Line 37: Line 37:
==== Daily Meetings (9AM) ==== ==== Daily Meetings (9AM, 1PM) ====
Line 45: Line 45:
=== Daily meeting === == Daily meeting ==
Line 52: Line 52:
=== 2019/3/12(Tue.) ===

=== Schedule ===
 * Center
  * --(2/26-27: Venting)--
  * 2/28-3/15: Health check and maintenance for VIS
   * --(PRM: One flag was dropped. -> leave it)--
   * --(3/6 PR3: range -> incline by 20-30mrad at mirror because of bistable.)--
   * 3/4-8 PRM: Misalignment does not reach where beam hits damper.
   * ~3/15 BS: Yaw offset adjustment by hand. -> 3/5-6

  * --(3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.)--
  * 3/18-19: Re-alignment
  * 3/19: Closing
  * 3/20: pump down

 * Yend
  * --(1/25-2/20: Yend Pcal finalization)--
  * --(3/5: EYA remaining works by Enomoto, Inoue.)--
  * --(2/25-3/5: Yend WAB finalization)--
  * --(3/6: Y end closing (no laser hazard at least in the morning))--
  * --(3/7: Y end pump down)--
   * --(3/7,8: leak test)--

 * Xend
  * --(2/11-2/14: Xend NAB installation)--
  * --(2/21: Removing FC, Payload release)--
   * --(2/27: ETMX release)--
  * --(2/23-3/6: Xend Pcal finalization 1)--
   * --(Periscope installation)--
   * --(3/6: Beam position by IR and Green)--
  * --(3/5 AOS: EY and EX(if they have time) work.)--
  * --(3/6: Green X alignment (no IR), and no hazard at Y end.)--
  * 3/11, 18,19: Xend WAB finalization.
  * 3/11~3/15: ETMX tuning.
  * 3/19: Heatlink etc.
  * 3/19: ETMX finalization by Takahashi
  * 3/18,19: ETMX alignement
  * 3/21 closing
  * 3/22 Pumping down
   * Leak test
=== 2019/5/31(Fri.) ===

==== Schedule ====
 * --(5/22-23: MZ release from PSL)--
 * --(5/20-24: Exchanging cryo valves.)--
 * 5/27-6/2: Y arm mass lock.
 * 5/29: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (specially BS)
 * 6/3-6/14: Installation of TMS for ETMY
 * 6/8: Engineering run

 * ITMX
  * --(5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm)--
  * --(5/22AM~: tuned off shield cooler, finesse measurement for Xarm)--

 * ETMX
  * --(5/2: Cooling start)--

 * ITMY
  * --(5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm)--

 * ETMY
  * --(5/17~: tuned off ETMY cryostat cooler)--

 * Long term:
  * 4/22-5/31: Yarm commissioning
  * 5/27-6/30: DRMI commissioning
  * 7/1-8/9: DRFPMI commissioning
  * 8/12-10/4: DRFPMI ASC
  * 10/7-11/15: Post Commissioning
  * 11/18-12/13: Noise hunting


==== Note ====

==== Night work ====

==== Weekend ====

==== Report of work ====
 * Type A: VIS team is changing all the TYPE A models for damping schemes.
 * Type A, CRY, COM: ITMX is fluctuating a lot.
 * COM: Yarm finesse was 1290, a bit lower than before. It might be contamination.
Line 94: Line 96:
 * 3/18~ : Night work starts, daily meeting will be moved to 1PM
  * Summary of work will last for a while in the morning meeting.

 * 2/18-2/22: PRMI commissioning
 * 3/25~?: DRMI commissioning
 * 3/25-4/19: Y arm commissioning
 * 3/25-4/19: FPMI commissioning

==== Note ====
 * Night work does not start from 3/11 due to the 2weeks delay by VIS troubles.
  * It does not mean that night work is prohibited but it means that officially night shift responsible person won't be assigned and we have no daily meeting at 1pm.
  * Official night work starts 3/18 or 3/25, but not determined yet.

=== Weekend ===

==== Report of work ====
 * Type A: ETMX was touching at top. Filter chain was fixed and it became free for swing, needs health check today.
  * ITMX and ITMY TF are close to edge of range. They will be checked today.
  *ETMY F3 is still something wrong. To be discussed.
 * Type B: Recoil of BS was touching and it was fixed. It became free for swing, needs health check today.
 * Type Bp: PRM seems to be touching, needs to be fixed today.
 * AOS: Finalization of WAB for ETMX is going on. Needs to move traverser of FR today. Needs scheduling with Type A work.

Line 119: Line 97:
 * AOS: Finalization of WAB at ETMX will start today. It lasts this week.  * DGS: Maintenance for replacing k1lsc0.
 * COM: Finesse measurement for y arm with low temperature. Contamination can happen with low temperature.
 * Type B: Smooth watch dog will be implemented into some Type Bs in the maintenance time.
Line 129: Line 109:
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom  * Location: Meeting room at Hokubukaikan, or Zoom
Line 133: Line 113:
||72||2019/5/28||[[KAGRA/Commissioning/Weekly/20190528/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190528/Minute|Minute]]||||
||71||2019/5/21||[[KAGRA/Commissioning/Weekly/20190521/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190521/Minute|Minute]]||||
||70||2019/5/14||[[KAGRA/Commissioning/Weekly/20190514/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190514/Minute|Minute]]||||
||69||2019/5/7||[[KAGRA/Commissioning/Weekly/20190507/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190507/Minute|Minute]]||||
||68||2019/4/23||[[KAGRA/Commissioning/Weekly/20190423/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190423/Minute|Minute]]||||
||67||2019/4/16||[[KAGRA/Commissioning/Weekly/20190416/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190416/Minute|Minute]]||||
||66||2019/4/9||[[KAGRA/Commissioning/Weekly/20190409/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190409/Minute|Minute]]||||
||65-1||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/TypeA_Agenda|Integrated Type-A meeting]]|| || || ||
||65||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190402/Minute|Minute]]||||
||64||2019/3/26||[[KAGRA/Commissioning/Weekly/20190326/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190326/Minute|Minute]]||[[attachment:KAGRA/Commissioning/20190326_avoding_delay.pptx|file]]||

KAGRA Commissioning Wiki


Task list


Schedule


Working people assignment

Readiness for the X arm commissioning


Meetings

Daily Meetings (9AM, 1PM)

Zoom URL: https://zoom.us/j/7631499341

Weekly Meetings (Tuesday 11AM)

Zoom URL: https://zoom.us/j/6676627462


Daily meeting

  • Date and time: Every weekday, 9AM
  • First ~10min in the morning meeting, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2019/5/31(Fri.)

Schedule

  • 5/22-23: MZ release from PSL

  • 5/20-24: Exchanging cryo valves.

  • 5/27-6/2: Y arm mass lock.
  • 5/29: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (specially BS)

  • 6/3-6/14: Installation of TMS for ETMY
  • 6/8: Engineering run
  • ITMX
    • 5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm

    • 5/22AM~: tuned off shield cooler, finesse measurement for Xarm

  • ETMX
    • 5/2: Cooling start

  • ITMY
    • 5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm

  • ETMY
    • 5/17~: tuned off ETMY cryostat cooler

  • Long term:
    • 4/22-5/31: Yarm commissioning
    • 5/27-6/30: DRMI commissioning
    • 7/1-8/9: DRFPMI commissioning
    • 8/12-10/4: DRFPMI ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting

Note

Night work

Weekend

Report of work

  • Type A: VIS team is changing all the TYPE A models for damping schemes.
  • Type A, CRY, COM: ITMX is fluctuating a lot.
  • COM: Yarm finesse was 1290, a bit lower than before. It might be contamination.

Work plan

  • DGS: Maintenance for replacing k1lsc0.
  • COM: Finesse measurement for y arm with low temperature. Contamination can happen with low temperature.
  • Type B: Smooth watch dog will be implemented into some Type Bs in the maintenance time.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or Zoom

No.

Date

Agenda

Schedule

Minute

Files

72

2019/5/28

Agenda

See agenda page

Minute

71

2019/5/21

Agenda

See agenda page

Minute

70

2019/5/14

Agenda

See agenda page

Minute

69

2019/5/7

Agenda

See agenda page

Minute

68

2019/4/23

Agenda

See agenda page

Minute

67

2019/4/16

Agenda

See agenda page

Minute

66

2019/4/9

Agenda

See agenda page

Minute

65-1

2019/4/2

Integrated Type-A meeting

65

2019/4/2

Agenda

See agenda page

Minute

64

2019/3/26

Agenda

See agenda page

Minute

file

63

2019/3/11

Agenda

See agenda page

Minute

62

2019/3/5

Agenda

See agenda page

Minute

61

2019/2/19

Agenda

See agenda page

Minute

60

2019/2/5

Agenda

See agenda page

Minute

59

2019/1/29

Agenda

Minute

58

2019/1/22

Agenda

Minute

57

2019/1/8

Agenda

Minute

56

2018/12/25

Agenda

Minute

55

2018/12/17

Agenda

Minute

54

2018/12/11

Agenda

Minute

53

2018/12/4

Agenda

Minute

52

2018/11/27

Agenda

Minute

51

2018/11/20

Agenda

Minute

50

2018/11/13

Agenda

Minute

49

2018/11/6

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)