18074
Comment:
|
19685
|
Deletions are marked like this. | Additions are marked like this. |
Line 37: | Line 37: |
==== Daily Meetings (9AM) ==== | ==== Daily Meetings (9AM, 1PM) ==== |
Line 45: | Line 45: |
=== Daily meeting === | == Daily meeting == |
Line 52: | Line 52: |
=== 2019/3/1(Fri.) === === Schedule === |
=== 2019/5/7(Tue.) === ==== Schedule ==== |
Line 56: | Line 56: |
* --(2/26-27: Venting)-- * 2/28: Fixing --(PR2, PR3)-- * 3/1: Fixing PRM, and SRM * 3/2-5: Re-alignment * 3/5-6: Closing |
* --(4/12: Pump down)-- * --(4/29,30: Leak check)-- * 5/2: Vent and pumpdown * 5/9: leak check * ITMX: * --(4/2~: closing chamber and start pumping down.)-- * --(4/10: Cooling starts.)-- * 5/8: Cooling done * Xend * --(4/25: Pumpdown)-- * --(5/2: leak check)-- * --(5/2: Cooling start)-- |
Line 63: | Line 72: |
* --(1/25-2/20: Yend Pcal finalization)-- * 2/25-3/4: Yend WAB finalization * 3/5-6: Closing * 3/6~ : Yend pumpdown 3/6~ * 3/7,8: leak test * Xend * --(2/11-2/14: Xend NAB installation)-- * --(2/21: Removing FC, Payload release)-- * 2/23-3/10: Xend Pcal finalization 1 * Periscope installation * Beam position by IR and Green * 2/27: ETMX release * 3/5: ETMX aligned * 3/5-3/10: Xend Pcal finalization 2 * 3/11,12 Xend WAB finalization * 3/19,20, Heatlink etc. * 3/22 Pumping down * Leak test * 3/11~ : Night work starts * 2/18-3/22 DRMI commissioning * 3/11-4/5 Y arm commissioning * 3/25-4/5 FPMI commissioning |
* --(4/4~: closing chamber and start pumping down.)-- * --(4/10: Cooling starts.)-- * 5/8: Cooling done * April: Measurement of TF, payload diagonalization on ITMX * End of April~: DRMI commissioning * End of April~: Y arm commissioning * ~End of May: FPMI commissioning |
Line 90: | Line 82: |
* Takoyaki party at 6pm. === Weekend === |
* ==== Night work ==== * Y arm commissioning, from the control room. ==== Weekend ==== |
Line 96: | Line 90: |
* PRM: Vibration measurement of cooler. * DGS: replaced RTPC of BS to V4 and PRM to V3. |
* IR laser frequency was too noisy for mass feedback lock. * Frequency is stabilized by X arm cavity, and Y arm will be locked to stabilized laser. * Beam spot on ITMY was too high. * Needs BS camera. * VAC: In the central area, leaks were found and it was fixed. Pumping down started again. |
Line 101: | Line 99: |
* VIS: Fixing PRM, PR3 and SRM * COM: Alignment of central area after tomorrow. |
|
Line 113: | Line 108: |
* Location: Meeting room at Hokubukaikan, or eZuce, Polycom | * Location: Meeting room at Hokubukaikan, or Zoom |
Line 117: | Line 112: |
---- /!\ '''Edit conflict - other version:''' ---- ---- /!\ '''Edit conflict - your version:''' ---- ||69||2019/5/7||[[KAGRA/Commissioning/Weekly/20190507/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190507/Minute|Minute]]|||| ---- /!\ '''End of edit conflict''' ---- ||68||2019/4/23||[[KAGRA/Commissioning/Weekly/20190423/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190423/Minute|Minute]]|||| ||67||2019/4/16||[[KAGRA/Commissioning/Weekly/20190416/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190416/Minute|Minute]]|||| ||66||2019/4/9||[[KAGRA/Commissioning/Weekly/20190409/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190409/Minute|Minute]]|||| ||65-1||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/TypeA_Agenda|Integrated Type-A meeting]]|| || || || ||65||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190402/Minute|Minute]]|||| ||64||2019/3/26||[[KAGRA/Commissioning/Weekly/20190326/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190326/Minute|Minute]]||[[attachment:KAGRA/Commissioning/20190326_avoding_delay.pptx|file]]|| ||63||2019/3/11||[[KAGRA/Commissioning/Weekly/20190311/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190311/Minute|Minute]]|| || ||62||2019/3/5||[[KAGRA/Commissioning/Weekly/20190305/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190305/Minute|Minute]]|| || |
|
Line 182: | Line 192: |
* 2019/3/8: Scheduling for FPMI [[/Meetings/Others/20190308/Agenda|Agenda]], [[KAGRA/Commissioning/Meetings/Others/20190308|Minute]] |
KAGRA Commissioning Wiki
Task list
Schedule
Working people assignment
Readiness for the X arm commissioning
https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing
Meetings
Daily Meetings (9AM, 1PM)
Zoom URL: https://zoom.us/j/7631499341
Weekly Meetings (Tuesday 11AM)
Zoom URL: https://zoom.us/j/6676627462
Daily meeting
- Date and time: Every weekday, 9AM
- First ~10min in the morning meeting, as short as possible
- Location: Control room and Fan hut connected by eZuce
2019/5/7(Tue.)
Schedule
- Center
4/12: Pump down
4/29,30: Leak check
- 5/2: Vent and pumpdown
- 5/9: leak check
- ITMX:
4/2~: closing chamber and start pumping down.
4/10: Cooling starts.
- 5/8: Cooling done
- Xend
4/25: Pumpdown
5/2: leak check
5/2: Cooling start
- Yend
4/4~: closing chamber and start pumping down.
4/10: Cooling starts.
- 5/8: Cooling done
- April: Measurement of TF, payload diagonalization on ITMX
- End of April~: DRMI commissioning
- End of April~: Y arm commissioning
- ~End of May: FPMI commissioning
Note
Night work
- Y arm commissioning, from the control room.
Weekend
Report of work
- IR laser frequency was too noisy for mass feedback lock.
- Frequency is stabilized by X arm cavity, and Y arm will be locked to stabilized laser.
- Beam spot on ITMY was too high.
- Needs BS camera.
- VAC: In the central area, leaks were found and it was fixed. Pumping down started again.
Work plan
KAGRA/Commissioning/DailyWork << < 2024 / 11 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | ||||
4 | 5 | 6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 | 16 | 17 |
18 | 19 | 20 | 21 | 22 | 23 | 24 |
25 | 26 | 27 | 28 | 29 | 30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or Zoom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
Edit conflict - other version:
Edit conflict - your version:
End of edit conflict
68 |
2019/4/23 |
See agenda page |
|||
67 |
2019/4/16 |
See agenda page |
|||
66 |
2019/4/9 |
See agenda page |
|||
65-1 |
2019/4/2 |
|
|
|
|
65 |
2019/4/2 |
See agenda page |
|||
64 |
2019/3/26 |
See agenda page |
|||
63 |
2019/3/11 |
See agenda page |
|
||
62 |
2019/3/5 |
See agenda page |
|
||
61 |
2019/2/19 |
See agenda page |
|
||
60 |
2019/2/5 |
See agenda page |
|
||
59 |
2019/1/29 |
|
|
||
58 |
2019/1/22 |
|
|
||
57 |
2019/1/8 |
|
|
||
56 |
2018/12/25 |
|
|
||
55 |
2018/12/17 |
|
|
||
54 |
2018/12/11 |
|
|
||
53 |
2018/12/4 |
|
|
||
52 |
2018/11/27 |
|
|
||
51 |
2018/11/20 |
|
|
||
50 |
2018/11/13 |
|
|
||
49 |
2018/11/6 |
|
|
||
48 |
2018/10/30 |
|
|
||
47 |
2018/10/23 |
|
|
||
46 |
2018/10/16 |
|
|
||
45 |
2018/10/9 |
|
|||
44 |
2018/10/2 |
|
|||
43 |
2018/9/18 |
|
|||
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
|||
35 |
2018/7/3 |
|
|||
34 |
2018/6/26 |
|
|||
33 |
2018/6/19 |
|
|||
32 |
2018/6/12 |
|
|||
31 |
2018/6/5 |
|
|||
30 |
2018/5/22 |
|
|||
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
2018/9/3: Extended chief meeting for Arm commissioning Agenda, Minute
2018/8/30: 3rd Meeting for pump down at ITMX (Minute, Check list)
2018/8/23: 2nd Meeting for pump down at ITMX (Minute, Check list)
2018/8/16: Meeting for pump down at ITMX (Minute, Check list)
2018/5/28: Meeting for looking back to phase1 for future of KAGRA as an extended chief meeting.
2018/4/11: Meeting for pump down test at ETMX 2 (Minute, Check list)
2018/4/5: Meeting for pump down test at ETMX 1 (Minute, Check list)
2018/3/14: Meeting for pump down test at Center are (Minute, Check list)
2018/1/18: Meeting for pump down and cooling at ETMY3 (Minute, Check list)
2018/1/17: Meeting for pump down and cooling at ETMY2 (Minute, Check list)
2018/1/10: Meeting for pump down and cooling at ETMY1 (Minute, Check list)
2017/12/13: Meeting for pump down at ETMY (Minute, schedule)
2017/11/27~12/1Commissioning Workshop 2017
2017/11/17: Meeting for closing ETY (Minute)
2017/10/12: Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools