Line 3: Line 3:

== Task list ==

 * [[KAGRA/Commissioning/Phase1/Task|Phase1]]
 * [[KAGRA/Commissioning/Phase2/Task|Phase2]]

-----
<<Anchor(Schedule)>>
=== Schedule ===




-----
Line 4: Line 18:
 * MIF + VIS  * [[https://teamup.com/kswnmta8p18h6u1uab|KAGRA Commissioning Planner]]

== Readiness for the X arm commissioning ==
 * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]]
Line 6: Line 24:
  * 10/20 *和泉、横澤、井上、榎本、中野、麻生、Fabian、Enzo、平田、神津、新井
  .
  * 10/23 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/24 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/25 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/26 *和泉、井上、中野、麻生、神津、新井 + Type-B誰か
  * 10/27 *井上、中野、麻生、神津、新井 + Type-B誰か

 . * 責任者
-----
-----
{{{#!wiki comment/dotted
-----
<<Anchor(EmergencyContactPerson)>>
== Emergency contact person for subsystem ==


}}}
-----

<<Anchor(Meetings)>>
Line 19: Line 37:
==== Daily Meetings (9AM, 1PM) ====
Zoom URL: [[https://zoom.us/j/7631499341|https://zoom.us/j/7631499341]]

==== Weekly Meetings (Tuesday 11AM) ====
Zoom URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]]
Line 20: Line 44:
=== Morning meeting === <<Anchor(MorningMeetings)>>
== Daily
meeting ==
Line 23: Line 48:
 * Location: Control room, or educe


2017/10/20(Fri)

 * Daily
  * 作業人員(*:責任者)
   * MIF+VIS: *和泉、榎本、新井、正田、井上、灰野、横澤、土田、Fabian、Enzo、平田 (PHS: V-3(榎本), V-7(), V-12(横澤))

  * Laser hazard
   * PSL直後で120mW、IMC出口で1000mW程度、PRM以降は10mW程度。
   * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。中央実験室のSRラインより向こうににいる人はそれ以降全員保護メガネの着用をお願いします。
   * Yエンド、Yアームに行く方は、最初にSRラインの安全パネルの前に置いてある保護メガネを使い通過して下さい。メガネはそのまま持って行って、帰りに中央エリアを通る際は再び保護メガネの着用をお願いします。
   * EXA, EYAの真空槽まわりで作業する人は保護メガネをかけください。そばを通るだけの方は保護メガネは必要ありません。

  * 作業
   * アラインメント(和泉)
    * 日に日にアラインメントがずれているようだったので、Oplevをキャリブレーションし直した。IMMTなどファクター3とか10間違っていた。
    * Xエンドまで光が通った。直接光かどうかはまだ不明。PDのゲイン調整と、センサーカードで確認予定。
    * PR2が100urad程度揺れている模様。
   * X/Y end
    * EXAにカメラがインストールされた。
    * 200HzのノイズはLEDと判明。リモートでオンオフできないので、現在は消してある。
    * EYAにもビューポーを設置した。EYAにもカメラをつけるかどうか検討する。(井上)

 * Weekly
  * 10/16の週の後半:PR3からの光をBSまで送る。さらにXエンドに送る。->ほぼ目標達成。
  * 10/23の週: Yエンドに光を送る。

 * 問題点など
  * コーチフィルターが不調。
 * First ~10min in the morning meeting, as short as possible
 * Location: Control room and Fan hut connected by eZuce


=== 2019/4/10(Wed.) ===

==== Schedule ====
 * Center
  * --(3/25: Venting)--
  * 3/27-4/9: Fixing PR2
   * --(4/4 -4/5: Gluing)--
   * 4/8: alignment check
   * 4/8-10: OSEM adjustment
  * 4/11-12: Closing
  * 4/12: Pump down
  * 4/15~: Leak check

 * ITMX:
  * --(3/19: Cooling stop)--
  * --(3/25: Venting start)--
  * --(3/27: Opning chamber)--
  * --(3/27~: Fixing thermal touch)--
  * --(4/2~: closing chamber and start pumping down)--
  * 4/12: Cooling starts.

 * Xend
  * --(3/25: closing and pump down)--
  * --(4/8: Leak check)--
  * 4/9-10: venting
  * 4/11: Exchange a broken LED for Photo sensor
  * 4/12: closing chamber and start pumping down
  * 4/15: Leak check
  * 4/19(or 22): Cooling start

 * Yend
  * --(3/26: Venting start)--
  * --(3/28~: Fixing short inside chamber)--
  * --(4/3: Fixing F0 actuator)--
  * --(4/4~: closing chamber and start pumping down.)--
  * 4/12: Cooling starts.


 * 4/8: Daily meeting will be moved to 1PM
  * Summary of work will last for a while in the morning meeting.

 * April: Measurement of TF, payload diagonalization on ITMX
 * End of April~: DRMI commissioning
 * End of April~: Y arm commissioning
 * ~End of May: FPMI commissioning

==== Note ====
  * Commissioning meeting moves at 1PM from this week.

==== Night work ====
 * IOO: iMC alignment (Kokeyama, Guiguo, June-gyu)

==== Weekend ====
 *
 
==== Report of work ====
 * DC position IP of SR3 is still not good. It will be fixed this morning with IFO alignment.
 * OSEM of PRM are fine now. PR2 and SR2 will be tuned today.
 * PR3 was kicked again this morning -> alignment was fixed.

 * Yaw of BS should be offloaded this morning.

 

==== Work plan ====
 1. alignment -> done during morning meeting, BS offload.
 * OSEM for PR2.
 * OSEM for SR2.
 
 * No maintenance will be done due to above works, specially there is a possibility that exchanging PCs will disturb PRMs and SRMs.

 * Tonight MIF will try IFO alignment again for the final check. It hopefully will be done tonight, but laser hazard is assigned all the day tomorrow in the case.

 * IOO: iMC ASC work.
Line 59: Line 131:
==== Weekly meeting ==== <<Anchor(WeeklyMeetings)>>
=== Weekly meeting ===
Line 61: Line 134:
 * Location: Meeting room at Hokum , or educe, Polycom
||No.||Date||Agenda||Minute||Files||
|| || || || || ||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
 * Location: Meeting room at Hokubukaikan, or Zoom

||No.||Date||Agenda||Schedule||Minute||Files||
|| || || || || || ||
||66||2019/4/9||[[KAGRA/Commissioning/Weekly/20190409/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190409/Minute|Minute]]||||
||65-1||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/TypeA_Agenda|Integrated Type-A meeting]]|| || || ||
||65||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190402/Minute|Minute]]||||
||64||2019/3/26||[[KAGRA/Commissioning/Weekly/20190326/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190326/Minute|Minute]]||[[attachment:KAGRA/Commissioning/20190326_avoding_delay.pptx|file]]||
||63||2019/3/11||[[KAGRA/Commissioning/Weekly/20190311/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190311/Minute|Minute]]|| ||
||62||2019/3/5||[[KAGRA/Commissioning/Weekly/20190305/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190305/Minute|Minute]]|| ||
||61||2019/2/19||[[KAGRA/Commissioning/Weekly/20190219/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190219/Minute|Minute]]|| ||
||60||2019/2/5||[[KAGRA/Commissioning/Weekly/20190205/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190205/Minute|Minute]]|| ||
||59||2019/1/29||[[KAGRA/Commissioning/Weekly/20190129/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190129/Minute|Minute]]|| ||
||58||2019/1/22||[[KAGRA/Commissioning/Weekly/20190122/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190122/Minute|Minute]]|| ||
||57||2019/1/8||[[KAGRA/Commissioning/Weekly/20190108/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20190108/Minute|Minute]]|| ||
||56||2018/12/25||[[KAGRA/Commissioning/Weekly/20181225/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181225/Minute|Minute]]|| ||
||55||2018/12/17||[[KAGRA/Commissioning/Weekly/20181217/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181217/Minute|Minute]]|| ||
||54||2018/12/11||[[KAGRA/Commissioning/Weekly/20181211/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181211/Minute|Minute]]|| ||
||53||2018/12/4 ||[[KAGRA/Commissioning/Weekly/20181204/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181204/Minute|Minute]]|| ||
||52||2018/11/27||[[KAGRA/Commissioning/Weekly/20181127/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181127/Minute|Minute]]|| ||
||51||2018/11/20||[[KAGRA/Commissioning/Weekly/20181120/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181120/Minute|Minute]]|| ||
||50||2018/11/13||[[KAGRA/Commissioning/Weekly/20181113/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181113/Minute|Minute]]|| ||
||49||2018/11/6 ||[[KAGRA/Commissioning/Weekly/20181105/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181105/Minute|Minute]]|| ||
||48||2018/10/30||[[KAGRA/Commissioning/Weekly/20181030/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181030/Minute|Minute]]|| ||
||47||2018/10/23||[[KAGRA/Commissioning/Weekly/20181023/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181023/Minute|Minute]]|| ||
||46||2018/10/16||[[KAGRA/Commissioning/Weekly/20181016/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20181016/Minute|Minute]]|| ||
||45||2018/10/9 ||[[KAGRA/Commissioning/Weekly/20181009/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181009/Minute|Minute]]|| ||
||44||2018/10/2 ||[[KAGRA/Commissioning/Weekly/20181002/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20181002/Minute|Minute]]|| ||
||43||2018/9/18 ||[[KAGRA/Commissioning/Weekly/20180918/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180918/Minute|Minute]]|| ||
||42||2018/9/4 ||[[KAGRA/Commissioning/Weekly/20180904/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180904/Minute|Minute]]|| ||
||41||2018/8/28 ||[[KAGRA/Commissioning/Weekly/20180828/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180828/Minute|Minute]]|| ||
||40||2018/8/21 ||[[KAGRA/Commissioning/Weekly/20180821/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180821.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180821/Minute|Minute]]|| ||
||39||2018/8/7 ||[[KAGRA/Commissioning/Weekly/20180807/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180807.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180807/Minute|Minute]]|| ||
||38||2018/7/31 ||[[KAGRA/Commissioning/Weekly/201807031/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180731.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180731/Minute|Minute]]|| ||
||37||2018/7/24 ||[[KAGRA/Commissioning/Weekly/201807024/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180724.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180724/Minute|Minute]]|| ||
||36||2018/7/17 ||[[KAGRA/Commissioning/Weekly/201807017/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180717.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180717/Minute|Minute]]|| ||
||35||2018/7/3 ||[[KAGRA/Commissioning/Weekly/20180703/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180703.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180703/Minute|Minute]]|| ||
||34||2018/6/26 ||[[KAGRA/Commissioning/Weekly/20180626/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180626.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180626/Minute|Minute]]|| ||
||33||2018/6/19 ||[[KAGRA/Commissioning/Weekly/20180619/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180619.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180619/Minute|Minute]]|| ||
||32||2018/6/12 ||[[KAGRA/Commissioning/Weekly/20180612/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180612.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180612/Minute|Minute]]|| ||
||31||2018/6/5 ||[[KAGRA/Commissioning/Weekly/20180605/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180605.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180605/Minute|Minute]]|| ||
||30||2018/5/22 ||[[KAGRA/Commissioning/Weekly/20180522/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180522.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180522/Minute|Minute]]|| ||
||29||2018/5/8 ||[[KAGRA/Commissioning/Weekly/20180508/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180508.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180508/Minute|Minute]]|| ||
||28||2018/5/1 ||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| ||
||27||2018/4/17 ||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| ||
||26||2018/4/10 ||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| ||
||25||2018/4/3 ||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| ||
||24||2018/3/27 ||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| ||
||23||2018/3/20 ||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| ||
||22||2018/3/13 ||[[KAGRA/Commissioning/Weekly/20180313/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180313.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180313/Minute|Minute]]|| ||
||21||2018/3/6 ||[[KAGRA/Commissioning/Weekly/20180306/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180306.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180306/Minute|Minute]]|| ||
||20||2018/2/27 ||[[KAGRA/Commissioning/Weekly/20180227/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180227.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180227/Minute|Minute]]|| ||
||19||2018/2/20 ||[[KAGRA/Commissioning/Weekly/20180220/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180220.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180220/Minute|Minute]]|| ||
||18||2018/2/13 ||[[KAGRA/Commissioning/Weekly/20180213/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180213.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180213/Minute|Minute]]|| ||
||17||2018/2/6 ||[[KAGRA/Commissioning/Weekly/20180206/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180206.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180206/Minute|Minute]]|| ||
||16||2018/1/30 ||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| ||
||15||2018/1/23 ||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| ||
||14||2018/1/16 ||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| ||
||13||2018/1/9 ||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| ||
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
||10||2017/11/28||[[KAGRA/Commissioning/Weekly/20171128/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171128.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171121/Minute|Minute]]|| ||
||9||2017/11/14||[[KAGRA/Commissioning/Weekly/20171114/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171114.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171114/Minute|Minute]]|| ||
||8||2017/11/7||[[KAGRA/Commissioning/Weekly/20171107/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171107/Minute|Minute]]|| ||
||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]||
||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]||
||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]||
||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]||
||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]||
||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]|| ||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]||
||1||2017/9/19|| || || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]||
Line 72: Line 208:
 * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])
 * 2019/3/8: Scheduling for FPMI [[/Meetings/Others/20190308/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20190308|Minute]]
 * 2018/9/3: Extended chief meeting for Arm commissioning [[/Meetings/Others/20180903/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20180903/Agenda/memo|Minute]]
 * 2018/8/30: 3rd Meeting for pump down at ITMX ([[/Meetings/Others/20180830|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]])
 * 2018/8/23: 2nd Meeting for pump down at ITMX ([[/Meetings/Others/20180823|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]])
 * 2018/8/16: Meeting for pump down at ITMX ([[/Meetings/Others/20180816|Minute]], [[/Phase2/Task/CheckList/VacuumITMX|Check list]])
 * 2018/5/28: [[KAGRA/Commissioning/Meetings/Others/20180528/Phase1|Meeting for looking back to phase1 for future of KAGRA]] as an extended chief meeting.
 * 2018/4/11: Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * 2018/4/5: Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]])
 * 2018/3/14: Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]])
 * 2018/1/18: Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * 2018/1/17: Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * 2018/1/10: Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]])
 * 2017/12/13: Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])
 * 2017/11/27~12/1[[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]]
 * 2017/11/17: Meeting for closing ETY ([[/Meetings/Others/20171117|Minute]])
 * 2017/10/12: Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]])
Line 81: Line 233:
 * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
 * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)
   * [[KAGRA/Commissioning/ML|KAGRA commissioning Mailing List]]
   * wiki
    * Task list (Phase base, stage base)
    * Meetings ([[KAGRA/Commissioning#MorningMeetings|morning]], [[KAGRA/Commissioning#WeeklyMeetings|weekly]])
   * [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171106.xlsx|Scheduler]]
   * Task assignment list ([[https://docs.google.com/spreadsheets/d/1qipguowxaEbEEV9LYxvHR_aMBxn0Evsl5nZkP5Vhj_4/edit#gid=0|example]])
   * [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php|klog]]
   * Issue tracker: [[http://172.16.33.20/bugzilla/|Bugzilla]] (currently site internal only)

KAGRA Commissioning Wiki


Task list


Schedule


Working people assignment

Readiness for the X arm commissioning


Meetings

Daily Meetings (9AM, 1PM)

Zoom URL: https://zoom.us/j/7631499341

Weekly Meetings (Tuesday 11AM)

Zoom URL: https://zoom.us/j/6676627462


Daily meeting

  • Date and time: Every weekday, 9AM
  • First ~10min in the morning meeting, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2019/4/10(Wed.)

Schedule

  • Center
    • 3/25: Venting

    • 3/27-4/9: Fixing PR2
      • 4/4 -4/5: Gluing

      • 4/8: alignment check
      • 4/8-10: OSEM adjustment
    • 4/11-12: Closing
    • 4/12: Pump down
    • 4/15~: Leak check
  • ITMX:
    • 3/19: Cooling stop

    • 3/25: Venting start

    • 3/27: Opning chamber

    • 3/27~: Fixing thermal touch

    • 4/2~: closing chamber and start pumping down

    • 4/12: Cooling starts.
  • Xend
    • 3/25: closing and pump down

    • 4/8: Leak check

    • 4/9-10: venting
    • 4/11: Exchange a broken LED for Photo sensor
    • 4/12: closing chamber and start pumping down
    • 4/15: Leak check
    • 4/19(or 22): Cooling start
  • Yend
    • 3/26: Venting start

    • 3/28~: Fixing short inside chamber

    • 4/3: Fixing F0 actuator

    • 4/4~: closing chamber and start pumping down.

    • 4/12: Cooling starts.
  • 4/8: Daily meeting will be moved to 1PM
    • Summary of work will last for a while in the morning meeting.
  • April: Measurement of TF, payload diagonalization on ITMX
  • End of April~: DRMI commissioning
  • End of April~: Y arm commissioning
  • ~End of May: FPMI commissioning

Note

  • Commissioning meeting moves at 1PM from this week.

Night work

  • IOO: iMC alignment (Kokeyama, Guiguo, June-gyu)

Weekend

Report of work

  • DC position IP of SR3 is still not good. It will be fixed this morning with IFO alignment.
  • OSEM of PRM are fine now. PR2 and SR2 will be tuned today.
  • PR3 was kicked again this morning -> alignment was fixed.

  • Yaw of BS should be offloaded this morning.

Work plan

  1. alignment -> done during morning meeting, BS offload.

  2. OSEM for PR2.
  3. OSEM for SR2.
  4. No maintenance will be done due to above works, specially there is a possibility that exchanging PCs will disturb PRMs and SRMs.
  5. Tonight MIF will try IFO alignment again for the final check. It hopefully will be done tonight, but laser hazard is assigned all the day tomorrow in the case.
  6. IOO: iMC ASC work.

KAGRA/Commissioning/DailyWork
<< <  2024 / 7 >  >>
Mon Tue Wed Thu Fri Sat Sun
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31        


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or Zoom

No.

Date

Agenda

Schedule

Minute

Files

66

2019/4/9

Agenda

See agenda page

Minute

65-1

2019/4/2

Integrated Type-A meeting

65

2019/4/2

Agenda

See agenda page

Minute

64

2019/3/26

Agenda

See agenda page

Minute

file

63

2019/3/11

Agenda

See agenda page

Minute

62

2019/3/5

Agenda

See agenda page

Minute

61

2019/2/19

Agenda

See agenda page

Minute

60

2019/2/5

Agenda

See agenda page

Minute

59

2019/1/29

Agenda

Minute

58

2019/1/22

Agenda

Minute

57

2019/1/8

Agenda

Minute

56

2018/12/25

Agenda

Minute

55

2018/12/17

Agenda

Minute

54

2018/12/11

Agenda

Minute

53

2018/12/4

Agenda

Minute

52

2018/11/27

Agenda

Minute

51

2018/11/20

Agenda

Minute

50

2018/11/13

Agenda

Minute

49

2018/11/6

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents