20469
Comment:
|
18931
|
Deletions are marked like this. | Additions are marked like this. |
Line 45: | Line 45: |
=== Daily meeting === | == Daily meeting == |
Line 52: | Line 52: |
=== 2019/3/22(Fri.) === === Schedule === |
=== 2019/4/2(Tue.) === ==== Schedule ==== |
Line 56: | Line 56: |
* --(2/26-27: Venting)-- * 2/28-3/15: Health check and maintenance for VIS * --(PRM: One flag was dropped. -> leave it)-- * --(3/4-14 PRM: Misalignment does not reach where beam hits damper.)-- * --(3/6 PR3: range -> incline by 20-30mrad at mirror because of bistable.)-- * --(3/15: BS: Yaw offset adjustment by hand. -> 3/5-6)-- * --(3/12: BS ok)-- * --(3/15: some SRs work)-- * --(3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.)-- * --(3/18: Re-alignment)-- * --(3/19-21: Closing)-- * --(3/22: Pump down)-- * 3/26: Leak test |
* --(3/25: Venting)-- * 3/27-4/10: Fixing PR2 * 4/12: Closing and pump down |
Line 73: | Line 62: |
* 3/28: Opning chamber * 3/28: Fixing thermal touch * 3/29: closing chamber and start pumping down. * 4/1: Start cooling. |
* --(3/25: Venting start)-- * --(3/27: Opning chamber)-- * 3/27~: Fixing thermal touch * ~4/4: closing chamber and start pumping down. * 4/12: Cooling starts. * Xend * --(3/25: closing and pump down)-- * 4/12: Cooling start |
Line 79: | Line 73: |
* --(1/25-2/20: Yend Pcal finalization)-- * --(3/5: EYA remaining works by Enomoto, Inoue.)-- * --(2/25-3/5: Yend WAB finalization)-- * --(3/6: Y end closing (no laser hazard at least in the morning))-- * --(3/7: Y end pump down)-- * 3/22-23: leak test * 3/27: cooling start * Xend * --(2/11-2/14: Xend NAB installation)-- * --(2/21: Removing FC, Payload release)-- * --(2/27: ETMX release)-- * --(2/23-3/6: Xend Pcal finalization 1)-- * --(Periscope installation)-- * --(3/6: Beam position by IR and Green)-- * --(3/5 AOS: EY and EX(if they have time) work.)-- * --(3/6: Green X alignment (no IR), and no hazard at Y end.)-- * --(3/11, ~20: Xend WAB finalization.)-- * --(3/11~3/15: ETMX tuning.)-- * --(3/19: ETMX finalization by Takahashi)-- * --(3/18,19: ETMX alignement)-- * 3/23-24: Pcal alignment * 3/25: Removing PD * 3/25: closing and pump down * 4/2-4: Leak test * 3/27: Cooling start * 3/25~ : Night work officially starts, daily meeting will be moved to 1PM |
* --(3/26: Venting start)-- * --(3/28~: Fixing short inside chamber)-- * ~4/3: closing chamber and start pumping down. * 4/10: Cooling starts. * 4/1~ : Night work starts, daily meeting will be moved to 1PM |
Line 109: | Line 82: |
* 2/18-2/22: PRMI commissioning * 3/25~?: DRMI commissioning * 3/25-4/19: Y arm commissioning * 3/25-4/19: FPMI commissioning |
* End of April~: DRMI commissioning * End of April~: Y arm commissioning * ~End of May: FPMI commissioning |
Line 115: | Line 87: |
* Official night work starts 3/25, but not determined yet. * Please DO NOT close laser shutter, this is for long term measurement. Currently laser is stopped thin foil at the end of PSL. === Weekend === * Pcal: (Sat?, Sun) Alignment check at ETMX. * COM: (Sun) alignment work in the mine. |
* Official night work starts 4/8 or 4/15. ==== Weekend ==== * |
Line 123: | Line 93: |
* Type B: It was found that BS was necessary to fix some hight issue yesterday. * Center area, all the chambers were closed by the end of yesterday, and pump down has just started this morning. * COM: Alignment was done by the night of day before yesterday. * Type A: * ETMX has been confirmed that it is healthy. * ETMY: IP was something wrong and still alignment was not finished day before yesterday. * Motor had some problem, and it will be fixed. * Type B: SR2 oplev is being tuned in these days. |
* CRY: One of the refrigerator on ITMY was reset(tuned off and turned on), then temperature started going low. * One more refrigerator will be reset today. |
Line 137: | Line 97: |
* Drift for all PRMs BS and SRMs will be monitored by Fabian, Terrence and Mark. * Yend leak test will be done today. |
|
Line 148: | Line 106: |
* Location: Meeting room at Hokubukaikan, or eZuce, Polycom | * Location: Meeting room at Hokubukaikan, or Zoom |
Line 152: | Line 110: |
||65-1||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/TypeA_Agenda|Integrated Type-A meeting]]|| || || || ||65||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190402/Minute|Minute]]|||| ||64||2019/3/26||[[KAGRA/Commissioning/Weekly/20190326/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190326/Minute|Minute]]||[[attachment:KAGRA/Commissioning/20190326_avoding_delay.pptx|file]]|| |
KAGRA Commissioning Wiki
Task list
Schedule
Working people assignment
Readiness for the X arm commissioning
https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing
Meetings
Daily Meetings (9AM)
Zoom URL: https://zoom.us/j/7631499341
Weekly Meetings (Tuesday 11AM)
Zoom URL: https://zoom.us/j/6676627462
Daily meeting
- Date and time: Every weekday, 9AM
- First ~10min in the morning meeting, as short as possible
- Location: Control room and Fan hut connected by eZuce
2019/4/2(Tue.)
Schedule
- Center
3/25: Venting
- 3/27-4/10: Fixing PR2
- 4/12: Closing and pump down
- ITMX:
3/19: Cooling stop
3/25: Venting start
3/27: Opning chamber
- 3/27~: Fixing thermal touch
- ~4/4: closing chamber and start pumping down.
- 4/12: Cooling starts.
- Xend
3/25: closing and pump down
- 4/12: Cooling start
- Yend
3/26: Venting start
3/28~: Fixing short inside chamber
- ~4/3: closing chamber and start pumping down.
- 4/10: Cooling starts.
- 4/1~ : Night work starts, daily meeting will be moved to 1PM
- Summary of work will last for a while in the morning meeting.
- End of April~: DRMI commissioning
- End of April~: Y arm commissioning
- ~End of May: FPMI commissioning
Note
- Official night work starts 4/8 or 4/15.
Weekend
Report of work
- CRY: One of the refrigerator on ITMY was reset(tuned off and turned on), then temperature started going low.
- One more refrigerator will be reset today.
Work plan
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or Zoom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
65-1 |
2019/4/2 |
|
|
|
|
65 |
2019/4/2 |
See agenda page |
|||
64 |
2019/3/26 |
See agenda page |
|||
63 |
2019/3/11 |
See agenda page |
|
||
62 |
2019/3/5 |
See agenda page |
|
||
61 |
2019/2/19 |
See agenda page |
|
||
60 |
2019/2/5 |
See agenda page |
|
||
59 |
2019/1/29 |
|
|
||
58 |
2019/1/22 |
|
|
||
57 |
2019/1/8 |
|
|
||
56 |
2018/12/25 |
|
|
||
55 |
2018/12/17 |
|
|
||
54 |
2018/12/11 |
|
|
||
53 |
2018/12/4 |
|
|
||
52 |
2018/11/27 |
|
|
||
51 |
2018/11/20 |
|
|
||
50 |
2018/11/13 |
|
|
||
49 |
2018/11/6 |
|
|
||
48 |
2018/10/30 |
|
|
||
47 |
2018/10/23 |
|
|
||
46 |
2018/10/16 |
|
|
||
45 |
2018/10/9 |
|
|||
44 |
2018/10/2 |
|
|||
43 |
2018/9/18 |
|
|||
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
|||
35 |
2018/7/3 |
|
|||
34 |
2018/6/26 |
|
|||
33 |
2018/6/19 |
|
|||
32 |
2018/6/12 |
|
|||
31 |
2018/6/5 |
|
|||
30 |
2018/5/22 |
|
|||
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
2018/9/3: Extended chief meeting for Arm commissioning Agenda, Minute
2018/8/30: 3rd Meeting for pump down at ITMX (Minute, Check list)
2018/8/23: 2nd Meeting for pump down at ITMX (Minute, Check list)
2018/8/16: Meeting for pump down at ITMX (Minute, Check list)
2018/5/28: Meeting for looking back to phase1 for future of KAGRA as an extended chief meeting.
2018/4/11: Meeting for pump down test at ETMX 2 (Minute, Check list)
2018/4/5: Meeting for pump down test at ETMX 1 (Minute, Check list)
2018/3/14: Meeting for pump down test at Center are (Minute, Check list)
2018/1/18: Meeting for pump down and cooling at ETMY3 (Minute, Check list)
2018/1/17: Meeting for pump down and cooling at ETMY2 (Minute, Check list)
2018/1/10: Meeting for pump down and cooling at ETMY1 (Minute, Check list)
2017/12/13: Meeting for pump down at ETMY (Minute, schedule)
2017/11/27~12/1Commissioning Workshop 2017
2017/11/17: Meeting for closing ETY (Minute)
2017/10/12: Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools