Line 52: Line 52:
=== 2019/2/6(Wed.) === === 2019/3/4(Mon.) ===

=== Schedule ===
 * Center
  * --(2/26-27: Venting)--
  * 2/28-3/5: Fixing PRMs and SRMs
  * 3/2-5: Re-alignment
  * 3/6-7: Closing

 * Yend
  * --(1/25-2/20: Yend Pcal finalization)--
  * 2/25-3/4: Yend WAB finalization
  * 3/5-6: Closing
  * 3/6~ : Yend pumpdown 3/6~
   * 3/7,8: leak test

 * Xend
  * --(2/11-2/14: Xend NAB installation)--
  * --(2/21: Removing FC, Payload release)--
   * --(2/27: ETMX release)--
  * 2/23-3/10: Xend Pcal finalization 1
   * Periscope installation
   * Beam position by IR and Green
  * 3/5: ETMX aligned
  * 3/5-3/10: Xend Pcal finalization 2
  * 3/11,12 Xend WAB finalization
  * 3/19,20, Heatlink etc.
  * 3/22 Pumping down
   * Leak test
 
 * 3/11~ : Night work starts

 * 2/18-3/22 DRMI commissioning
 * 3/11-4/5 Y arm commissioning
 * 3/25-4/5 FPMI commissioning

==== Note ====
Line 56: Line 92:
=== Schedule ===
  * Current status as of 1/22: IR and Green reached X end PD.
  * --(1/22: Surface inspection for PR mirrors.)-- Cleaning will be done after 1/31.
  * --(1/23: Surface inspection for SR mirrors.)--
  * --(1/24-25: Cleaning HR of SR3, SRM.)--

  * --(1/23: BS is aligned to Y-end PD by IR.)--
  * --(1/27: ITMY is aligned to REFL by IR.)--
  * --(1/27: ITMX is aligned to REFL by IR.)--
  * --(1/27: Beam position of IR at SR3 is confirmed how far from the center.)--

  * --(1/28-29: SR3 is aligned to SR2 center by IR.)--
  * --(1/28: Alignment of SR2 -> SRM by IR.)--
  * --(1/29: Green beam is injected from SR2 AR surface to Y end PD.)--

  * --(1/31: Removing bellows at PR and SR area.)--
  * --(1/31-2/1: Cleaning HR of PR3 and HR, AR of SR2)--

  * 2/5: --(Alignment of SRM to OMMT1 by IR)--
  * 2/6-8: OMMT -> OSTM by IR, OSTM -> OMC by IR
  * 2/6-8: Alignment of ETMY -> POS by Green

  * 2/12-15: Closing door for central area, pumping down
   * needs drift monitor for VIS

==== Note ====
 * Today is the last day of Wang-san.
 * Report klog, and gokagra ML if urgent things.
 * If you work other location from where it was confirmed at the morning meeting, please contact related poeple.

Line 88: Line 93:
 * Type B: Height of SRs were adjusted.
 * COM: Beam was aligned to OMMT1 but had 2-3cm off from center.
  * OMMT1 suspension will be moved on Friday.
  * Beam reached to OMMT2 already but off from the center in 2-3cm as the same oder as OMMT1.
 * ETMY: Mechanical trouble or something caused that ETMY did not work well. TF was something wrong.
 * Oplev beam of SR? was hit at edge of optical table but it was fixed.
 * SR models was splited.
 * Pcal: QPD at ETMY was installed.
 * Type B: Drifts of relative yaw on SRM are still lasting, but getting slower.
 * Type Bp: GAS filter keystone was almost touching something. PR3 looks healthy.
  * PR2 has some broken circuit for sensors.
  * One of the magnet on PRM was off.
  * some works inside the chamber still remains.

 * Type A: Alignment of IR to ETMX, and to ETMY, and Green to both ETM were done on Friday.
 * Type A: Some ETMX LVDT signals showed a 584Hz oscillation. It will be traced today.

 * CAL: EX alignment was done.
  * EX cryopayload had some strange signal. Connection will be checked again.

 * PEM: Ground vibration measurement is being continued. Air Conditioner was not a cause of the vibration.

Line 98: Line 110:
 * COM: ETMY alignment by green.
 * PCal: Needs little more ealignment.
Line 113: Line 123:
||61||2019/2/19||[[KAGRA/Commissioning/Weekly/20190219/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190219/Minute|Minute]]|| ||

KAGRA Commissioning Wiki


Task list


Schedule


Working people assignment

Readiness for the X arm commissioning


Meetings

Daily Meetings (9AM)

Zoom URL: https://zoom.us/j/7631499341

Weekly Meetings (Tuesday 11AM)

Zoom URL: https://zoom.us/j/6676627462


Daily meeting

  • Date and time: Every weekday, 9AM
  • First ~10min in the morning meeting, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2019/3/4(Mon.)

Schedule

  • Center
    • 2/26-27: Venting

    • 2/28-3/5: Fixing PRMs and SRMs
    • 3/2-5: Re-alignment
    • 3/6-7: Closing
  • Yend
    • 1/25-2/20: Yend Pcal finalization

    • 2/25-3/4: Yend WAB finalization
    • 3/5-6: Closing
    • 3/6~ : Yend pumpdown 3/6~
      • 3/7,8: leak test
  • Xend
    • 2/11-2/14: Xend NAB installation

    • 2/21: Removing FC, Payload release

      • 2/27: ETMX release

    • 2/23-3/10: Xend Pcal finalization 1
      • Periscope installation
      • Beam position by IR and Green
    • 3/5: ETMX aligned
    • 3/5-3/10: Xend Pcal finalization 2
    • 3/11,12 Xend WAB finalization
    • 3/19,20, Heatlink etc.
    • 3/22 Pumping down
      • Leak test
  • 3/11~ : Night work starts
  • 2/18-3/22 DRMI commissioning
  • 3/11-4/5 Y arm commissioning
  • 3/25-4/5 FPMI commissioning

Note

Weekend

Report of work

  • Type B: Drifts of relative yaw on SRM are still lasting, but getting slower.
  • Type Bp: GAS filter keystone was almost touching something. PR3 looks healthy.
    • PR2 has some broken circuit for sensors.
    • One of the magnet on PRM was off.
    • some works inside the chamber still remains.
  • Type A: Alignment of IR to ETMX, and to ETMY, and Green to both ETM were done on Friday.
  • Type A: Some ETMX LVDT signals showed a 584Hz oscillation. It will be traced today.
  • CAL: EX alignment was done.
    • EX cryopayload had some strange signal. Connection will be checked again.
  • PEM: Ground vibration measurement is being continued. Air Conditioner was not a cause of the vibration.

Work plan

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

61

2019/2/19

Agenda

See agenda page

Minute

60

2019/2/5

Agenda

See agenda page

Minute

59

2019/1/29

Agenda

Minute

58

2019/1/22

Agenda

Minute

57

2019/1/8

Agenda

Minute

56

2018/12/25

Agenda

Minute

55

2018/12/17

Agenda

Minute

54

2018/12/11

Agenda

Minute

53

2018/12/4

Agenda

Minute

52

2018/11/27

Agenda

Minute

51

2018/11/20

Agenda

Minute

50

2018/11/13

Agenda

Minute

49

2018/11/6

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1