF showed something different from the last correct measurement.
  * FR moved 800um.
  * Anyway alignment can be proceeded probably this afternoon.

 * CRY: we found disconnected cables at ITMX.

 * OMC: OMMT was aligned, and it was found that OSEM was touched somewhere.
 * PEM: Ondotori is still not working because of software issue.


==== Work plan (*:responsible person) ====

 * COMM: we will check PR3 first, then SR3.
  * Access to PR3 is quite difficult, gate valve needs to be removed or optical table needs to be fix.
  * we will decide whether we need clean the mirror surface or not.
  * Once mirror inspection and cleaning (if necessary), then will start alignment for REFL using reflected beam from ITMX.
 * COMM: PDA will be placed EYA.

 * SR3, SR2: height is OK. FR will be tuned.
  * SR3 surface will be inspected.
==== Report of work ====

 * PR3 was tuned once but oplev was gone again. Needs tuning one more day.
 * Type A: ETMX seems not healthy. To be fixed the next week.
 * Type B:Offset on IP of BS was seen but not real motion.
 * IOO: Beam damp for misalignment of PRM seems not working well. Mirror cannot be tilted well.
 * CAL: Pcal alignment was done. AOS will finish finalization. We need to confirm scheduling at sitework meeting or commissioning meeting.



==== Work plan ====
Line 96: Line 116:
||62||2019/3/5||[[KAGRA/Commissioning/Weekly/20190305/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190305/Minute|Minute]]|| ||
||61||2019/2/19||[[KAGRA/Commissioning/Weekly/20190219/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190219/Minute|Minute]]|| ||
||60||2019/2/5||[[KAGRA/Commissioning/Weekly/20190205/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190205/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule


Working people assignment

Readiness for the X arm commissioning


Meetings

Daily Meetings (9AM)

Zoom URL: https://zoom.us/j/7631499341

Weekly Meetings (Tuesday 11AM)

Zoom URL: https://zoom.us/j/6676627462


Daily meeting

  • Date and time: Every weekday, 9AM
  • First ~10min in the morning meeting, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2019/3/5(Tue.)

Schedule

  • Center
    • 2/26-27: Venting

    • 2/28-3/5: Fixing PRMs and SRMs
    • 3/2-5: Re-alignment
    • 3/6-7: Closing
  • Yend
    • 1/25-2/20: Yend Pcal finalization

    • 2/25-3/4: Yend WAB finalization
    • 3/5-6: Closing
    • 3/6~ : Yend pumpdown 3/6~
      • 3/7,8: leak test
  • Xend
    • 2/11-2/14: Xend NAB installation

    • 2/21: Removing FC, Payload release

      • 2/27: ETMX release

    • 2/23-3/10: Xend Pcal finalization 1
      • Periscope installation
      • Beam position by IR and Green
    • 3/5: ETMX aligned
    • 3/5-3/10: Xend Pcal finalization 2
    • 3/11,12 Xend WAB finalization
    • 3/19,20, Heatlink etc.
    • 3/22 Pumping down
      • Leak test
  • 3/11~ : Night work starts
  • 2/18-3/22 DRMI commissioning
  • 3/11-4/5 Y arm commissioning
  • 3/25-4/5 FPMI commissioning

Note

Weekend

Report of work

  • PR3 was tuned once but oplev was gone again. Needs tuning one more day.
  • Type A: ETMX seems not healthy. To be fixed the next week.
  • Type B:Offset on IP of BS was seen but not real motion.
  • IOO: Beam damp for misalignment of PRM seems not working well. Mirror cannot be tilted well.
  • CAL: Pcal alignment was done. AOS will finish finalization. We need to confirm scheduling at sitework meeting or commissioning meeting.

Work plan

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

62

2019/3/5

Agenda

See agenda page

Minute

61

2019/2/19

Agenda

See agenda page

Minute

60

2019/2/5

Agenda

See agenda page

Minute

59

2019/1/29

Agenda

Minute

58

2019/1/22

Agenda

Minute

57

2019/1/8

Agenda

Minute

56

2018/12/25

Agenda

Minute

55

2018/12/17

Agenda

Minute

54

2018/12/11

Agenda

Minute

53

2018/12/4

Agenda

Minute

52

2018/11/27

Agenda

Minute

51

2018/11/20

Agenda

Minute

50

2018/11/13

Agenda

Minute

49

2018/11/6

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)