Line 52: Line 52:
=== 2019/4/22(Mon.) === === 2019/5/23(Thur.) ===
Line 55: Line 55:
 * Center
  * --(3/25: Venting)--
  * --(3/27-4/9: Fixing PR2 or others)--
   * --(4/4 -4/5: Gluing)--
   * --(4/8: alignment check)--
   * --(4/8-10: OSEM adjustment)--
  * --(4/10: alignment check)--
  * --(4/11: VIS final health check)--
  * --(4/11-12: Closing)--
  * --(4/12: Pump down)--
  * 4/29,30: Leak check

 * ITMX:
  * --(3/19: Cooling stop)--
  * --(3/25: Venting start)--
  * --(3/27: Opning chamber)--
  * --(3/27~: Fixing thermal touch)--
  * --(4/2~: closing chamber and start pumping down)--
  * --(4/10: Cooling starts.)--

 * Xend
  * --(3/25: closing and pump down)--
  * --(4/8: Leak check)--
  * --(4/9-10: venting)--
  * --(4/11: Exchange a broken LED for Photo sensor)--
  * --(4/12: closing chamber and start pumping down)--
  * 4/22: Leak check
  * 4/22: vent
  * 4/24: fix oplev mirror
  * 4/25: Pumpdown
  * 5/2: leak check
  * 5/2: Cooling start

 * Yend
  * --(3/26: Venting start)--
  * --(3/28~: Fixing short inside chamber)--
  * --(4/3: Fixing F0 actuator)--
  * --(4/4~: closing chamber and start pumping down.)--
  * --(4/10: Cooling starts.)--

 * April: Measurement of TF, payload diagonalization on ITMX
 * End of April~: DRMI commissioning
 * End of April~: Y arm commissioning
 * ~End of May: FPMI commissioning
 * --(5/22: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (BS) )--
 * --(5/22-23: MZ release from PSL)--
 * --(5/20-24: Exchanging cryo valves.)--
 * 5/27-6/2: Y arm mass lock.
 * 6/3-6/14: Installation of TMS for ETMY
 * 6/8: Engineering run

 * ITMX
  * --(5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm)--
  * --(5/22AM~: tuned off shield cooler, finesse measurement for Xarm)--

 * ETMX
  * --(5/2: Cooling start)--
  * 5/29: Cooling done

 * ITMY
  * --(5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm)--

 * ETMY
  * --(5/17~: tuned off ETMY cryostat cooler)--
  * 5/24PM~ inject 100Pa Nitrogen. -> postponed after 6/3?
  * 5/27 evacuation of Nitrogen. -> postponed after 6/3?

 * Long term:
  * 4/22-5/31: Yarm commissioning
  * 5/27-6/30: DRMI commissioning
  * 7/1-8/9: DRFPMI commissioning
  * 8/12-10/4: DRFPMI ASC
  * 10/7-11/15: Post Commissioning
  * 11/18-12/13: Noise hunting
Line 101: Line 87:
 *
Line 104: Line 89:
 *
Line 107: Line 91:
 *  * IOO maybe
Line 110: Line 94:
 * COM: All mirrors except for ETMX have been aligned.
 * AOS: Laser source for oplev for PR3 seems to be dead. It will be replaced.
 * COM: Finesse measurement did not succeed by some troubles.
  * T cam fo X arm had trouble. It was fixed this morning by restarting Team.
  * SR3 drift caused by VIS work in the mid night. Working time should be coordinated.
 * Type A: After stopping cryo cooler of ITMY stopped and temperature went up, ITMY surface looks better by T cam image with green light. Spots by dust? seems to be gone and the surface looks more clean.
 * IOO: Alignment of PSL is back after MZ was removed day before yesterday.
Line 115: Line 101:
 * VAC: We have venting for ETMX to fix Oplev.  * DGS: Maintenance work afternoon for k1asc0.
Line 129: Line 115:
||71||2019/5/21||[[KAGRA/Commissioning/Weekly/20190521/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190521/Minute|Minute]]||||
||70||2019/5/14||[[KAGRA/Commissioning/Weekly/20190514/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190514/Minute|Minute]]||||
||69||2019/5/7||[[KAGRA/Commissioning/Weekly/20190507/Agenda|Agenda]]||See agenda page||[[KAGRA/Commissioning/Weekly/20190507/Minute|Minute]]||||

KAGRA Commissioning Wiki


Task list


Schedule


Working people assignment

Readiness for the X arm commissioning


Meetings

Daily Meetings (9AM, 1PM)

Zoom URL: https://zoom.us/j/7631499341

Weekly Meetings (Tuesday 11AM)

Zoom URL: https://zoom.us/j/6676627462


Daily meeting

  • Date and time: Every weekday, 9AM
  • First ~10min in the morning meeting, as short as possible
  • Location: Control room and Fan hut connected by eZuce

2019/5/23(Thur.)

Schedule

  • 5/22: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (BS)

  • 5/22-23: MZ release from PSL

  • 5/20-24: Exchanging cryo valves.

  • 5/27-6/2: Y arm mass lock.
  • 6/3-6/14: Installation of TMS for ETMY
  • 6/8: Engineering run
  • ITMX
    • 5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm

    • 5/22AM~: tuned off shield cooler, finesse measurement for Xarm

  • ETMX
    • 5/2: Cooling start

    • 5/29: Cooling done
  • ITMY
    • 5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm

  • ETMY
    • 5/17~: tuned off ETMY cryostat cooler

    • 5/24PM~ inject 100Pa Nitrogen. -> postponed after 6/3?

    • 5/27 evacuation of Nitrogen. -> postponed after 6/3?

  • Long term:
    • 4/22-5/31: Yarm commissioning
    • 5/27-6/30: DRMI commissioning
    • 7/1-8/9: DRFPMI commissioning
    • 8/12-10/4: DRFPMI ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting

Note

Night work

Weekend

  • IOO maybe

Report of work

  • COM: Finesse measurement did not succeed by some troubles.
    • T cam fo X arm had trouble. It was fixed this morning by restarting Team.
    • SR3 drift caused by VIS work in the mid night. Working time should be coordinated.
  • Type A: After stopping cryo cooler of ITMY stopped and temperature went up, ITMY surface looks better by T cam image with green light. Spots by dust? seems to be gone and the surface looks more clean.
  • IOO: Alignment of PSL is back after MZ was removed day before yesterday.

Work plan

  • DGS: Maintenance work afternoon for k1asc0.

KAGRA/Commissioning/DailyWork
<< <  2024 / 10 >  >>
Mon Tue Wed Thu Fri Sat Sun
  1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31      


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or Zoom

No.

Date

Agenda

Schedule

Minute

Files

71

2019/5/21

Agenda

See agenda page

Minute

70

2019/5/14

Agenda

See agenda page

Minute

69

2019/5/7

Agenda

See agenda page

Minute

68

2019/4/23

Agenda

See agenda page

Minute

67

2019/4/16

Agenda

See agenda page

Minute

66

2019/4/9

Agenda

See agenda page

Minute

65-1

2019/4/2

Integrated Type-A meeting

65

2019/4/2

Agenda

See agenda page

Minute

64

2019/3/26

Agenda

See agenda page

Minute

file

63

2019/3/11

Agenda

See agenda page

Minute

62

2019/3/5

Agenda

See agenda page

Minute

61

2019/2/19

Agenda

See agenda page

Minute

60

2019/2/5

Agenda

See agenda page

Minute

59

2019/1/29

Agenda

Minute

58

2019/1/22

Agenda

Minute

57

2019/1/8

Agenda

Minute

56

2018/12/25

Agenda

Minute

55

2018/12/17

Agenda

Minute

54

2018/12/11

Agenda

Minute

53

2018/12/4

Agenda

Minute

52

2018/11/27

Agenda

Minute

51

2018/11/20

Agenda

Minute

50

2018/11/13

Agenda

Minute

49

2018/11/6

Agenda

Minute

48

2018/10/30

Agenda

Minute

47

2018/10/23

Agenda

Minute

46

2018/10/16

Agenda

Minute

45

2018/10/9

Agenda

Schedule

Minute

44

2018/10/2

Agenda

Schedule

Minute

43

2018/9/18

Agenda

Schedule

Minute

42

2018/9/4

Agenda

Schedule

Minute

41

2018/8/28

Agenda

Schedule

Minute

40

2018/8/21

Agenda

Schedule

Minute

39

2018/8/7

Agenda

Schedule

Minute

38

2018/7/31

Agenda

Schedule

Minute

37

2018/7/24

Agenda

Schedule

Minute

36

2018/7/17

Agenda

Schedule

Minute

35

2018/7/3

Agenda

Schedule

Minute

34

2018/6/26

Agenda

Schedule

Minute

33

2018/6/19

Agenda

Schedule

Minute

32

2018/6/12

Agenda

Schedule

Minute

31

2018/6/5

Agenda

Schedule

Minute

30

2018/5/22

Agenda

Schedule

Minute

29

2018/5/8

Agenda

Schedule

Minute

28

2018/5/1

Agenda

Schedule

Minute

27

2018/4/17

Agenda

Schedule

Minute

26

2018/4/10

Agenda

Schedule

Minute

25

2018/4/3

Agenda

Schedule

Minute

24

2018/3/27

Agenda

Schedule

Minute

23

2018/3/20

Agenda

Schedule

Minute

22

2018/3/13

Agenda

Schedule

Minute

21

2018/3/6

Agenda

Schedule

Minute

20

2018/2/27

Agenda

Schedule

Minute

19

2018/2/20

Agenda

Schedule

Minute

18

2018/2/13

Agenda

Schedule

Minute

17

2018/2/6

Agenda

Schedule

Minute

16

2018/1/30

Agenda

Schedule

Minute

15

2018/1/23

Agenda

Schedule

Minute

14

2018/1/16

Agenda

Schedule

Minute

13

2018/1/9

Agenda

Schedule

Minute

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1

2017/9/19

Commissioning plan for phase1


Other meetings


Documents

Communication tools


for New members

KAGRA/Commissioning (last edited 2023-09-24 11:11:02 by miyoki)