Line 52: Line 52:
=== 2019/1/23(Wed.) === === 2019/3/7(Thur.) ===

=== Schedule ===
 * Center
  * --(2/26-27: Venting)--
  * 2/28-3/15: Health check and maintenance for VIS
   * --(PRM: One flag was dropped. -> leave it)--
   * 3/4-8 PRM: Misalignment does not reach where beam hits damper.
   * --(3/6 PR3: range -> incline by 20-30mrad at mirror because of bistable.)--
   * ~3/15 BS: Yaw offset adjustment by hand. -> 3/5-6

  * --(3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.)--
  * 3/18-19: Re-alignment
  * 3/19: Closing
  * 3/20: pump down

 * Yend
  * --(1/25-2/20: Yend Pcal finalization)--
  * --(3/5: EYA remaining works by Enomoto, Inoue.)--
  * --(2/25-3/4: Yend WAB finalization)--
   * 3/5: --(AOS EY)-- and EX(if they have time) work.
  * --(3/6: Y end closing (no laser hazard at least in the morning))--
  * 3/7: Y end pump down
   * 3/7,8: leak test

 * Xend
  * --(2/11-2/14: Xend NAB installation)--
  * --(2/21: Removing FC, Payload release)--
   * --(2/27: ETMX release)--
  * --(2/23-3/6: Xend Pcal finalization 1)--
   * --(Periscope installation)--
   * --(3/6: Beam position by IR and Green)--
  * --(3/5 AOS: EY and EX(if they have time) work.)--
  * --(3/6: Green X alignment (no IR), and no hazard at Y end.)--
  * 3/11, 18,19: Xend WAB finalization.
  * ~3/15: ETMX tuning.
  * 3/19: Heatlink etc.
  * 3/19: ETMX finalization by Takahashi
  * 3/18,19: ETMX alignement
  * 3/21 closing
  * 3/22 Pumping down
   * Leak test
 
 * 3/18~ : Night work starts, daily meeting will be moved to 1PM
  * Summary of work will last for a while in the morning meeting.

 * 2/18-3/22(?postponed): DRMI commissioning
 * 3/25-4/19: Y arm commissioning
 * 3/25-4/19: FPMI commissioning

==== Note ====
Line 56: Line 106:

==== Transition from morning work (*:responsible person) ====
 * Schedule
  * Current status as of 1/22: IR and Green reached X end PD.
  * 1/22 Surface inspection for PR mirrors. Cleaning will be done after 1/31.
  * 1/22 or 23 Surface inspection for SR mirrors.
  * 1/23-25 Cleaning HR of SR2.

  * 1/23 BS will be aligned to Y-end PD by IR.
  * 1/24-25 ITMX will be aligned to REFL by IR.
   * 1/24-25 ITMY will be aligned to REFL by IR.

  * 1/26 Beam position of IR at SR3 will be confirmed how far from the center.

  * 1/28-29 SR3 will be aligned to SR2 center by IR.
  * 1/30 Green beam will be injected from SR2 AR surface to Y end PD.

  * 1/31-2/1 Removing bellows at PR and SR area.
  * 1/31-2/1 Cleaning HR of PR3 and AR of SR2

  * 2/4-8 Alignment of SR2 -> SRM by IR, SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR
  * 2/4-8 Alignment of ETMY -> POS by Green

  * 2/12-15 Closing door for central area, pumping down
   * needs drift monitor for VIS


==== Report of work (*:responsible person) ====
 * BS: needs to be fixed or replaced the GEO Phone.
  * BS is ready for alignment to ETMY.
 * MIR: PR3, PR2, PRM were checked and it was found that PR3 was dirty. PR3 will be cleaned eventually ~2/2.
 * COM: we did some preparation for POS table.
 * PEM: Ondotori has been recovered.

==== Work plan (*:responsible person) ====
 * COM: we tried BS alignment yesterday night but we did not succeed. We will try it today again with centering to ITMY.
 * MIR: Cleaning of SR2 will be done today.
 * AOS, COMM: we need install a view port on SR2 chamber.
 * ISS: needs to work on optical table.
==== Report of work ====

 * Pump down for central area was postponed for 2 weeks.
 * Type B: BS still has some trouble, it was decided to open chamber again.
 * Type Bp: OSEMs were fixed, and it looks OK. Beam position on QPD was off. PRM needs more tuning and measurement. It will be done in the next week.
 * Y end temperature became low by 3 degree.
 * IOO: Found touching AOM driver and fork, and it was making a big group loop. Once it was released the noise became much smaller.



==== Work plan ====
 * Yend pump down start today.
Line 108: Line 131:
||62||2019/3/5||[[KAGRA/Commissioning/Weekly/20190305/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190305/Minute|Minute]]|| ||
||61||2019/2/19||[[KAGRA/Commissioning/Weekly/20190219/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190219/Minute|Minute]]|| ||
||60||2019/2/5||[[KAGRA/Commissioning/Weekly/20190205/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190205/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule


Working people assignment

Readiness for the X arm commissioning


Meetings

Daily Meetings (9AM)

Zoom URL: https://zoom.us/j/7631499341

Weekly Meetings (Tuesday 11AM)

Zoom URL: https://zoom.us/j/6676627462


Daily meeting

  • Date and time: Every weekday, 9AM
  • First ~10min in the morning meeting, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2019/3/7(Thur.)

Schedule

  • Center
    • 2/26-27: Venting

    • 2/28-3/15: Health check and maintenance for VIS
      • PRM: One flag was dropped. -> leave it

      • 3/4-8 PRM: Misalignment does not reach where beam hits damper.
      • 3/6 PR3: range -> incline by 20-30mrad at mirror because of bistable.

      • ~3/15 BS: Yaw offset adjustment by hand. -> 3/5-6

    • 3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.

    • 3/18-19: Re-alignment
    • 3/19: Closing
    • 3/20: pump down
  • Yend
    • 1/25-2/20: Yend Pcal finalization

    • 3/5: EYA remaining works by Enomoto, Inoue.

    • 2/25-3/4: Yend WAB finalization

      • 3/5: AOS EY and EX(if they have time) work.

    • 3/6: Y end closing (no laser hazard at least in the morning)

    • 3/7: Y end pump down
      • 3/7,8: leak test
  • Xend
    • 2/11-2/14: Xend NAB installation

    • 2/21: Removing FC, Payload release

      • 2/27: ETMX release

    • 2/23-3/6: Xend Pcal finalization 1

      • Periscope installation

      • 3/6: Beam position by IR and Green

    • 3/5 AOS: EY and EX(if they have time) work.

    • 3/6: Green X alignment (no IR), and no hazard at Y end.

    • 3/11, 18,19: Xend WAB finalization.
    • ~3/15: ETMX tuning.
    • 3/19: Heatlink etc.
    • 3/19: ETMX finalization by Takahashi
    • 3/18,19: ETMX alignement
    • 3/21 closing
    • 3/22 Pumping down
      • Leak test
  • 3/18~ : Night work starts, daily meeting will be moved to 1PM
    • Summary of work will last for a while in the morning meeting.
  • 2/18-3/22(?postponed): DRMI commissioning
  • 3/25-4/19: Y arm commissioning
  • 3/25-4/19: FPMI commissioning

Note

Weekend

Report of work

  • Pump down for central area was postponed for 2 weeks.
  • Type B: BS still has some trouble, it was decided to open chamber again.
  • Type Bp: OSEMs were fixed, and it looks OK. Beam position on QPD was off. PRM needs more tuning and measurement. It will be done in the next week.
  • Y end temperature became low by 3 degree.
  • IOO: Found touching AOM driver and fork, and it was making a big group loop. Once it was released the noise became much smaller.

Work plan

  • Yend pump down start today.

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

62

2019/3/5

Agenda

See agenda page

Minute

61

2019/2/19

Agenda

See agenda page

Minute

60

2019/2/5

Agenda

See agenda page

Minute

59

2019/1/29

Agenda

Minute

58

2019/1/22

Agenda

Minute

57

2019/1/8

Agenda

Minute

56

2018/12/25

Agenda

Minute

55

2018/12/17

Agenda

Minute

54

2018/12/11

Agenda

Minute

53

2018/12/4

Agenda

Minute

52

2018/11/27

Agenda

Minute

51

2018/11/20

Agenda

Minute

50

2018/11/13

Agenda

Minute

49

2018/11/6

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)