Differences between revisions 666 and 740 (spanning 74 versions)
Revision 666 as of 2019-03-25 16:36:23
Size: 20016
Comment:
Revision 740 as of 2019-05-24 09:58:33
Size: 20384
Comment:
Deletions are marked like this. Additions are marked like this.
Line 37: Line 37:
==== Daily Meetings (9AM) ==== ==== Daily Meetings (9AM, 1PM) ====
Line 45: Line 45:
=== Daily meeting === == Daily meeting ==
Line 52: Line 52:
=== 2019/3/25(Mon.) ===

=== Schedule ===
 * Center
  * --(2/26-27: Venting)--
  * 2/28-3/15: Health check and maintenance for VIS
   * --(PRM: One flag was dropped. -> leave it)--
   * --(3/4-14 PRM: Misalignment does not reach where beam hits damper.)--
   * --(3/6 PR3: range -> incline by 20-30mrad at mirror because of bistable.)--
   * --(3/15: BS: Yaw offset adjustment by hand. -> 3/5-6)--
    * --(3/12: BS ok)--
   * --(3/15: some SRs work)--

  * --(3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.)--
  * --(3/18: Re-alignment)--
  * --(3/19-21: Closing)--
  * --(3/22: Pump down)--
  * --(3/25: Venting)--
  * 3/26: Leak test

 * ITMX:
  * --(3/19: Cooling stop)--
  * 3/28: Opning chamber
  * 3/28: Fixing thermal touch
  * 3/29: closing chamber and start pumping down.
  * 4/1: Start cooling.

 * Yend
  * --(1/25-2/20: Yend Pcal finalization)--
  * --(3/5: EYA remaining works by Enomoto, Inoue.)--
  * --(2/25-3/5: Yend WAB finalization)--
  * --(3/6: Y end closing (no laser hazard at least in the morning))--
  * --(3/7: Y end pump down)--
  * --(3/22-23: leak test)--
  * 3/27: cooling start

 * Xend
  * --(2/11-2/14: Xend NAB installation)--
  * --(2/21: Removing FC, Payload release)--
   * --(2/27: ETMX release)--
  * --(2/23-3/6: Xend Pcal finalization 1)--
   * --(Periscope installation)--
   * --(3/6: Beam position by IR and Green)--
  * --(3/5 AOS: EY and EX(if they have time) work.)--
  * --(3/6: Green X alignment (no IR), and no hazard at Y end.)--
  * --(3/11, ~20: Xend WAB finalization.)--
  * --(3/11~3/15: ETMX tuning.)--
  * --(3/19: ETMX finalization by Takahashi)--
  * --(3/18,19: ETMX alignement)--
  * --(3/23-24: Pcal alignment)--
  * --(3/24: Removing PD)--
  * 3/25: closing and pump down
  * 4/2-4: Leak test
  * 3/27: Cooling start
 
 * 3/25~ : Night work officially starts, daily meeting will be moved to 1PM
  * Summary of work will last for a while in the morning meeting.

 * 2/18-2/22: PRMI commissioning
 * 3/25~?: DRMI commissioning
 * 3/25-4/19: Y arm commissioning
 * 3/25-4/19: FPMI commissioning
=== 2019/5/24(Fri.) ===

==== Schedule ====
 * --(5/22: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (BS) )--
 * --(5/22-23: MZ release from PSL)--
 * --(5/20-24: Exchanging cryo valves.)--
 * 5/27-6/2: Y arm mass lock.
 * 6/3-6/14: Installation of TMS for ETMY
 * 6/8: Engineering run

 * ITMX
  * --(5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm)--
  * --(5/22AM~: tuned off shield cooler, finesse measurement for Xarm)--

 * ETMX
  * --(5/2: Cooling start)--
  * 5/29: Cooling done

 * ITMY
  * --(5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm)--

 * ETMY
  * --(5/17~: tuned off ETMY cryostat cooler)--
  * 5/24PM~ inject 100Pa Nitrogen. -> postponed after 6/3?
  * 5/27 evacuation of Nitrogen. -> postponed after 6/3?

 * Long term:
  * 4/22-5/31: Yarm commissioning
  * 5/27-6/30: DRMI commissioning
  * 7/1-8/9: DRFPMI commissioning
  * 8/12-10/4: DRFPMI ASC
  * 10/7-11/15: Post Commissioning
  * 11/18-12/13: Noise hunting
Line 116: Line 87:
  * Official night work starts 4/1.

=== Weekend ===

 

====
Night work ====

==== Weekend ====
 * IOO maybe
Line 122: Line 94:

 * Type Bp: It was fount that there was a big bump at PR2 last week, and Vertical of Oplev was out of range.
  * It was decided to vent again. Venting starts 11am today.

 * CAL: Beam position of Pcal was fixed at ETMX.
 * COM: Finesse measurement did not succeed by some troubles.
  * T cam fo X arm had trouble. It was fixed this morning by restarting Team.
  * SR3 drift caused by VIS work in the mid night. Working time should be coordinated.
 * Type A: After stopping cryo cooler of ITMY stopped and temperature went up, ITMY surface looks better by T cam image with green light. Spots by dust? seems to be gone and the surface looks more clean.
 * IOO: Alignment of PSL is back after MZ was removed day before yesterday.
Line 130: Line 101:
 * Vent at center area.  * DGS: Maintenance work afternoon for k1asc0.
Line 139: Line 111:
 * Location: Meeting room at Hokubukaikan, or eZuce, Polycom  * Location: Meeting room at Hokubukaikan, or Zoom
Line 143: Line 115:
||64||2019/3/26||[[KAGRA/Commissioning/Weekly/20190326/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190326/Minute|Minute]]|| || ||71||2019/5/21||[[KAGRA/Commissioning/Weekly/20190521/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190521/Minute|Minute]]||||
||70||2019/5/14||[[KAGRA/Commissioning/Weekly/20190514/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190514/Minute|Minute]]||||
||69||2019/5/7||[[KAGRA/Commissioning/Weekly/20190507/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190507/Minute|Minute]]||||
||68||2019/4/23||[[KAGRA/Commissioning/Weekly/20190423/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190423/Minute|Minute]]||||
||67||2019/4/16||[[KAGRA/Commissioning/Weekly/20190416/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190416/Minute|Minute]]||||
||66||2019/4/9||[[KAGRA/Commissioning/Weekly/20190409/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190409/Minute|Minute]]||||
||65-1||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/TypeA_Agenda|Integrated Type-A meeting]]|| || || ||
||65||2019/4/2||[[KAGRA/Commissioning/Weekly/20190402/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190402/Minute|Minute]]||||
||64||2019/3/26||[[KAGRA/Commissioning/Weekly/20190326/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190326/Minute|Minute]]||[[attachment:KAGRA/Commissioning/20190326_avoding_delay.pptx|file]]||

KAGRA Commissioning Wiki


Task list


Schedule


Working people assignment

Readiness for the X arm commissioning


Meetings

Daily Meetings (9AM, 1PM)

Zoom URL: https://zoom.us/j/7631499341

Weekly Meetings (Tuesday 11AM)

Zoom URL: https://zoom.us/j/6676627462


Daily meeting

  • Date and time: Every weekday, 9AM
  • First ~10min in the morning meeting, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2019/5/24(Fri.)

Schedule

  • 5/22: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (BS)

  • 5/22-23: MZ release from PSL

  • 5/20-24: Exchanging cryo valves.

  • 5/27-6/2: Y arm mass lock.
  • 6/3-6/14: Installation of TMS for ETMY
  • 6/8: Engineering run
  • ITMX
    • 5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm

    • 5/22AM~: tuned off shield cooler, finesse measurement for Xarm

  • ETMX
    • 5/2: Cooling start

    • 5/29: Cooling done
  • ITMY
    • 5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm

  • ETMY
    • 5/17~: tuned off ETMY cryostat cooler

    • 5/24PM~ inject 100Pa Nitrogen. -> postponed after 6/3?

    • 5/27 evacuation of Nitrogen. -> postponed after 6/3?

  • Long term:
    • 4/22-5/31: Yarm commissioning
    • 5/27-6/30: DRMI commissioning
    • 7/1-8/9: DRFPMI commissioning
    • 8/12-10/4: DRFPMI ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting

Note

Night work

Weekend

  • IOO maybe

Report of work

  • COM: Finesse measurement did not succeed by some troubles.
    • T cam fo X arm had trouble. It was fixed this morning by restarting Team.
    • SR3 drift caused by VIS work in the mid night. Working time should be coordinated.
  • Type A: After stopping cryo cooler of ITMY stopped and temperature went up, ITMY surface looks better by T cam image with green light. Spots by dust? seems to be gone and the surface looks more clean.
  • IOO: Alignment of PSL is back after MZ was removed day before yesterday.

Work plan

  • DGS: Maintenance work afternoon for k1asc0.

KAGRA/Commissioning/DailyWork
<< <  2024 / 11 >  >>
Mon Tue Wed Thu Fri Sat Sun
        1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30  


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or Zoom

No.

Date

Agenda

Schedule

Minute

Files

71

2019/5/21

Agenda

See agenda page

Minute

70

2019/5/14

Agenda

See agenda page

Minute

69

2019/5/7

Agenda

See agenda page

Minute

68

2019/4/23

Agenda

See agenda page

Minute

67

2019/4/16

Agenda

See agenda page

Minute

66

2019/4/9

Agenda

See agenda page

Minute

65-1

2019/4/2

Integrated Type-A meeting

65

2019/4/2

Agenda

See agenda page

Minute

64

2019/3/26

Agenda

See agenda page

Minute

file

63

2019/3/11

Agenda

See agenda page

Minute

62

2019/3/5

Agenda

See agenda page

Minute

61

2019/2/19

Agenda

See agenda page

Minute

60

2019/2/5

Agenda

See agenda page

Minute

59

2019/1/29

Agenda

Minute

58

2019/1/22

Agenda

Minute

57

2019/1/8

Agenda

Minute

56

2018/12/25

Agenda

Minute

55

2018/12/17

Agenda

Minute

54

2018/12/11

Agenda

Minute

53

2018/12/4

Agenda

Minute

52

2018/11/27

Agenda

Minute

51

2018/11/20

Agenda

Minute

50

2018/11/13

Agenda

Minute

49

2018/11/6

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)