Line 37: | Line 37: |
==== Daily Meetings (9AM) ==== | ==== Daily Meetings (9AM, 1PM) ==== |
Line 45: | Line 45: |
=== Daily meeting === | == Daily meeting == |
Line 52: | Line 52: |
=== 2019/2/6(Wed.) === === Weekend === === Schedule === * Current status as of 1/22: IR and Green reached X end PD. * --(1/22: Surface inspection for PR mirrors.)-- Cleaning will be done after 1/31. * --(1/23: Surface inspection for SR mirrors.)-- * --(1/24-25: Cleaning HR of SR3, SRM.)-- * --(1/23: BS is aligned to Y-end PD by IR.)-- * --(1/27: ITMY is aligned to REFL by IR.)-- * --(1/27: ITMX is aligned to REFL by IR.)-- * --(1/27: Beam position of IR at SR3 is confirmed how far from the center.)-- * --(1/28-29: SR3 is aligned to SR2 center by IR.)-- * --(1/28: Alignment of SR2 -> SRM by IR.)-- * --(1/29: Green beam is injected from SR2 AR surface to Y end PD.)-- * --(1/31: Removing bellows at PR and SR area.)-- * --(1/31-2/1: Cleaning HR of PR3 and HR, AR of SR2)-- * 2/5: --(Alignment of SRM to OMMT1 by IR)-- * 2/6-8: OMMT -> OSTM by IR, OSTM -> OMC by IR * 2/6-8: Alignment of ETMY -> POS by Green * 2/12-15: Closing door for central area, pumping down * needs drift monitor for VIS |
=== 2019/4/25(Thur.) === ==== Schedule ==== * Center * --(3/25: Venting)-- * --(3/27-4/9: Fixing PR2 or others)-- * --(4/4 -4/5: Gluing)-- * --(4/8: alignment check)-- * --(4/8-10: OSEM adjustment)-- * --(4/10: alignment check)-- * --(4/11: VIS final health check)-- * --(4/11-12: Closing)-- * --(4/12: Pump down)-- * 4/29,30: Leak check * ITMX: * --(3/19: Cooling stop)-- * --(3/25: Venting start)-- * --(3/27: Opning chamber)-- * --(3/27~: Fixing thermal touch)-- * --(4/2~: closing chamber and start pumping down)-- * --(4/10: Cooling starts.)-- * Xend * --(3/25: closing and pump down)-- * --(4/8: Leak check)-- * --(4/9-10: venting)-- * --(4/11: Exchange a broken LED for Photo sensor)-- * --(4/12: closing chamber and start pumping down)-- * --(4/22: Leak check)-- * --(4/22: vent)-- * --(4/24: fix oplev mirror)-- * --(4/25: Pumpdown)-- * 5/2: leak check * 5/2: Cooling start * Yend * --(3/26: Venting start)-- * --(3/28~: Fixing short inside chamber)-- * --(4/3: Fixing F0 actuator)-- * --(4/4~: closing chamber and start pumping down.)-- * --(4/10: Cooling starts.)-- * April: Measurement of TF, payload diagonalization on ITMX * End of April~: DRMI commissioning * End of April~: Y arm commissioning * ~End of May: FPMI commissioning |
Line 82: | Line 101: |
* Today is the last day of Wang-san. * Report klog, and gokagra ML if urgent things. * If you work other location from where it was confirmed at the morning meeting, please contact related poeple. |
* ==== Night work ==== * Y arm commissioning, from the control room. ==== Weekend ==== * Big holiday will start tomorrow. * CAL: 4/27 Yokozawa, Washimi in the mine. * Other work specially IFO work remotely from the control room will be proceeded: |
Line 88: | Line 112: |
* Type B: Height of SRs were adjusted. * COM: Beam was aligned to OMMT1 but had 2-3cm off from center. * OMMT1 suspension will be moved. * ETMY: Mechanical trouble or something caused that ETMY did not work well. TF was something wrong. * Oplev beam of SR? was hit at edge of optical table but it was fixed. * SR models was splited. * Pcal: QPD at ETMY was installed. |
* VAC: pumping down at ETMX started. -> monitor: Okutomi * Measured TF each point to L using IFO with green light. * Diagnalization of test mass will be going on. * Measurement for phase lock loop of Y arm will done by Sugimoto-kun, Enomoto-kun. * IOO: started the second loop ISS by Kuromiya-kun and Nakano-kun. |
Line 97: | Line 119: |
* COM: ETMY alignment by green. * PCal: Needs little more ealignment. |
* Type B: continuously improving Gardian code. |
Line 108: | Line 129: |
* Location: Meeting room at Hokubukaikan, or eZuce, Polycom | * Location: Meeting room at Hokubukaikan, or Zoom |
Line 112: | Line 133: |
||68||2019/4/23||[[KAGRA/Commissioning/Weekly/20190423/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190423/Minute|Minute]]|||| ||67||2019/4/16||[[KAGRA/Commissioning/Weekly/20190416/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190416/Minute|Minute]]|||| ||66||2019/4/9||[[KAGRA/Commissioning/Weekly/20190409/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190409/Minute|Minute]]|||| ||65-1||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/TypeA_Agenda|Integrated Type-A meeting]]|| || || || ||65||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190402/Minute|Minute]]|||| ||64||2019/3/26||[[KAGRA/Commissioning/Weekly/20190326/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190326/Minute|Minute]]||[[attachment:KAGRA/Commissioning/20190326_avoding_delay.pptx|file]]|| ||63||2019/3/11||[[KAGRA/Commissioning/Weekly/20190311/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190311/Minute|Minute]]|| || ||62||2019/3/5||[[KAGRA/Commissioning/Weekly/20190305/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190305/Minute|Minute]]|| || ||61||2019/2/19||[[KAGRA/Commissioning/Weekly/20190219/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190219/Minute|Minute]]|| || |
|
Line 176: | Line 206: |
* 2019/3/8: Scheduling for FPMI [[/Meetings/Others/20190308/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20190308|Minute]] |
KAGRA Commissioning Wiki
Task list
Schedule
Working people assignment
Readiness for the X arm commissioning
https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing
Meetings
Daily Meetings (9AM, 1PM)
Zoom URL: https://zoom.us/j/7631499341
Weekly Meetings (Tuesday 11AM)
Zoom URL: https://zoom.us/j/6676627462
Daily meeting
- Date and time: Every weekday, 9AM
- First ~10min in the morning meeting, as short as possible
- Location: Control room and Fan hut connected by eZuce
2019/4/25(Thur.)
Schedule
- Center
3/25: Venting
3/27-4/9: Fixing PR2 or others
4/4 -4/5: Gluing
4/8: alignment check
4/8-10: OSEM adjustment
4/10: alignment check
4/11: VIS final health check
4/11-12: Closing
4/12: Pump down
- 4/29,30: Leak check
- ITMX:
3/19: Cooling stop
3/25: Venting start
3/27: Opning chamber
3/27~: Fixing thermal touch
4/2~: closing chamber and start pumping down
4/10: Cooling starts.
- Xend
3/25: closing and pump down
4/8: Leak check
4/9-10: venting
4/11: Exchange a broken LED for Photo sensor
4/12: closing chamber and start pumping down
4/22: Leak check
4/22: vent
4/24: fix oplev mirror
4/25: Pumpdown
- 5/2: leak check
- 5/2: Cooling start
- Yend
3/26: Venting start
3/28~: Fixing short inside chamber
4/3: Fixing F0 actuator
4/4~: closing chamber and start pumping down.
4/10: Cooling starts.
- April: Measurement of TF, payload diagonalization on ITMX
- End of April~: DRMI commissioning
- End of April~: Y arm commissioning
- ~End of May: FPMI commissioning
Note
Night work
- Y arm commissioning, from the control room.
Weekend
- Big holiday will start tomorrow.
- CAL: 4/27 Yokozawa, Washimi in the mine.
- Other work specially IFO work remotely from the control room will be proceeded:
Report of work
VAC: pumping down at ETMX started. -> monitor: Okutomi
- Measured TF each point to L using IFO with green light.
- Diagnalization of test mass will be going on.
- Measurement for phase lock loop of Y arm will done by Sugimoto-kun, Enomoto-kun.
- IOO: started the second loop ISS by Kuromiya-kun and Nakano-kun.
Work plan
- Type B: continuously improving Gardian code.
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or Zoom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
68 |
2019/4/23 |
See agenda page |
|||
67 |
2019/4/16 |
See agenda page |
|||
66 |
2019/4/9 |
See agenda page |
|||
65-1 |
2019/4/2 |
|
|
|
|
65 |
2019/4/2 |
See agenda page |
|||
64 |
2019/3/26 |
See agenda page |
|||
63 |
2019/3/11 |
See agenda page |
|
||
62 |
2019/3/5 |
See agenda page |
|
||
61 |
2019/2/19 |
See agenda page |
|
||
60 |
2019/2/5 |
See agenda page |
|
||
59 |
2019/1/29 |
|
|
||
58 |
2019/1/22 |
|
|
||
57 |
2019/1/8 |
|
|
||
56 |
2018/12/25 |
|
|
||
55 |
2018/12/17 |
|
|
||
54 |
2018/12/11 |
|
|
||
53 |
2018/12/4 |
|
|
||
52 |
2018/11/27 |
|
|
||
51 |
2018/11/20 |
|
|
||
50 |
2018/11/13 |
|
|
||
49 |
2018/11/6 |
|
|
||
48 |
2018/10/30 |
|
|
||
47 |
2018/10/23 |
|
|
||
46 |
2018/10/16 |
|
|
||
45 |
2018/10/9 |
|
|||
44 |
2018/10/2 |
|
|||
43 |
2018/9/18 |
|
|||
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
|||
35 |
2018/7/3 |
|
|||
34 |
2018/6/26 |
|
|||
33 |
2018/6/19 |
|
|||
32 |
2018/6/12 |
|
|||
31 |
2018/6/5 |
|
|||
30 |
2018/5/22 |
|
|||
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
2018/9/3: Extended chief meeting for Arm commissioning Agenda, Minute
2018/8/30: 3rd Meeting for pump down at ITMX (Minute, Check list)
2018/8/23: 2nd Meeting for pump down at ITMX (Minute, Check list)
2018/8/16: Meeting for pump down at ITMX (Minute, Check list)
2018/5/28: Meeting for looking back to phase1 for future of KAGRA as an extended chief meeting.
2018/4/11: Meeting for pump down test at ETMX 2 (Minute, Check list)
2018/4/5: Meeting for pump down test at ETMX 1 (Minute, Check list)
2018/3/14: Meeting for pump down test at Center are (Minute, Check list)
2018/1/18: Meeting for pump down and cooling at ETMY3 (Minute, Check list)
2018/1/17: Meeting for pump down and cooling at ETMY2 (Minute, Check list)
2018/1/10: Meeting for pump down and cooling at ETMY1 (Minute, Check list)
2017/12/13: Meeting for pump down at ETMY (Minute, schedule)
2017/11/27~12/1Commissioning Workshop 2017
2017/11/17: Meeting for closing ETY (Minute)
2017/10/12: Meeting about PR2 pitch misalignment (Minute)